Responds to IE Bulletin 79-28, Possible Malfunction of Namco Model EA180 Limit Switches at Elevated Temps. Namco EA180 Switches Have Been Installed.None Falls in Identified Group W/Faulty Gaskets
ML18081A940
Person / Time
Site: Salem  PSEG icon.png
Issue date: 12/18/1979
From: Schneider F
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-28, NUDOCS 8001240348
Download: ML18081A940 (1)


Text

Frederick W. Schneider Vice President Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 201 /430-7373 Production December 18, 1979 Mr. Boyce H. Grier, Director u.s. Nuclear Regulatory Conunission Off ice of Inspection and Enforcement Region 1 631 Park Avenue King of Prussia, PA 19406

Dear Mr. Grier:

POSSIBLE FAILURE OF NAMCO MODEL EA180 LIMIT SWITCHES AT ELEVATED TEMPERATURES NRC IE BULLETIN 79-28 SALEM GENERATING STATION UNIT NOS. 1 AND 2 An investigation into. the application of the *subject limit switches has shown that, although NAMCO EA 180 switches have been installed, none fall in the identified group with faulty upper gaske~s. This response applies.to both units of our Salem Gen-erating station.

If you* have any further questions on this matter, we will be pleased to discuss them with you.

Sincereiy, CC* Director, Office of Inspection & Enforcement USNRC Division of Reactor Operations Inspection Washington, DC 20555 I