Frederick W. Schneider Vice President Public Service Electric and Gas Company 80.Park Place Newark, N.J. 07101 201/430-7373 Production July 29,* 1980 Mr. Boyce H. Grier, Director U. s. Nuclear Regulatory Commission Office of Inspection and Enforcement Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406
Dear Mr. Grier:
NRC IE BULLETIN NO. 80-05 SUPPLEMENTAL RESPONSE NO. 1 AND 2 UNITS SALEM GENERATING STATION Pursuant to our initial response of June 6, 1980 on the subject bulletin, please be advised that a subsequent investigation has revealed. two addition.al tanks that could be subjected to conP,itions that might cause inward buckling of the tanks.
The evaluation of these tanks i~ as follows:
- 1.
Pressurizer Relief Tank (PRT).
The PRT is automatically maintained with a 3 psig nitrogen cover.
In addition~
the tank has rupture disks that are designed to protect __ _
against both excessive pressure or vacuum.
- 2.
Reactor Coo].ant Drain Tank (RCDT).
The RCDT is fitted with a tank pressure readout*on the Auxiliary Control Panel.
A low pressure.alarm (0.5 psig) is also provided on
- this panel.
In add-i tion, the tank is* designed to operate under a full vacuum. -
In summary, these two additional tanks which can contain primary fluid are adequately designed to protect against inward buckling.
If you require additional information, we will be pleased to discuss it with you.
Sincerely, Attach.
~
CC:
Office of Inspecti6n and Enforcement Division of Reactor Operations Inspection Washington, D. C.
- 1)
L. J. Norrholm NRC Resident Inspector - Salem
- -....