Response to Request Withdrawal the Diablo Canyon Power Plant, Units 1 and 2, License Renewal Application
ML18093A115
Person / Time
Site: Diablo Canyon  
Issue date: 04/16/2018
From: George Wilson
Division of Materials and License Renewal
To: Welsch J
Pacific Gas & Electric Co
Keegan E, NRR-DMLR 415-8517
Shared Package
ML18093A114 List:
References
Download: ML18093A115 (2)


Text

April 16, 2018 Mr. James M. Welsch Vice President, Nuclear Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424

SUBJECT:

RESPONSE TO REQUEST TO WITHDRAW THE DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. Welsch:

On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am responding to your March 7, 2018 (ADAMS Accession No. ML18066A937), letter requesting to withdraw the Diablo Canyon Power Plant, Unit Nos. 1 and 2 (DCPP), license renewal application (LRA), and all associated correspondence and commitments. Per your request of June 21, 2016 (ADAMS Accession No. ML16175A561), all work on the LRA by NRC staff and its contractors was suspended. The NRC cost activity codes associated with DCPP, Units 1 and 2 will now be formally closed. Enclosed is a draft copy of the notice to be published in the Federal Register regarding the withdrawal of the LRA for DCPP, Units 1 and 2.

Pursuant to the requirements in Title 10 of the Code of Federal Regulations (10 CFR) Part 2, the Commission grants the PG&E request to withdraw the DCPP, Units 1 and 2 LRA, and all associated correspondence and commitments.

Sincerely,

/RA/

George A. Wilson Jr., Director Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

As stated cc w/encl: Distribution via Listserv

Package: ML18093A114 Letter: ML18093A115 FRN: ML18093A117

  • Concurrence via email OFFICE PM:MRPB:DMLR LA:MRPB:DMLR BC:MRPB:DMLR OGC-NLO D:DMLR NAME EKeegan YEdmonds EOesterle
  • CKanatas GWilson DATE 4/9/18 4/9/18 4/10/18 4/12/18 4/16/18