Similar Documents at Salem |
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML18107A4991999-08-25025 August 1999 Application for Amends to Licenses DPR-70 & DPR-75,proposing to Authorize Licensee to Perform Single Cell Charging of Connected Cells in Operable Class 1E Batteries ML18107A5141999-08-25025 August 1999 Suppl to 971114 Application for Amends to Licenses DPR-70 & DPR-75,deleting Footnotes Added as one-time Changes & Proposing Change Identified Subsequent to 971114 Submittal That Corrects Error Issued in Amend 69 for Unit 2 ML18107A4631999-07-29029 July 1999 Application for Amends to Licenses DPR-70 & DPR-75,replacing Surveillance 4.6.1.1a with Appropriate NUREG-1431 Requirements ML18107A4581999-07-23023 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Change TS Surveillance Requirement 4.8.1.1.2 D 7 by Removing Restriction to Perform Test Every 18 Months During Shutdown ML18107A4221999-07-0202 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Relocate TS 3/4.3.4 Lco,Surveillance Requirements & Bases from TS to Ufsar,Iaw GL 95-10 ML18107A3771999-06-10010 June 1999 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.6.1, Containment Integrity, by Clarifying When Verification of Primary Containment Integrity May Be Performed by Administrative Means ML18107A3571999-06-0404 June 1999 Application for Amends to Licenses DPR-70,DPR-75 & NPF-57 Re Transfer of PSEG Ownership Interests & Licensed Operating Authorities to New,Affiliated Nuclear Generating Company, PSEG Nuclear Llc.Proprietary Encls Withheld ML18107A2081999-04-14014 April 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.9.12, Fhvas, to Ensure Consistency Between TS Requirements for Fhavs & Sys Design Basis,Per NUREG-1431. Page 4 of 4 in Attachment 2 of Incoming Submittal Omitted ML18106B1571999-03-31031 March 1999 Suppl to 990115 Application for Amend to License DPR-70, Allowing Plant Operation to Continue to Thirteenth Refueling Outage (1R13),currently Scheduled to Begin on 990918 ML18106B0621999-02-0808 February 1999 Application for Amends to Licenses DPR-70 & DPR-75, Respectively.Proposed Amend Modifies ECCS Subsystems Surveillance Requirement 4.5.3.2.b by Adding Option of Providing Necessary Isolation Function When Testing ML18106B0501999-02-0202 February 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising Max Permissible Enrichment of Stored New Fuel Described in TS Section 5.6.1.1.Rept Entitled, Criticality Analysis of Salem Units 1 & 2 Fresh Fuel Racks, Encl ML18106B0221999-01-15015 January 1999 Application for Amend to License DPR-70,proposing one-time Changes to Certain Unit 1 TS Surveillance Requirements for Fuel Cycle 13,currently Scheduled to Begin on 990918 ML18106A9161998-10-12012 October 1998 Application for Amend to License DPR-75,requesting one-time Changes to Certain Unit 2 TS SR for Fuel Cycle 10.Basis for Requested Changes,Analysis Supporting No Significant Hazards Determination & Marked Up TS Pages,Encl ML18106A8921998-09-29029 September 1998 Application for Amends to Licenses DPR-72 & DPR-75,modifying TS 3/4.9.4 to Permit Use of Equivalent Methods to Obtain Containment Closure During Refueling Operations for Containment Equipment Hatch ML18106A8761998-09-17017 September 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TSs 3/4.8.2.2,3/4.8.2.4 & 3/4.8.2.6 to Address Movement of Irradiated Fuel & Deleting LCO Re Requirement to Establish Containment Integrity ML18106A8351998-08-12012 August 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS for Containment Air Locks for Salem Units 1 & 2 ML18106A7911998-07-30030 July 1998 Application for Amends to Licenses DPR-70 & DPR-75,revising Acceptance Criteria for CR Emergency Air Conditioning Sys from Maintaining CR at 1/8-inch Positive Pressure W/Respect to Adjacent Areas to Following Phrase ML18106A4271998-03-26026 March 1998 Application for Amend to License DPR-70,changing Applicability Statement from Mode 3 to Modes 1 & 2 ML18106A4221998-03-26026 March 1998 Application for Amends to Licenses DPR-70 & DPR-75, Respectively,Incorporating Note at Bottom of Salem Unit 2 T3/4.8.2 Into Salem 1 TS & Adding Asterisks to Word Inverters. ML18106A2521998-01-0808 January 1998 Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page ML18106A2111997-12-15015 December 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS to Adopt Option B of 10CFR50,App J,For Type B & C Testing & Modifying Existing TS Wording for Previous Adoption of Option B on Type a Testing ML18106A1941997-12-11011 December 1997 Application for Amend to License DPR-70,requesting one-time Exemption to Allow Containment Purging in Modes 3 & 4 ML18102B6771997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing TS Surveillance Requirements to Codify Existing Procedural Commitments for SW Accumulator Vessels ML18102B6731997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75, Correcting Editorial & Administrative Errors in Ts,Which Existed Since Initial Issuance ML18102B6611997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.8.1 Re EDG & Deleting SR 4.8.1.1.2.d.1,calling for Diesels to Be Subjected to Insp Based on Vendor Recommendations ML18102B6571997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Surveillance Requirement 4.6.2.1.b to Verify That on Recirculation Flow,Containment Spray Pumps Develop Differential Pressure of Greater than or Equal to 204 Psid ML18102B6371997-10-29029 October 1997 Application for Amend to License DPR-75,revising TS 3/4.4.6, Steam Generators, Making One Time Change to Unit 2 SG Insp Schedule to Require Next Insp within 24 Months of Mode 2 for Unit 2 Fuel Cycle 10 ML18102B6411997-10-29029 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.8.1.1.2.d.2 Proposed in Util 960925 Submittal Re EDG Testing ML18102B6471997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.7.7, Auxiliary Building Exhaust Air Filtration Sys & Bases ML18102B6441997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of TS 4.6.4.1 ML18102B6291997-10-21021 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,extending Applicability of Power Range Neutron Flux TS Trip to Require Operability & Surveillance Testing in Mode 3,when Reactor Trip Sys Breakers in Closed Position ML18102B6181997-10-14014 October 1997 Application for Amend to License DPR-70,modifying Pressure Isolation Valve Lco,Lco Action Statement,Surveillance Requirement & Table 4.4-4 to Be Consistent W/Salem Unit 2 ML18102B6061997-10-0606 October 1997 Application for Amend to License DPR-70,changing TS for LCOs 3.1.3.1, Movable Control Assemblies & 3.1.3.2.1, Position Indication Sys. ML18102B5551997-08-27027 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing Revised TS Bases Pages for TS 3.7.3, CCW Sys, to State That CCW Pumps Required to Be Operable to Meet LCO ML18102B5281997-08-19019 August 1997 Application for Amend to License DPR-75,providing Addl Operational Flexibility to Allow Orderly Resumption of Startup & Preclude Unwarranted Power Transients at Plant Unit 2 ML18102B5321997-08-18018 August 1997 Application for Amend to License DPR-75,incorporating Plant Computer (P-250) Into TS Bases for Movable Control Assemblies ML18102B4871997-08-0101 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,rewording TS Section 4.2.1 to State That Util Will Adhere to Section 7 Incidental Take Statement Approved by Natl Marine Fisheries Svc ML18102B3041997-05-14014 May 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.7.6.1.d.1 to Indicate That Specified Acceptable Filter Dp Is to Be Measured Across Filter Housing & to Reflecting Filter Dp Acceptance Value of Greater than 2.70 Wg ML18102B2611997-05-0101 May 1997 Suppl Info to Util 970211 Application for Amends to Licenses DPR-70 & DPR-75,revising TS for Chilled Water Sys - Auxiliary Bldg Subsystem.Ref to Radiation Monitoring Signal Removed from Bases Section ML18102B2581997-05-0101 May 1997 Application for Amend to License DPR-75,revising TS Section 3/4.7.7 to Reflect Extended Allowed Outage Times & Creating New TS Section 3/4.7.11 to Address Importance of Switchgear & Penetration Area Ventilation Sys ML18102B0071997-04-30030 April 1997 Application for Amends to Licenses DPR-40,DPR-56,DPR-70 & DPR-75,requesting Consent of NRC for Indirect Transfer of Control of Interest in Plants That Will Occur Under Proposed Merger ML18102B2511997-04-28028 April 1997 Submits Suppl to 970131 & 0314 Applications for Amends to Licenses DPR-70 & DPR-75,revising TS on Pressurizer Power Operated Relief Valves.Suppl Issued to State That Conclusion of NSHC Remains Valid ML18102B0221997-04-25025 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Eliminating Flow Path from RHR Sys to RCS Hot Legs as Specified in LCO 3.5.2.c.2 ML18102A9791997-04-11011 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Increasing Cw Flow to 2550 Gpm for 31 Day Surveillance Fans Started & Operated in Low Speed ML18102A8951997-03-0404 March 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying ECCS Surveillance Test Acceptance Criteria for Centrifugal Charging & SI Pumps ML18102A8491997-02-11011 February 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Addition of New TS 3/4.7.10, Chilled Water Sys ML18102A8361997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.4.3 to Ensure That Automatic Capability of Power Operated Relief Valve to Relieve Pressure Is Maintained When Valves Are Isolated by Closure of Block Valves ML18102A8021997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Rev to TS Re Containment Systems Air Temp to Ensure Representative Average Air Temp Is Measured ML18102A7861997-01-23023 January 1997 Application for Amend to License DPR-75,revising TS Bases 3/4.3.3.1 Re Radiation Monitoring Instrumentation Channel 2R41 ML18102A7361997-01-0707 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Eighteen Month Surveillance Performed to Measure RCS Total Flow Rate to Account for Necessary Plant Conditions for Performing Test in Mode 1 & Current Extended Plant Outages 1999-08-25
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML18107A4991999-08-25025 August 1999 Application for Amends to Licenses DPR-70 & DPR-75,proposing to Authorize Licensee to Perform Single Cell Charging of Connected Cells in Operable Class 1E Batteries ML18107A5141999-08-25025 August 1999 Suppl to 971114 Application for Amends to Licenses DPR-70 & DPR-75,deleting Footnotes Added as one-time Changes & Proposing Change Identified Subsequent to 971114 Submittal That Corrects Error Issued in Amend 69 for Unit 2 ML18107A4631999-07-29029 July 1999 Application for Amends to Licenses DPR-70 & DPR-75,replacing Surveillance 4.6.1.1a with Appropriate NUREG-1431 Requirements ML18107A4581999-07-23023 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Change TS Surveillance Requirement 4.8.1.1.2 D 7 by Removing Restriction to Perform Test Every 18 Months During Shutdown ML18107A4221999-07-0202 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Relocate TS 3/4.3.4 Lco,Surveillance Requirements & Bases from TS to Ufsar,Iaw GL 95-10 ML18107A3771999-06-10010 June 1999 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.6.1, Containment Integrity, by Clarifying When Verification of Primary Containment Integrity May Be Performed by Administrative Means ML18107A3571999-06-0404 June 1999 Application for Amends to Licenses DPR-70,DPR-75 & NPF-57 Re Transfer of PSEG Ownership Interests & Licensed Operating Authorities to New,Affiliated Nuclear Generating Company, PSEG Nuclear Llc.Proprietary Encls Withheld ML18107A2081999-04-14014 April 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.9.12, Fhvas, to Ensure Consistency Between TS Requirements for Fhavs & Sys Design Basis,Per NUREG-1431. Page 4 of 4 in Attachment 2 of Incoming Submittal Omitted ML18106B1571999-03-31031 March 1999 Suppl to 990115 Application for Amend to License DPR-70, Allowing Plant Operation to Continue to Thirteenth Refueling Outage (1R13),currently Scheduled to Begin on 990918 ML18106B0621999-02-0808 February 1999 Application for Amends to Licenses DPR-70 & DPR-75, Respectively.Proposed Amend Modifies ECCS Subsystems Surveillance Requirement 4.5.3.2.b by Adding Option of Providing Necessary Isolation Function When Testing ML18106B0501999-02-0202 February 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising Max Permissible Enrichment of Stored New Fuel Described in TS Section 5.6.1.1.Rept Entitled, Criticality Analysis of Salem Units 1 & 2 Fresh Fuel Racks, Encl ML18106B0221999-01-15015 January 1999 Application for Amend to License DPR-70,proposing one-time Changes to Certain Unit 1 TS Surveillance Requirements for Fuel Cycle 13,currently Scheduled to Begin on 990918 ML18106A9161998-10-12012 October 1998 Application for Amend to License DPR-75,requesting one-time Changes to Certain Unit 2 TS SR for Fuel Cycle 10.Basis for Requested Changes,Analysis Supporting No Significant Hazards Determination & Marked Up TS Pages,Encl ML18106A8921998-09-29029 September 1998 Application for Amends to Licenses DPR-72 & DPR-75,modifying TS 3/4.9.4 to Permit Use of Equivalent Methods to Obtain Containment Closure During Refueling Operations for Containment Equipment Hatch ML18106A8761998-09-17017 September 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TSs 3/4.8.2.2,3/4.8.2.4 & 3/4.8.2.6 to Address Movement of Irradiated Fuel & Deleting LCO Re Requirement to Establish Containment Integrity ML18106A8351998-08-12012 August 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS for Containment Air Locks for Salem Units 1 & 2 ML18106A7911998-07-30030 July 1998 Application for Amends to Licenses DPR-70 & DPR-75,revising Acceptance Criteria for CR Emergency Air Conditioning Sys from Maintaining CR at 1/8-inch Positive Pressure W/Respect to Adjacent Areas to Following Phrase ML18106A4271998-03-26026 March 1998 Application for Amend to License DPR-70,changing Applicability Statement from Mode 3 to Modes 1 & 2 ML18106A4221998-03-26026 March 1998 Application for Amends to Licenses DPR-70 & DPR-75, Respectively,Incorporating Note at Bottom of Salem Unit 2 T3/4.8.2 Into Salem 1 TS & Adding Asterisks to Word Inverters. ML18106A2521998-01-0808 January 1998 Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page ML18106A2111997-12-15015 December 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS to Adopt Option B of 10CFR50,App J,For Type B & C Testing & Modifying Existing TS Wording for Previous Adoption of Option B on Type a Testing ML18106A1941997-12-11011 December 1997 Application for Amend to License DPR-70,requesting one-time Exemption to Allow Containment Purging in Modes 3 & 4 ML18102B6771997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing TS Surveillance Requirements to Codify Existing Procedural Commitments for SW Accumulator Vessels ML18102B6731997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75, Correcting Editorial & Administrative Errors in Ts,Which Existed Since Initial Issuance ML18102B6611997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.8.1 Re EDG & Deleting SR 4.8.1.1.2.d.1,calling for Diesels to Be Subjected to Insp Based on Vendor Recommendations ML18102B6571997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Surveillance Requirement 4.6.2.1.b to Verify That on Recirculation Flow,Containment Spray Pumps Develop Differential Pressure of Greater than or Equal to 204 Psid ML18102B6371997-10-29029 October 1997 Application for Amend to License DPR-75,revising TS 3/4.4.6, Steam Generators, Making One Time Change to Unit 2 SG Insp Schedule to Require Next Insp within 24 Months of Mode 2 for Unit 2 Fuel Cycle 10 ML18102B6411997-10-29029 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.8.1.1.2.d.2 Proposed in Util 960925 Submittal Re EDG Testing ML18102B6471997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.7.7, Auxiliary Building Exhaust Air Filtration Sys & Bases ML18102B6441997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of TS 4.6.4.1 ML18102B6291997-10-21021 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,extending Applicability of Power Range Neutron Flux TS Trip to Require Operability & Surveillance Testing in Mode 3,when Reactor Trip Sys Breakers in Closed Position ML18102B6181997-10-14014 October 1997 Application for Amend to License DPR-70,modifying Pressure Isolation Valve Lco,Lco Action Statement,Surveillance Requirement & Table 4.4-4 to Be Consistent W/Salem Unit 2 ML18102B6061997-10-0606 October 1997 Application for Amend to License DPR-70,changing TS for LCOs 3.1.3.1, Movable Control Assemblies & 3.1.3.2.1, Position Indication Sys. ML18102B5551997-08-27027 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing Revised TS Bases Pages for TS 3.7.3, CCW Sys, to State That CCW Pumps Required to Be Operable to Meet LCO ML18102B5281997-08-19019 August 1997 Application for Amend to License DPR-75,providing Addl Operational Flexibility to Allow Orderly Resumption of Startup & Preclude Unwarranted Power Transients at Plant Unit 2 ML18102B5321997-08-18018 August 1997 Application for Amend to License DPR-75,incorporating Plant Computer (P-250) Into TS Bases for Movable Control Assemblies ML18102B4871997-08-0101 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,rewording TS Section 4.2.1 to State That Util Will Adhere to Section 7 Incidental Take Statement Approved by Natl Marine Fisheries Svc ML20148K0841997-06-0404 June 1997 Amends 194 & 177 to Licenses DPR-70 & DPR-75,respectively, Changing TSs 3.4.3 & 3.4.5, Relief Valves, to Ensure That Automatic Capability of PORVs to Relieve Pressure Is Maintained When Valves Are Isolated ML18102B3041997-05-14014 May 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.7.6.1.d.1 to Indicate That Specified Acceptable Filter Dp Is to Be Measured Across Filter Housing & to Reflecting Filter Dp Acceptance Value of Greater than 2.70 Wg ML18102B2611997-05-0101 May 1997 Suppl Info to Util 970211 Application for Amends to Licenses DPR-70 & DPR-75,revising TS for Chilled Water Sys - Auxiliary Bldg Subsystem.Ref to Radiation Monitoring Signal Removed from Bases Section ML18102B2581997-05-0101 May 1997 Application for Amend to License DPR-75,revising TS Section 3/4.7.7 to Reflect Extended Allowed Outage Times & Creating New TS Section 3/4.7.11 to Address Importance of Switchgear & Penetration Area Ventilation Sys ML18102B0071997-04-30030 April 1997 Application for Amends to Licenses DPR-40,DPR-56,DPR-70 & DPR-75,requesting Consent of NRC for Indirect Transfer of Control of Interest in Plants That Will Occur Under Proposed Merger ML18102B2511997-04-28028 April 1997 Submits Suppl to 970131 & 0314 Applications for Amends to Licenses DPR-70 & DPR-75,revising TS on Pressurizer Power Operated Relief Valves.Suppl Issued to State That Conclusion of NSHC Remains Valid ML18102B0221997-04-25025 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Eliminating Flow Path from RHR Sys to RCS Hot Legs as Specified in LCO 3.5.2.c.2 ML18102A9791997-04-11011 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Increasing Cw Flow to 2550 Gpm for 31 Day Surveillance Fans Started & Operated in Low Speed ML18102A8951997-03-0404 March 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying ECCS Surveillance Test Acceptance Criteria for Centrifugal Charging & SI Pumps ML18102A8491997-02-11011 February 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Addition of New TS 3/4.7.10, Chilled Water Sys ML18102A8361997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.4.3 to Ensure That Automatic Capability of Power Operated Relief Valve to Relieve Pressure Is Maintained When Valves Are Isolated by Closure of Block Valves ML18102A8021997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Rev to TS Re Containment Systems Air Temp to Ensure Representative Average Air Temp Is Measured ML18102A7861997-01-23023 January 1997 Application for Amend to License DPR-75,revising TS Bases 3/4.3.3.1 Re Radiation Monitoring Instrumentation Channel 2R41 1999-08-25
[Table view] |
Text
PS~G*
Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 Nuclear Department Ref: LCR-85-02 February 8, 1985 Director of Nuclear Reactor Regulation
- u. s. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Mr. Steven A. Varga, Chief Operations Reactors Branch 1 Division of Licensing Gentlemen:
REQUEST FOR AMENDMENT FACILITY OPERATING LICENSES UNIT NOS. 1 AND 2 SALEM GENERATING STATION DOCKET NOS. 50-272 AND 50-311 In accordance with the Atomic Energy Act of 1954, as amended and the regulations thereunder, we hereby transmit copies of our request for amendment and our analyses of the changes to Facility Operating Licenses DPR-70 and DPR-75 for Salem Generating Station, Unit Nos. 1 and 2.
This amendment request consists of corrections to recently issued Amendments Nos. 55 and 28 for Salem Units 1 and 2 respectively which pertained to Radiological-Environmental Technical Specifications.
In accordance with the fee requireme.nts of 10CFRl 70. 21, a check in the amount of $150.00 is enclosed.
Pursuant to the requirements of 10CFR50.91, a copy of this request for amendment has been sent to the State of New Jersey as indicated below. tA\frf~rf'\
- - ----- --- c,Y.,-~ I ";\ .J.,tv 8502200301 850208 \CJiN '\'b'}
The Energy P PDR ADOCK 05000272 \~ \))\ ~"\)\
P PDR
~".V. *o' 95-2168 (25M) 6-84
~*
Mr. Steven A. Varga 2/8/85 This submittal includes three (3) signed originals and forty (40) copies.
Sincerely, Manager - Nuclear Licensing and Regulation Enclosure C Mr. Donald c. Fischer Licensing Project Manager Mr. James Linville Senior Resident Inspector Mr. Frank Cosolito, Acting Chief Bureau of Radiation Protection Department of Environmental Protection 380 Scotch Road Trenton, New Jersey 08628 Honorable Charles M. Oberly, III Attorney General of the State of Delaware Department of Justice 820 North French Street Wilmington, Delaware 19801
Ref: LCR 85-0J STATE OF NEW JERSEY SS. COUNTY OF SALEM COUNTY OF SALEM RICHARD A. UDERITZ, being duly sworn according to law deposes and says:
I am a Vice President of Public Service Electric and Gas Company, and as such, I find the matters set forth in our Request for Amendment dated February 8, 1985, are true to the best of my knowledge, information and belief.
RICHARD A.-UDERITZ ??'
Subscribed and sworn to before me this I I U.. day of <t,;kt(u..uu";f , 198 5 Notary Public of New Jersey
.. rmr~Wi G. H!TCH~lr::n NOTARY PUBLIC OF NEW JERsr:y
,* ls My Comm
- s 1* on exp 1* res 0 My__
n ______,,* Cnn*mic*""
~_..._._ 1-. 1 *
..,_,,,_,11_,._:.*_,_:p.;.;.. *
- .'r rl'-'?:....*,_t-_,_1n""'.P~?'------
1.,,;:..;:"'°' -' ' ""1....
LCR 85-02 PROPOSED LICENSE AMENDMENT SALEM GENERATING STATION UNIT .NOS. 1 AND 2 DESCRIPTION OF CHANGE Revise Salem Unit Nos. 1 and 2 Technical Specifications to agree with the attached corrected pages from Amendments 59 and 28 for Units 1 and 2 respectively. The corrections are predominantly typographical errors; several are editorial or clarifying in nature~ finally, some material, added by recent amendm~nts has been inadvertently replaced by out-dated wording in the two year old license change which initiated Amendments_ 59 and 28. An itemized list of effected pages and a description of the changes is as follows:
- Unit Tech Spec. Page No. Section No. Justification for Change 1/2 1.7.1 1-2 Corrects two typographical spelling errors.
1 1. 25 1-5 Corrects typographical error on RATED THERMAL POWER Table 1/2 4.3-1 3/4 3-13 NOTATION ITEMS 7 through 12 remove.d from page for no apparent reason ***
original submittal contained these NOTATION items: NOTATION 8 deleted.
Table 1 3.3-12 3/4 3-59 Chemical Waste Basin is a common and and collection basin for both Salem 4.3-12 3/4 3-62 Units: R37 monitor channel readout is physically located on Unit No. 2 Control Room: such that Surveillance and Operability requirements are listed on Unit No. 2 Tables 3.3-12
. and 4.3-12 only.
LCR 85-02 Continued Unit Tech Spec. Page No. Section No. Justification for Change Table 2 3.3-12 3/4 3-54 Corrects tha MINIMUM CHANNELS and and OPERABLE to 3 for Containment fan 4.3-12 3/4 3-57 cooler Service Water monitors.
2-Rl3 A, B & C are installed on Unit No. 2; there are no D and E channels. This was a submitted typographical error which was not noticed until implementation activities began.
Table 1/2 4.3-12 3/4 3-63/ Clarifies and corrects NOTATION Notation 3-58 Nos. 1 and 2 regarding automatic isolation and control room alarm annunciation for listed conditions for Salem Units 1 and 2 as designed and built. Corrects footnote numbe.r for Unit 2 to read "The R-18 channel is an off-line channel *** "
Table 1 4.3-13 3/4 3-68 Corrects table heading typographical error which reads, "Table 3.3-13 *** "
to.read "Table 4.3-13".
Table 1/2 4. 3-13 3/ 4 3-69/ Clarifies and corrects NOTATION Notation 3-64 Nos. 1 and 2 regarding automatic isolation and control room alarm annunciation for listed conditions for Salem Units 1 and 2 as designed and built.
Table 1/2 4.11-1 3/4 11,..4 Adds footnote ( *) .to provide -a Notation principal gamma emitters LLD for and and Ce-144 of 2x1cr-6 uCi/ml which is Table realistically achievable for Table 4.11-2 3/4 11-10 4.11-1 NOTATION (c) and for Table Notation 4.11-2 NOTATION (b). Also corrected is a misspelled word in 4.11-2 (c.l) and changed item (c.2) factor of 3 to "exceeds the monitor 'warning' setpoint".
.*e LCR 85-02 Continued Unit Tech Spec. Page No. Section No. Justification for Change Table 1/2 4.11-2 3/4 11-11 Adds a line of type inadvertently Notation left out of original submittal of RETS change request, and changed factor of 3 to "exceeds the monitor
'warning' setpoint".
1/2 3/4.11.2.5 3/4 11-15 Corrects a typographical error (repeated phras~) in ACTION (a) 1 3.11.3 3/4 11-17 Corrects typographical error in word "CONTROL" 1/2 3ol2.2 3/4 12-11 Corrects ACTION references to Specification 6.9.1.11 and typographical error in footnote *.
Bases 1/2 3/4 11.2.5 B3/4 11-6 Removes reference to non-existent "automatic control features" and corrects a typographical error.
Bases 1/2 3/4 11.2.6 B3/4 11-6 Inserts missing phrase " ** ~tank's contents, the resulting total body exposure to an individual at the nearest *** " in second paragraph *.
1/2 5.3.1 5-4 Restores 11 4.05 weight percent" maximum enrichment which was incorporated by Amendments 55 and 22 for the Salem Unit Nos. 1 and 2 respectively. The recent amendments (59 and 28) were submitted as change requests prior to issuance of Amendment 55 and 22 and thus contained out-of-date enrichment limits.
1/2 6.9.1.11 6-20 Corrects typographical error in item
- (c) for Unit No. 2 and adds total phrase on Unit No. 1 for the same i tern ( c).
LCR 85-02 Continued REASON FOR CHANGE During implementation efforts which followed receipt of Amendments 59 and 28 to the Facility Operating Licenses for Salem Unit Nos. 1 and 2 respectively, a number of typographical and editorial inaccuracies were discovered that are inconsistent with the as-built Salem plants. Implementation of specifications containing these inaccuracies will have a severe impact on station operations involving entry into numerous ACTION statements. Expedited correction and clarification of these items will provide for a timely implementation of the specifications within the guidance and intent of NUREG 0472, Rev. 3, NUREG 0133, and 10CFR50, Appendix I.
SIGNIFICANT HAZARDS EVALUATION These changes are administrative, in that, they either achieve consistency in the Technical Specifications, add clarifications, or correct errors in the recently issued Amendments 59 and 28.
As an administrative change, this amendment request conforms to example (i) of Examples of Amendments That are Considered Not Likely to Involve Significant Hazards Consideration in the guidance provided by the Commission in Federal Register, 48FR14870.
~4-
ATTACHMENT 1 (Corrected pages)