Advises That Startup Test Program Rept Due 820111 Will Be Submitted by 820202 Due to Time Required for Data Compilation
ML18086B256
Person / Time
Site: Salem 
Issue date: 01/08/1982
From: Liden E
Public Service Enterprise Group
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8201220313
Download: ML18086B256 (1)


Text

PS~G*

Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 Phone 201/430-7000 January 8, 1982 Mr. R. C. Haynes, Regional Administrator U.S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, PA 19406

Dear Mr. Haynes:

STARTUP TEST REPORT SALEM NO. 2 CYCLE 1 LICENSE NO. DPR-75 DOCKET NO. 50-311 In accordance with Salem Generating Station Technical Specifications, Unit No. 2, section 6.9.1.3, a startup report is required to be submitted 90 days following completion of the startup test program.

The program was completed on October 13, 1981 thereby establishing a submittal date of January 11, 1982.

Due to the compilation and data reduction effort requiring more time than expected, we find that we are unable to submit the report by January 11, 1982.

It is anticipated that the report will be submitted in February 2, 1982.

Should you have any questions in this regard, do not hesitate to contact us.

,'J!ruly yours,

,/. Ma,nager ;... Nuclear

'L~c~nsiri~ and Regulation CC Director, Office of In~pecti~n; and:: Enforcement ( 36)

U. S. Nuclear Regulatory Commission Washington, DC 20555

-1 a201220318--e20-i-oa --

PDR ADOCK 05000311 P

PDR The Energy People

,,,&:i-b

~.SJ


9-5--20-01 (40~:J