Provides Addl Info Re License Change Request 85-07 Concerning Boron Injection Tank Removal,Per 861003 Conversation.Tech Spec Change Will Not Be Implemented Until Lines Between Boric Injection & Acid Tanks Cut & Capped
ML18092B333
Person / Time
Site: Salem PSEG icon.png
Issue date: 10/24/1986
From: Corbin McNeil
Public Service Enterprise Group
To: Noonan V
Office of Nuclear Reactor Regulation
References
NLR-N86143, NUDOCS 8610280426
Download: ML18092B333 (2)


Text

Public Service Electric and Gas Company Corbin A. McNeill, Jr.

Vice President -

Public Service Electric and Gas Company P.O. Box236, Han cocks Bridge, NJ 08038 609 339-4800 Nuclear October 24, 1986 NLR-N86143 Off ice of Nuclear Reactor Regulation United States Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, MD 20014 Attention:

Mr. Vincent N. Noonan, Director PWR Project Directorate #5 Division of PWR Licensing A Gentlemen:

REQUEST FOR AMENDMENT FACILITY OPERATING LICENSE DPR-70 LICENSE CHANGE REQUEST 85-07 SALEM GENERATING STATION UNIT NO. 1 In accordance with a conversation held on 10/03/86 with Mr. B. Mann of your staff, Public Service Electric and Gas Company (PSE&G) is providing the following additional information related to License Change Request (LCR) 85-07, Boron Injection Tank (BIT) removal.

PSE&G will not implement the Technical Specification change requested in 85-07 until lines between the BIT and the Boric Acid Tank (BAT) have been cut and capped.

Additionally, the BIT boron concentration will be sampled once per calendar quarter to ensure the BIT boron concentration does not exceed the maximum Technical Specification Refueling Water Storage Tank boron concentration.

If boron concentrations exceed the RWST limit steps will be taken to return the concentration to within the limit.

The procedure addressing emergency boration of the RCS is being revised to incorporate a cautionary note after emergency boration and, per Mr. Mann's request, will be forwarded for your information after it is revised.

The emergency boration flow path is either heat traced or flushed during normal system operation.

The cautionary note will alert operators to the need to flush affected portions of the line if a system realignment is necessary immediately after emergency boration.

A safety injection during or shortly after an emergency boration will result in all safety related lines being thoroughly flushed with water at the RWST boron concentration.


=:-:A~ ~i (I

02804'")6 86102-i*

I 861

~

05000272 I

~DR ADOCK PDR

Mr. Vincent S. Noonan 2

10/24/86 In order to ensure that the environmental qualification issue related to steam superheat is adequately addressed, PSE&G will await the results of the ongoing steam superheat analysis, addressing BIT removal, prior to implementing the design changes associated with LCR 85-07.

If you should have any further questions please feel free to contact us.

C Mr. D. C. Fischer Licensing Project Manager Mr. T. J. Kenny Senior Resident Inspector Sincerely,