Submits Supplemental Info Re 890809 Notice of Violation,Per Insp Rept 50-272/89-16.Investigation Concludes That No Meaningful Reason Exists for Inconsistency in Feedwater Control Valve Containment Isolation Time
ML18094B335
Person / Time
Site: Salem PSEG icon.png
Issue date: 03/08/1990
From: Crimmins T
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLR-N90043, NUDOCS 9003150408
Download: ML18094B335 (2)


Text

Public Service Electric and Gas Company Thomas M. Crimmins, Jr. Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-4700 Vice President - Nuclear Engineering MAR 0 8 1990 NLR-N90043 United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Gentlemen:

SUPPLEMENTAL INFORMATION NOTICE OF VIOLATION 272/89-16-01 SALEM GENERATING STATION UNIT NOS. 1 AND 2 FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 Public Service Electric and Gas Company (PSE&G) agreed to submit a Technical Specification change by February 28, 1990 in response to a Notice of Violation dated August 9, 1989, associated with feedwater control valve surveillance testing. The Technical Specification change will eliminate the current inconsistency in feedwater control valve Containment Isolation times between Salem Units 1 and 2.

To accomplish the above, PSE&G conducted an investigation to determine if there was a basis for different Salem Unit response times. The review concluded that there is no meaningful reason for this difference. In addition, PSE&G contracted Westinghouse Electric Corporation to perform a safety analysis to determine if an increase in feedwater control valve closure time could be supported by the current licensing basis safety analysis. Due to delays resulting from the safety evaluation comment resolution process, PSE&G is unable to meet the February 28, 1990 commitment date. The subject license change request will be submitted by March 31, 1990. Mr. T. Johnson, Senior Resident Inspector, and Mr. P. Swetland, Chief, Reactor Projects Section 2A were apprised of this situation on February 28, 1990.

Should you have any questions on this transmittal, please do not hesitate to contact us.

SiCfZ_ hL

  • (

I I

I 90031~040P

~fi~- ~Oot~ -05000272 Q

900308 PDC I

. I

I J. ' ...

  • Document Control Desk NLR-N90043 c Mr. J. c. Stone 2

Licensing Project Manager - Salem MAR O8 1990 Mr. T. Johnson Senior Resident Inspector Mr. w. T. Russell, Administrator Region I Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625