Requests Extension of Response Dates Re IE Bulletin 79-01. Extension Required Due to Numerous Changes & Respective Scope of Work
ML18082A137
Person / Time
Site: Salem PSEG icon.png
Issue date: 02/29/1980
From: Schneider F
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-01, IEB-79-1, NUDOCS 8004100256
Download: ML18082A137 (1)


Text

'

Frederick W. Schneider Vice President Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 201/430-7373 Production Mr. Boyce H. Grier, _Director U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Grier:

NRC IE BULLETIN NO. 79-0lB NO.

1-- UNIT SALEM GENERATING STATION February 29, 1980 PursuanL to the telecon of this date between_Mr. R. D: Evans of the PSE&G Quality Assurance Department and Mr.- R. W. McGaughy-of your office, PSE&G hereby requests an extension to the current response due dates of March 3, 1980 (bulletin items 1-3) and April 15, 1980 (bulletin items 4 & 5).

This extension is required as a result of the numerous changes and respective scope of work.

The following sch_edule has been developed by PSE&G for submittal of the subject.information:

March_ 7, 1980...;,_--_Submittal of partial response covering -bulletin items-1-3.

March l~, 1980 - Submittal of balance on items 1.& 2 and possibly --

item 3.

April 15, 1980 -

~ubmittal of partial response covering bulletin item? 4 & 5 and balance of item 3 if required.

June 2, 1980

- Submittal of all outstanding information.

If Y?~-r~quire additional information concerning the above request, we wil~ be pleased to discuss it with you.

CC:

Sincerely,

\\.___, -I tJ ~-/.__._. <----~:'\\.

NRC Office of Inspection and Enforcement

~iv~~ion of Rea.c,tor Construction Inspection was1_ington 1 D. C.