Forwards Rev 1 to Inservice Testing Program,Adding Relief Request for Valves Missed During Original Applicability Review of IE Info Notice 87-01.Interim Approval of Revised 870330 Submittal,Allowing 870701 Implementation,Requested
ML18093A196
Person / Time
Site: Salem  PSEG icon.png
Issue date: 06/26/1987
From: Corbin McNeil
Public Service Enterprise Group
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML18093A197 List:
References
IEIN-87-001, IEIN-87-1, NLR-N87121, NUDOCS 8707010540
Download: ML18093A196 (2)


Text

. *

  • Public Service Electric and Gas Company Corbin A. McNeill, Jr. Public Service Electric and Gas Company P.O. Box236, Han cocks Bridge, NJ 08038 609 339-4800 Senior Vice President -

Nuclear June 26, 1987 NLR-N87121 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

INSERVICE TESTING PROGRAM REVISION AND REQUEST FOR INTERIM APPROVAL OF SECOND TEN YEAR INTERVAL IST PROGRAM SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 The subject IST program revision adds a relief request for valves 11CS21, 21CS21, 12CS21 and 22CS21 to allow testing of these valves during cold shutdown so as to avoid the improper alignment of an ECCS system during an operating condition as discussed in NRC IE Information Notice 87-01, RHR Valve Misalignment Causes Degradation of ECCS in PWRs. These valves were missed during our original review for applicability of IE IN 87-01 and were therefore not included in our March 30, 1987 submittal of the IST program for the Second Ten Year Interval for both Salem units.

We are also requesting interim approval for the March 30, 1987 submittal as amended by this revision so that the submitted IST Program may be implemented on July 1, 1987, i.e., upon expiration of the First Ten Year Interval for Salem Unit 1 on June 30, 1987. This was discussed via telecon on June 22, 1987 with Mr.

D. C. Fischer of your staff. Mr. Fischer indicated that interim approval of the submitted IST program was forthcoming and would be effective until the detailed review has been completed. The results of the review will be addressed at that time, as applicable.

  • If additional information is required, please do not hesitate to contact us.

Sincerely,

( 8707010540 97062 6 I PDR ADOCK 05000272 G PDR

" to). , * . ~

0 Document Control Desk 2 6-26-87 Attachments - Salem Unit 1 !ST Program, Second Ten Year Interval, Revision 1

- Salem Unit 2 !ST Program, Second Ten Year Interval, Revision 1 C Mr. D. C. Fischer USNRC Licensing Project Manager Mr. T. J. Kenny USNRC Senior Resident Inspector Mr. w. T. Russell, Administrator USNRC Region I Mr. D. M. Scott, Chief Bureau of Nuclear Engineering Department of Environmental Protection 380 Scotch Road Trenton, NJ 08628