Forwards Procedure Reactor Vessel Head Vent Operation, Per NUREG-0737,Item II.B.1 Requirement.Procedure Developed Per 810720 Westinghouse Owners Group Ltr WOG-81-191
ML18086B239
Person / Time
Site: Salem  PSEG icon.png
Issue date: 12/30/1981
From: Liden E
Public Service Enterprise Group
To: Varga S
Office of Nuclear Reactor Regulation
Shared Package
ML18086B240 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.1, TASK-TM NUDOCS 8201110433
Download: ML18086B239 (1)


Text

  • ~.

0 Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 Phone 201/430-7000 Mail to:

P. o. Box 570, Newark, New Jersey 07101 December 30, 1981 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, MD 20014 Attention:

Mr. Steven A. Varga, Chief Operating Reactors Branch 1 Division of Licensing Gentlemen:

PROCEDURE FOR OPERATION REACTOR VESSEL HEAD VENT SYSTEM NO. l AND 2 UNIT SALEM NUCLEAR GENERATING STATION DOCKET NO. 50-272 AND 50-311 This letter transmits to you, in its enclosure, PSE&G's pro-cedure for operation of the Reactor Vessel Head Vent System, as required by NUREG-0737, Item II.B.l.

This procedure has been developed according to the guide-lines provided by Westinghouse Owners Group letter WOG 191, dated July 20, 1981.

Following NRC approval, this procedure will be incorporated in the appropriate station procedures manual.

Until this is accomplished, the reactor vessel head vent system will remain isolated.

Should you have any questions in this regard, do not hesi-tate to contact us.

FAM:mw Very truly yours,

,/" YA

/

/'

/E. A. Liden, Manager

  • Nuclear Licensing and CC:

Mr. Leif Norrholm Senior Resident Inspector Mr. Gary c. Meyer Licensing Project Manager The Energy People

~ 8201110433 811230 PDR ADOCK 05000272 P

PDR Regulation 95*0942