Richard A. Uderitz Vice President -

Nuclear Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609 935-6010 September 20, 1983 Mr. Steven A. Varga Operator Reactors Branch #1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. varga:

IX>CKET NOS. 50-272 AND 50-311 SALEM GENERATING STATION UNIT NOS

  • 1 AND 2 SAFEGUARDS REGULATORY EFFECTIVENESS REVIEW In response to your letter dated August 17, 1983, PSE&G is com-mitted to the purchase and installation of the required search equipment by the fourth quarter of 1984 as stated in our letter of August 30, 1983.

The implementation schedule to achieve this goal will be as follows:

TASK

1.

Evaluation of available equipment.

2.

Submit purchase request.

3.

Request bids from vendors.

4.

Evaluate bids/award contract.

5.

Receive equipment.

6.

Install and test equipment.

7.

Equipment operational.

COMPLETION DATE 12/83 1/84 2/84 3/84 8/84 9/84 10/84 It is understood that with* the resolution of this matter all concerns identified in the Regulatory Effectiveness Review will have been satisfactorily addressed.

PSE&G appreciates the constructive recommendations which the RER provided.

we are gratified by the resulting improvements to our security pro-gram.

CC:

Nuclear Reactor Regulation Office of the Director NRC Resident Inspector Salem Generating Station NRC Licensing Project Manager

~3092A7D00~~90~~86~~2 I

PDR PDR F