Responds to Item of Concern Noted in Insp on 810629-0702. Responses to NRC Re Station Commitments Are Routed to Coordinator for Distribution to Provide Tracking Mechanism to Assure Completion of Commitments
ML18086B079
Person / Time
Site: Salem 
Issue date: 11/25/1981
From: Schneider F
Public Service Enterprise Group
To: Haynes R, Keimig R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8111300252
Download: ML18086B079 (3)


Text

c Public Service Electric and Gas Company Frederick W. Schneider 80 Park Plaza, Newark, NJ 07101 201430-7373 Mailing Address: P.O. Box 570, Newark, NJ 07101 Vice President - Production and Assistant to Senior Vice President -

Energy Supply and Engineering Mr. R. c. Haynes, Director November 25, 1981 U.S. Nuclear Regulatory Commission Off ice of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, PA 19406 Attention:

Mr. R. R. Keimig, Chief Projects Branch #2, Division of Resident and Project Inspection Gentlemen:

NRC INSPECTION NO. 50-272/81-20 SALEM GENERATING STATION UNIT NO. 1 We have reviewed the report of your inspection conducted by Mr.

J. R. White during the period of June 29 - July 2, 1981.

Our response to your item of concern identified in your letter is as follows:

Item of Concern:

Our statement in the letter to the Director, NRC Region I dated July 7, 1980, that procedural changes pertaining to performirig and documenting daily reviews for anomalous gaseous releases had been completed was inaccurate, raising the concern that management controls were not sufficient to assure the accuracy of statements made.

Reply to Item of Concern:

The procedural changes pertaining to performance and documenting daily reviews for anomalous gaseous releases had not been accom-plished at the station due to an intercompany communication breakdown regarding commitments made.

The procedural changes were implemented by August l, 1981.

To correct the breakdown of management controls that caused the inaccuracy identified, all 8111300252 811125 PDR ADOCK 05000272 G

PDR

  • Mr. R. C. Haynes, Director U.S. Nuclear Regulatory Conunission 11/25/81 responses to the NRC containing station commitments are now routed to a response coordinator for distribution to the appro-priate department head and to provide a tracking mechanism to assure completion of the conunitments.

Sincerely, CC Director, Office of Inspection and Enforcement U.S. Nuclear Regulatory Conunission Washington, D.C.

20555

STATE OF NEW JERSEY SS:

COUNTY OF ESSEX COUNTY OF ESSEX FREDERICK W. SCHNEIDER, being duly sworn according to law deposes and says:

I am a Vice President of Public Service Electric and Gas Company, and as such, I find the matters set forth in our response dated November 25, 1981, to the NRC's inspection report 50-311/81-20 are true to the best of my knowledge, information and belief.

Subscribed and sworn to before me this d.5.f/l,,,1day of )1(1.U,.--rJlh.&< _}, 1981 of New Jersey My Commission expires on

)