Responds to Generic Ltr 81-04 Re Station Blackout Events. Procedure to Address NRC Requirements Will Be Completed by 810901
ML18086A864
Person / Time
Site: Salem  PSEG icon.png
Issue date: 08/03/1981
From: Mittl R
Public Service Enterprise Group
To: Miraglia F, Varga S
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-1.C.1, TASK-TM GL-81-04, GL-81-4, NUDOCS 8108140255
Download: ML18086A864 (2)


Text

,...

PS~G Public Service Electric and Gas Company 80 Park Plaza, T16D Newark, N.J. 07101 201/430-8217 Robert L. Mittl General Manager - Licensing and Environment August 3, 1981 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Mr. Frank J. Miraglia, Chief Licensing Branch 3 Division of Licensing Mr. Steven A. Varga, Chief Operating Reactors Branch 1 Division of Licensing Gentlemen:

EMERGENCY PROCEDURES AND TRAINING FOR STATION BLACK-OUT EVENTS NO. 1 AND 2 UNITS SALEM NUCLEAR GENERATING STATION DOCKET NO. 50-272 and 50-311 As requested by your *letter of July 13, 1981, we have re-viewed the status of our response to Generic Letter 81-04, and we can offer the following information:

Development of a procedure to address the requirements of Generic Letter 81-04 is currently being pursued by the Westinghouse Owners Group. This activity is expected to lead to completion of a guideline by September 1, 1981.

This guideline will subsequently be evaluated by the Owners Group and converted into a specific plan procedure in accord-

. ance with the implementaion schedule of NUREG-0737, Item l.C.l.

The specific items of information requested in the Generic Letter (paragraphs a thru g) cannot be fully addressed until the Owners Group procedure development is concluded. The existing design and training provisions at Salem were de-veloped to address the loss of off-site a.c. power and not a total loss of a.c. power. We currently see no credible mechanisms which would result in a total loss of off-site and on-site a.c. power, since the diesel generator system is activated by a "de-based" control power system, which sup-plies the necessary 115V a.c. vital buses.

81os1402s-s--aioao3 **

PDR ADOCK 05000272 F PDR I ne Cllt:l ~y vuple I

  • '1 :'*
  • 8-3-81 Additional training for maintaining natural circulation con-ditions without a.c. power was accomplished during the startup testing of Unit No. 2. The startup tests indicated that the plant can be maintained in a safe condition for a limited time during the total loss of a.c. power. We be-lieve that our training program can efficiently address any new procedural requirements as they are developed.

Any available information on items which are not impacted by the Owners Group efforts will be supplied to you by September 1, 1981.

Should you have any questions in this regard, do not hesi-tate to contact us.

Very truly yours[

CC: Mr. Leif Norrholm Senior Resident Inspector BE9 1-2