PS~G*

Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Phone 201/430-7000 February 26; 1980 Director of Nuclear Reactor Regulations

u. s. Nuclear Regulatory Commission Washington; D. C.

20555 Attn:

Mr. Olan D. Parr; Chief Light Water Reactors Branch 3 Division of Project Management Gentlemen:

SINGLE DROPPED ROD EVENTS NO. 2 UNIT SALEM NUCLEAR GENERATING STATION DOCKET NO. 50-311 We are in receipt of your letter dated February 12; 1980; advising us of an interim solution for the single dropped rod event that has been agreed upon between Westinghouse and the NRC staff.

PSE&G will implement the interim solution as requested; such that (a) the plant may operate in manual control from 0 to 100% power with no changes in the current rod insertion limits, and (b) the plant may operate in automatic control from 0 to 90% power with no changes in the current rod in-sertion limits: above 90% power the D control rod bank would have to be withdrawn to 215 steps or greater.

Should you have any questions in this regard; please do not hesitate to contact us.

BJ02 The Energy People Very truly yours, R /. )J;d:ce_J; R. L. Mittl

~

General Manager -

Licensing and Environment Engineering and Construction fJ l

95-0942