PS~G Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Phone 201 /430-7000 December 19, 1979 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington,.D. C..

2 0555 Attention:

Mr. Darrell G. Eisenhut, Acting Director Division of Operating Reactors Off ice of Nuclear Reactor Regulations Gentlemen:

NRC REQUIREMENTS AUXILIARY FEEDWATER SYSTEMS SALEM GENERATING STATION UNIT NO. 1 DOCKET NO. 50-272 In our letter to you on November 1, 1979, responding to your letter on Auxiliary Feedwater Systems of September 21, 1979, we committed under item 7 that we would meet the AFW pump test requirement by January 1, 1980.

Due to the extended outage of Salem 1, it does not appear at this time that the unit will be in the mode which will permit the testing of the steam driven pump by January 1.

We, therefore, revise our commitment to perform the test at the earliest appropriate time after the unit returns to power operation.

ll:\\llSOF SEll\\1('E Very truly yours,

~~*

Frank P. Librizzi General Manager*-