April 3, 2018 MEMORANDUM TO:
Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors FROM:
Jordan Hoellman, Project Manager /RA/
Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors
SUBJECT:
AUDIT PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4, REQUEST FOR LICENSE AMENDMENT AND EXEMPTION REGARDING CHANGES TO THE BUILDING GAP BETWEEN THE NUCLEAR ISLAND AND ADJACENT BUILDINGS (LAR-18-002)
By letter dated February 1, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18032A359), Southern Nuclear Operating Company (SNC) requested an amendment to Combined License (COL) Numbers NPF-91 and NPF-92, for Vogtle Electric Generating Plant (VEGP) Units 3 and 4.
The requested amendment proposes changes to revise the Updated Final Safety Analysis Report in the form of departures from the incorporated plant-specific Design Control Document Tier 2* and Tier 2 information and involves related changes to plant-specific Tier 1 information, with corresponding changes to the associated COL Appendix C information. Specifically, the requested amendment proposes changes to relax the minimum gap requirement above grade between the nuclear island and the annex building/turbine building and to remove the minimum gap requirement for the radwaste building from the Inspections, Tests, Analyses and Acceptance Criteria.
NRC staff from the Geoscience and Geotechnical Engineering branch plan to conduct an audit to confirm SNCs conclusion that the differential settlement does not have adverse impact on the gaps between the nuclear island and adjacent buildings and to reach reasonable findings by reviewing VEGP Units 3 and 4 settlement survey data and related documentation.
Docket Nos.: 52-025 and 52-026
Enclosure:
Regulatory Audit Plan cc: See next page CONTACT: Jordan Hoellman, NRO/DNRL/LB4 301-415-5481
ML18089A282 NRO-008 OFFICE DNRL/LB4/PM DNRL/LB4/LA DNRL/LB4/BC NAME JHoellman RButler JDixon-Herrity DATE 4/3/18 4/2/18 4/3/18
Vogtle Units 3 & 4 Mailing List (Revised 03/13/2018) cc:
Office of the Attorney General Resident Inspector 40 Capitol Square, SW Vogtle Plant Units 3 & 4 Atlanta, GA 30334 8805 River Road Waynesboro, GA 30830 Resident Manager Oglethorpe Power Corporation Mr. Barty Simonton Alvin W. Vogtle Nuclear Plant Team Leader 7821 River Road Environmental Radiation Program Waynesboro, GA 30830 Air Protection Branch Environmental Protection Division Southern Nuclear Operating Company 4244 International Parkway, Suite 120 Document Control Coordinator Atlanta, GA 30354-3906 42 Inverness Center Parkway, Bin 237 Birmingham, AL 35242 George B. Taylor, Jr.
2100 East Exchange Pl Anne F. Appleby Atlanta, GA 30084-5336 Olgethorpe Power Corporation 2100 East Exchange Place Brian H. Whitley Tucker, GA 30084 Regulatory Affairs Director Southern Nuclear Operating Company County Commissioner 42 Inverness Center Parkway, BIN B237 Office of the County Commissioner Birmingham, AL 35242 Burke County Commission Waynesboro, GA 30830 Mr. Michael Yox Site Regulatory Affairs Director Mr. Wayne Guilfoyle Vogtle Units 3 & 4 Commissioner District 8 7825 River Road, Bin 63031 Augusta-Richmond County Commission Waynesboro, GA 30830 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Page 1 of 3
Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)
ALPUGH@southernco.com (Amanda Pugh) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)
Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis)
G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner)
JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)
John.Bozga@nrc.gov (John Bozga)
Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kmstacy@southernco.com (Kara Stacy)
KSutton@morganlewis.com (Kathryn M. Sutton)
Page 2 of 3
Vogtle Units 3 & 4 Mailing List kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler)
Marc.Pickering@hq.doe.gov (Marc Pickering) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson)
Melissa.Smith@Hq.Doe.Gov (Melissa Smith)
Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price)
MKWASHIN@southernco.com (MKWashington) mlgraves@southernco.com (Michelle Graves)
MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)
Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)
Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi)
RJB@NEI.org (Russell Bell)
Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)
Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)
TomClements329@cs.com (Tom Clements)
Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert)
Page 3 of 3
Enclosure U.S. Nuclear Regulatory Commission Audit Plan for Vogtle Electric Generating Plant Units 3 and 4 Request for License Amendment and Exemption Regarding Changes to the Building Gap Between the Nuclear Island and Adjacent Buildings (LAR-18-002)
Licensee:
Southern Nuclear Operating Company (SNC)
Licensee
Contact:
Paige Ridgway, SNC Date:
April 5, 2018 Audit Location:
Westinghouse Electric Company, LLC 11333 Woodglen Drive, Suite 202 Rockville, Maryland 20852 Purpose The staff will perform a regulatory audit to examine and evaluate technical information in order to confirm that the differential settlement at the Vogtle Electric Generating Plant (VEGP) Units 3 and 4 does not have adverse impact on the gaps between the nuclear island and adjacent buildings that support the conclusions stated in License Amendment Request (LAR)18-002, Changes to the Building Gap between the Nuclear Island and Adjacent Buildings, VEGP Units 3 and 4 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18032A359).
=
Background===
On February 1, 2018, SNC submitted VEGP Units 3 and 4 LAR-18-002 to the U.S. Nuclear Regulatory Commission (NRC). The requested amendment includes changes to revise the Updated Final Safety Analysis Report in the form of departures from the incorporated plant-specific Design Control Document Tier 2* and Tier 2 information and involves related changes to plant-specific Tier 1 information, with corresponding changes to the associated combined license Appendix C information. Specifically, the requested amendment proposes changes to relax the minimum gap requirement above grade between the nuclear island and the annex building/turbine building and to remove the minimum gap requirement for the radwaste building from the Inspections, Tests, Analyses and Acceptance Criteria.
VEGP Units 3 and 4 LAR-18-002 on pages 9 and 10 of Enclosure 1 states that differential settlement of foundations may impact the gaps between the nuclear island and adjacent buildings and that differential settlement of foundations is evaluated based on the VEGP Units 3 and 4 settlement survey data collected from the site specific settlement monitoring program for potential impact on the gap between the nuclear island and adjacent buildings. SNCs conclusion that the differential settlement does not have adverse impact on the gaps between the nuclear island and adjacent buildings is based on the settlement survey data.
The staff will perform an audit to confirm that the differential settlement does not have adverse impact on the gaps between the nuclear island and adjacent buildings by reviewing settlement
survey data demonstrating that the nuclear island and the turbine building foundations have deflected more in the center, and the annex building foundation has deflected uniformly after all construction stages.
Regulatory Bases Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix A, General Design Criterion 1, Quality standards and records, as it relates to the requirement that structures, systems, and components (SSCs) important to safety be designed, fabricated, erected, and tested to quality standards commensurate with the importance of the safety functions to be performed. It also requires that appropriate records of the design, fabrication, erection, and testing of SSCs important to safety be maintained by or under the control of the nuclear power unit licensee throughout the life of the unit.
10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Processing Plants, as it relates to quality assurance requirements for the design, fabrication, construction, and testing of those SSCs of nuclear power plants that prevent or mitigate the consequences of postulated accidents that could cause undue risk to the health and safety of the public.
The NRC staff will follow the Office of New Reactors (NRO) Office Instruction NRO-REG-108 (Revision 0), Regulatory Audits, (ADAMS Accession No. ML081910260) in performing the audit of the report cited below.
Regulatory Audit Scope
- 1. NRC staff seeks to confirm SNCs conclusion that the differential settlement does not have adverse impact on the gaps between the nuclear island and adjacent buildings at VEGP Units 3 and 4.
- 2. Staff will review the following document:
SV0-0500-XCR-800030 R0, VEGP Units 3&4 Settlement Survey Data The staff will identify additional documents, if necessary.
- 3. Audit teleconferences will be scheduled, as necessary, to clarify any information in the documents reviewed.
Audit Team Assignments The audit team comprises of the following NRC staff. These individuals will review the relevant documents that are related to the audit and are available at the time of the audit:
Zuhan Xi, Technical Reviewer, Geotechnical Engineering Pravin Patel, Technical Reviewer, Structural Engineering Jordan Hoellman, Project Manager, Licensing Branch 4 Deliverables Once the regulatory audit is completed, the audit team will issue an audit summary within 90 days.