Supplemental Report of Investigation Pursuant to 10 CFR Part 20 Appendix G
ML18082A094
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 02/28/2018
From: Gerard van Noordennen
EnergySolutions
To:
Office of Nuclear Reactor Regulation, NRC Region 1
References
ES-2018-004
Download: ML18082A094 (2)


Text

',~

, ~

ENE:RGYSOLUTiONS 10 CFR 20 Appendix G ES-2018-004 February 28; 2018 U.S. NRC Region I 2100 Renaissarice Blvd., Suite 100 King of Prussia, PA 19406-2713 James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Renewed Facility Operating License No. DPR-059

Subject:

Supplemental Report of Investigation.Pursuant to 10 CFR Part 20 Appenqix G

Reference:

(1) EnergySp/u,tlons letter to U.S.iNuclear Reguh1tory: Commission Region I, Report oftnvestigation Pursuantto*:lO'CFR Part 20 Appendix G, E*S-2018-002, dated January 25, 2018

.This letter documents the closeout of an ~1}:vestigation performed wjth respect to two

tadib~ctive*\vaste 'sliipments-contained1 on t<<r'o\heavy haul fractor'trailets, **which exceeded the (2,0 day time.'limit
fc;r*notification'.ofrecei'pffroili'the disposal*faciiity:afspecified iht1'0°'CFR Part 20 Appendix G. The investigation was completed on January 15, 2018 and submitted to
the U.S. Nricl¢~atiRegulatory Commission (NRC) Region Ion Januai"y25,
*2018 (Referenc~

1). The. two shipments were traced on a dl:l,ily basis arid the locations of the shipments were known to the carrier'(Perkins), EnergySolutions (ES) and James A. FitzPatrick Nuclear Power:Plant (JAF) wast~ operations personnel:

Supplemental Report*

  • Low Pressure Rot9r Alpha (A) Shipment, ID# [[::JAF-2017-1755|JAF-2017-1755]] and Low Pressure Rotor Bravo (B) Shipment ID# [[::JAF-2017-1756|JAF-2017-1756]] were released from JAF. ori December 27, 2017 and December 28, 2017, respectively, as planned, then transported to the safe birth located 1.5 miles from JAF. Daily trace reports were provided by Perkins to ES as to the condition arid security of the shipments since their depart,ure from the safe birth until their arrival at the Clive, Utah disposal facility-with no issue*to report. The Rotor B Shipment arrived at the ES Clive;Utah disposal facility on February 20, 2018-and was offloaded and accepted for disposal on February 21, 2018. The Rotor A Shipment arrived at the ES disposal facility on Febru.ary 21,...2:018-and was offloaded and accepted for disposal.orrFebrutj,22; 2018.'*ci:,,:

.. ~,::};}:(:' , .- , ._;-.. :-.: .. :;;__ * -~-~ ., ,- -~'.*:.~::;.:*:\.ij~*:;,.~*:.5~:.:~:~

Should y~~ have* ru~y.questioris; plea~e confac(Mr. Randy'Pratt;* JA:FRa&'Wasfo Shipper at .:

(315):349-6812-br Mr. Jolin Berider,cEi:i.ergySolu/ions ProjecfManag~fat (803)(758-1818 ..

  • , *:: ;,*::;,<: . ... *i:,.r_:".':°::* ,:, . . ,*..:,'.:::::.....:.: T'c:::* i.,.<;:.:r;: *:*:*i' **;.:c:.~:Jx.,:,**, .': ::: :.,,:::*;*. : :,., :*.-.. .-, ~ G-,1J b I rv fL fc_
    • , 15*1 *Lafayette D;., Suite 201 **0a!c.Ridge, T~n11essee 378.30 ' * * * , ' ' ** (2_ G, I\)_:"\

(8~5).481-6300

  • Fax: (865) 483-32.18
  • www.energysoluti~ns.com.

~ * * "7 \ * '

EnergySolutions ES-2018-004 Page 2 of2 Sincerely, Gerard van N oordennen Vice President Regulatory Affairs cc: Ken Kolaczyk, NRC Senior Resident Inspector NRC Project Manager _

NRC Document Control Desk Joseph Pacher, Site Vice President, James A. FitzPatrick Nuclear Power Plant