FENOC- 5501 North State Route 2 Oak Harbot. Ohio 43449 FirstEnergy Nuclear Operating Company 419-321 -7676 Mark B. Bezilla Vice President, Nuclear March 16,2018 L-1 8-093 Mr. Jamnes L. Cameron, Chief, Reactor Projects Branch 4 United States Nuclear Regulatory Commission Region lll 2443 Warrenville Road, Suite 210 Lisle, lL 605324352

SUBJECT:

Davis-Besse Nuclear Power Station, Unit 1 Docket Number 50-346, License Number NPF-3 Response to NRC lnspection Report 05000346/2018010. EA-18-008 The purpose of this letter is to confirm the position the FirstEnergy Nuclear Operating Company (FENOC) is taking in response to Nuclear Regulatory Commission (NRC) tnspection Report 0500034612018010 dated March 9,2018. As instructed bythe lnspection Report, I verbally notified you on March 14,2018, that FENOC is not requesting a regulatory conference on this matter, and will not be submitting a written response. FENOC understands that by declining to submit a written response or to arrange a regulatory conference, the preliminary assessment of significance will become final, and that we relinquish our right to appeal the NRC's final significance determination of the issue.

There are no regulatory commitments contained in this letter. lf there are any questions or if additional information is required, please contact Mr. Patrick J. McCloskey, Manager, Site Regulatory Compliance, at (419) 321-7274.

Sincerely, t.'

Mark B. Bezilla GMW cc: NRC Document Control Desk DB-1 NRC/NRR Project Manager DB-1 Senior Resident lnsPector Utility Radiological Safety Board RECEIVEN $,iAR 19 2O1O