ML18093B326

From kanterella
Jump to navigation Jump to search
Supplemental Special Rept 88-5-1:on 880817,fire Barrier Penetrations Impaired for Greater than 7 Days.Complete Review of Fire Protection Program Initiated.Impaired Penetrations Resealed Utilizing Existing Procedures
ML18093B326
Person / Time
Site: Salem PSEG icon.png
Issue date: 11/30/1988
From: Miller L
Public Service Enterprise Group
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
88-5-1, NUDOCS 8812070069
Download: ML18093B326 (3)


Text

.*-

  • ~
  • e

-CPS~G Public Service Electric and Gas Company P.O. Box E Hancocks Bridge, New Jersey 08038 Salem Generating Station U. s. Nuclear Regulatory Commission Document Control Desk Washington, DC.

20555 __ _

Dear Sir:

SALEM GENERATING STATION LICENSE NO. DPR-75 DOCKET NO. 50-311 UNIT NO. 2 SUPPLEMENTAL SPECIAL REPORT-88-5-1 November 30, 1988 This supplemental Special_ Report addresses those planned fire barrier penetration impairments which were not restored to-functional status within seven (7) days.

These penetrations were impaired in support of the Unit 2 outage.

This report satisfies the reporting requirements of Technical Specification Action Statement 3.7.11.a pursuant to Technical Specification 6.9.2.

MJP:pc Distribution 8812070069 881130 PDR ADOCK 05000311 S

PDC The Energy People Sincerely yours, L. K. Miller General Manager-Salem Operations

'¢"'1,..-

1\\ 1 95-2189 (11 Mi 12-84

UNIT 2 SPECIAL REPORT 1 PLANT IDENTIFICATION:

Salem Generating Station - Unit 2 Public Service Electric & Gas Company Hancock's Bridge, New Jersey 08038 IDENTIFICATION OF OCCURRENCE:..

Fire Barrier Penetrations Impaired :For_ Greater __ Than 7 *Days Event Date1(sJ,:*::**;_-*.8/17/8:8***.:;. * *- - ** ' * *

  • Report Date:

11/30/88 CONDITIONS PRIOR TO OCCURRENCE:

N/A DESCRIPTION OF OCCURRENCE:

This report addresses the planned impairment of several fire barrier penetrations located throughout Salem Unit 2.

Th_ese impairments are in support of design modifications during the current refueling outage.

The impairments will in some cases last greater than seven days.

Therefore a Special Report is required as per Technical Specification Action Statement 3.7.11.a.

Technical*specification 3.7.11 states:

"All fire penetrations (including *cable penetration barriers, fire doors and fire dampers), in fire zone boundaries, protecting safety related areas shall be OPERABLE."

Salem Unit 2 Technical Specification Action Statement 3.7.11.a states:

"With one or more of the above required fire barrier penetrations inoperable, within one (1) hour either establish a continuous fire watch on at least one (1) side of the affected penetration, or verify the OPERABILITY of fire detectors on at least one side of the inoperable fire barrier and establish an hourly fire watch patrol.

Restore the inoperable fire barrier penetration(s) to functional status within 7 days or, in lieu of any other report required by Specification -6.9.1, prepare ~nd submit a Special Report to the Commission pursuant to Specification 6.9.2 within the next 30 days outlining the action taken, the cause of the inoperable penetration and plans and schedule for restoring the fire barrier penetration(s) to OPERABLE status."

APPARENT CAUSE OF OCCURRENCE:

As explained in prior correspondence with the Nuclear Regulatory Commission (e.g., PSE&G letter NLR-N88037, dated March 4, 1988),

PSE&G is undergoing a complete review of its Fire Protection Program.

Included in this review was the adequacy of the fire

~ UNIT 2 SPECIAL REPORT 8il5-1

  • ~ APPARENT CAUSE OF OCCURRENCE: (cont'd) barrier penetrations to meet their design function.

To ensure consistent and adequate seal design, PSE&G decided to curtail the repair of fire barrier penetration impairments until completion of the Penetration Seal Task Force review of the penetration configuration/design.

This review, due to the work scope of the task force, in some *cases h*as** taken greater *than *seven (7 )* days~

The functional integrity of the penetration fire barr.iers. ensures that fires will be confined or prevented from spreading to adjacent portions of the facility.

This design feature minimizes the possibility* of *a singl'.e **fire invo-lving *several: areas of the facility.

The fire barrier penetration seals are a passive element.in the facility. fire,;protection program ***and*'""are** subj*ect;;:~td'<"p-erio'dic inspections.

Since the penetration impairments will not be sealed within seven (7) days, this report is required as per Technical Specification 3.7.11.a pursuant to Technical Specification 6.9.2.

Where fire watches were not yet in place, they were posted in accordance with ---the requirements of Technical Specification Action Statement 3..* 7.11. a when barrier penetrations within those areas were impaired.

With the controls implemented in accordance with Technical Specification Action Statement 3.7.11.a, this practice did not involve undue risk to the health or safety of the public.

A total of 105 penetration impairments were issued* and resealed in support of the Unit 2 refueling outage in various fire barriers throughout the Unit.

Of these impaired penetrations; ten ( 1.0) were resealed within seven (7) days.

The NRC resident inspector has been periodically apprised of those fire barriers affected by this policy during the course of the Unit 2 outage.

This report satisfies the Action Statement "Special Report" requirement as per the agreement reached with the NRC on August 26, 1988 via telephone conference.

CORRECTIVE ACTION:

Impaired penetrations, caused in support of the Unit 2 outage, have been resealed utilizing existing procedures prior to the Unit restarto The hourly fire watches, in the subject areas, will continue until those fire protection concerns addressed in Unit 1 LER 272/88-013-00 and Unit 2 LER 311/88-009-06 are resolved.

MJP:pc SORC Mtg.88-105 General Manager -

Salem Operations