Text
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Human Factors Verification and Validation Scenarios Revision 2 Non-Proprietary January 2018 Copyright 2018 Korea Electric Power Corporation &
Korea Hydro & Nuclear Power Co., Ltd All Rights Reserved KEPCO & KHNP
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 REVISION HISTORY Revision Date Page Description December 0 All First Issue 2014 x Terminology changed. (anticipated transient without trip (Table of -> anticipated transient without scram)
Contents) S_MES/KP-160186M Section 4.1 Major Operator Errors deleted.
R_352-8205(61) xi Terminology changed. (anticipated transient without trip (Acronym and -> anticipated transient without scram)
Abbreviations) S_MES/KP-160186M 3 Terminology changed. (anticipated transient without trip (3.1) -> anticipated transient without scram)
S_MES/KP-160186M 5, 6 Editorial correction and description for IHA added.
(3.2) R_352-8205(61) 8 Major operator errors for PRA deleted.
(4.1) R_352-8205(61) 9 Terminology changed. (anticipated transient without trip (5) -> anticipated transient without scram) 1 March 2017 S_MES/KP-160186M 12 Terminology changed. (anticipated transient without trip (5.2) -> anticipated transient without scram)
S_MES/KP-160186M A4 Description for briefing before scenario added.
(Appendix A R_352-8205(76) 1.1)
A5 Description for briefing before scenario added.
(Appendix A R_352-8205(76) 1.2)
A6 Description added to ensure failure criteria (Appendix A R_352-8205(69) 1.3.2)
A8-A9 Reference to Attachment 5 added.
(Appendix A R_352-8205(76) 1.3.2)
KEPCO & KHNP ii
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Revision Date Page Description A14-A15 Editorial correction and description for freezing (Appendix simulator deleted.
A.2.1) R_352-8205(72)
A26 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
A.3.2.3)
A46 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
A.3.3.1) R_352-8205(72)
A53 Attachment 5 Guidance when difficulties occur during (Appendix A simulation or testing added.
Attachment 5) R_352-8205(76)
A53 Attachment 5 Guidance when difficulties occur during (Appendix A simulation or testing modified.
Attachment 5) R_352-8205(76R)
B3 Description for briefing before scenario added.
(Appendix B R_352-8205(76) 1.1)
B4 Description for briefing before scenario added.
(Appendix B R_352-8205(76) 1.2)
B8 Description for briefing before scenario added.
(Appendix B R_352-8205(76) 1.3)
B11 Editorial correction and description for freezing (Appendix simulator deleted.
B.2.1) R_352-8205(72)
B17 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
B.3.2.5)
B22 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
B.3.2.5)
B25 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
B.3.3.1) R_352-8205(72)
B33-B34 Attachment 5 Guidance when difficulties occur during (Appendix B simulation or testing added.
Attachment 5) R_352-8205(76)
KEPCO & KHNP iii
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Revision Date Page Description B33-B34 Attachment 5 Guidance when difficulties occur during (Appendix B simulation or testing modified.
Attachment 5) R_352-8205(76R)
C3 Description for briefing before scenario added.
(Appendix C R_352-8205(76) 1.1)
C4 Description for briefing before scenario added.
(Appendix C R_352-8205(76) 1.2)
C8 Description for briefing before scenario added.
(Appendix C R_352-8205(76) 1.2)
C12-C13 Editorial correction and description for freezing (Appendix simulator deleted.
C.2.1) R_352-8205(72)
C20 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
C.3.2.5)
C20 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
C.3.2.6)
C29 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
C.3.3.1) R_352-8205(72)
C38 Attachment 5 Guidance when difficulties occur during (Appendix C simulation or testing added.
Attachment 5) R_352-8205(76)
C38 Attachment 5 Guidance when difficulties occur during (Appendix C simulation or testing modified.
Attachment 5) R_352-8205(76R)
D3 Description for briefing before scenario added.
(Appendix D R_352-8205(76) 1.1)
D4 Description for briefing before scenario added.
(Appendix D R_352-8205(76) 1.2)
D7 Description for briefing before scenario added.
(Appendix D R_352-8205(76) 1.3)
KEPCO & KHNP iv
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Revision Date Page Description D10-D11 Editorial correction and description for freezing (Appendix simulator deleted.
D.2.1) R_352-8205(72)
D22 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
D.3.2.2)
D33 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
D.3.3.1) R_352-8205(72)
D40 Attachment 5 Guidance when difficulties occur during (Appendix D simulation or testing added.
Attachment 5) R_352-8205(76)
D40 Attachment 5 Guidance when difficulties occur during (Appendix D simulation or testing modified.
Attachment 5) R_352-8205(76R)
E3 Description for briefing before scenario added.
(Appendix E R_352-8205(76) 1.1)
E4 Description for briefing before scenario added.
(Appendix E R_352-8205(76) 1.2)
E7 Description for briefing before scenario added.
(Appendix E R_352-8205(76) 1.3)
E11-E12 Editorial correction and description for freezing (Appendix simulator deleted.
E.2.1) R_352-8205(72)
E16 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
E.3.2.3)
E31 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
E.3.3.1) R_352-8205(72)
E39 Attachment 5 Guidance when difficulties occur during (Appendix E simulation or testing added.
Attachment 5) R_352-8205(76)
E39 Attachment 5 Guidance when difficulties occur during (Appendix E simulation or testing modified.
Attachment 5) R_352-8205(76R)
KEPCO & KHNP v
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Revision Date Page Description F3 Description for briefing before scenario added.
(Appendix F R_352-8205(76) 1.1)
F4 Description for briefing before scenario added.
(Appendix F R_352-8205(76) 1.2)
F8 Description for briefing before scenario added.
(Appendix F R_352-8205(76) 1.3)
F11-F12 Editorial correction and description for freezing (Appendix simulator deleted.
F.2.1) R_352-8205(72)
F18 Description for freezing simulator deleted.
(Appendix R_352-8205(72)
F.3.2.4)
F38-F39 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
F.3.3.1) R_352-8205(72)
F47 Attachment 5 Guidance when difficulties occur during (Appendix F simulation or testing added.
Attachment 5) R_352-8205(76)
F47 Attachment 5 Guidance when difficulties occur during (Appendix F simulation or testing modified.
Attachment 5) R_352-8205(76R)
G3 Description for briefing before scenario added.
(Appendix G R_352-8205(76) 1.1)
G4 Description for briefing before scenario added.
(Appendix G R_352-8205(76) 1.2)
G7-G8 Description for briefing before scenario added.
(Appendix G R_352-8205(76) 1.3)
G11-G12 Editorial correction and description for freezing (Appendix simulator deleted.
G.2.1) R_352-8205(72)
G20 Editorial correction and NASA-TLX added to post (Appendix exercise evaluation.
G.3.3.1) R_352-8205(72)
KEPCO & KHNP vi
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Revision Date Page Description G27 Attachment 5 Guidance when difficulties occur during (Appendix G simulation or testing added.
Attachment 5) R_352-8205(76)
G27 Attachment 5 Guidance when difficulties occur during (Appendix G simulation or testing modified.
Attachment 5) R_352-8205(76R) 2 Editorial correction (Month) and Revision No. and Issue (2.1.5) Year/Month updated CR-17-J-220 A52 Editorial correction (Deletion of bullet)
(Appendix A CR-17-J-220 Attachment 5) 2 January 2018 B33 Editorial correction (Deletion of bullet)
(Appendix B CR-17-J-220 Attachment 5)
F38 Editorial correction (Relocation of word SART)
(Appendix F CR-17-J-220 3.3.1)
KEPCO & KHNP vii
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 This document was prepared for the design certification application to the U.S. Nuclear Regulatory Commission and contains technological information that constitutes intellectual property of Korea Hydro & Nuclear Power Co., Ltd.
Copying, using, or distributing the information in this document in whole or in part is permitted only to the U.S.
Nuclear Regulatory Commission and its contractors for the purpose of reviewing design certification application materials. Other uses are strictly prohibited without the written permission of Korea Electric Power Corporation and Korea Hydro & Nuclear Power Co., Ltd.
KEPCO & KHNP viii
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 ABSTRACT The purpose of this technical report, Human Factors Verification and Validation Scenarios, is to identify the operational conditions and scenarios that are used in the human-system interface (HSI) task support verification, design verification, and integrated system validation and to provide detailed scenarios suitable for use on a full-scope simulator.
The scenarios that are described in this technical report contain a sampling of operational conditions and a summary of the Advanced Power Reactor 1400 probabilistic risk assessment.
KEPCO & KHNP ix
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 TABLE OF CONTENTS
- 1. PURPOSE............................................................................................................. 1
- 2. SCOPE ................................................................................................................. 2 2.1. Applicable Documents .................................................................................................................... 2
- 3. SAMPLING OF OPERATIONAL CONDITIONS FOR THE INTEGRATED SYSTEM VERIFICATION ..................................................................................................... 3 3.1. Plant Conditions .............................................................................................................................. 3 3.2. Types of Personnel Tasks ............................................................................................................... 5 3.3. Situational Factors or Error-Forcing Contexts ................................................................................ 7
- 4.
SUMMARY
OF THE APR1400 PROBABILISTIC RISK ASSESSMENT ................... 8 4.1. Total Core Damage Frequency of Initial Events ............................................................................. 8 4.2. Analysis of Significances ................................................................................................................ 8
- 5. APR1400 HUMAN FACTORS VERIFICATION AND VALIDATION SCENARIOS ..... 9 5.1. Small Break Loss-of-Coolant Accident with Computer-Based Procedure and Human-System Interface Display Failure ............................................................................................................... 10 5.2. Anticipated Transient without Scram with Ovation Distributed Control System Failure ............... 12 5.3. Excessive Steam Demand Event with Alarm Server Failure ........................................................ 13 5.4. Loss of All Feedwater ................................................................................................................... 14 5.5. Station Blackout ............................................................................................................................ 15 5.6. Steam Generator Tube Rupture ................................................................................................... 16 5.7. Main Control Room FIRE ............................................................................................................. 17 Appendix A Small Break Loss-of-Coolant Accident with Computer-Based Procedure and Human-System Interface Display Failure (ISV-1) ................................................ A1 Appendix B Anticipated Transient without Scram with Ovation Distributed Control System Failures (ISV-2) ................................................................................................... B1 Appendix C Excessive Steam Demand Event with Alarm Server Failure (ISV3) ..................... C1 Appendix D Loss of All Feedwater (ISV4) ............................................................................... D1 Appendix E Station Blackout (ISV5) ....................................................................................... E1 Appendix F Steam Generator Tube Rupture (ISV6) ............................................................... F1 Appendix G Main Control Room Fire (ISV7) ........................................................................... G1 KEPCO & KHNP x
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 ACRONYMS AND ABBREVIATIONS AAC alternate alternating current ACU air cleaning unit AOP abnormal operating procedure AFWP auxiliary feedwater pump ATWS anticipated transient without scram BOL beginning of life BTP Branch Technical Position CBP computer-based procedure CCW component cooling water CCWP component cooling water pump CHG charging CMF common mode failure CRS control room supervisor CVCS chemical and volume control system DBA design basis accident DCS distributed control system DG diesel generator EDG emergency diesel generator EO electrical operator EOP emergency operating procedure ESWP essential service water pump FW feedwater GOP general operating procedure HA human action HSB hot standby HSI human system interface Hx heat exchanger I&C instrumentation and control IC initial condition ISV integrated system validation L/D letdown LDP large display panel KEPCO & KHNP xi
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 LOAF loss of all feedwater LOCA loss-of-coolant accident LOOP loss of offsite power LPMS loose part monitoring system MCR main control room MD motor driven MF mitigating function MFWP main feedwater pump NRC U.S. Nuclear Regulatory Commission OER operating experience review PM preventive maintenance PME predictive maintenance engineer POP plant operating procedure PRA probabilistic risk assessment PZR pressurizer RCS reactor coolant system RO reactor operator RPCS reactor power cutback system RSR remote shutdown room RTP return to power SBO station black out SBLOCA small break loss-of-coolant accident SG steam generator SGTR steam generator tube rupture SI safety injection SIAS safety injection actuation signal SM shift manager SRO senior reactor operator STA shift technical advisor SUFWP start-up feedwater pump Tavg average temperature TD turbine driven TO turbine operator TS trade secret KEPCO & KHNP xii
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 VCT volume control tank V&V verification and validation KEPCO & KHNP xiii
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 Page intentionally blank KEPCO & KHNP xiv
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2
- 1. PURPOSE The purpose of this technical report, Human Factors Verification and Validation Scenarios, is to identify the operational conditions and scenarios that are used in the human-system interface (HSI) task support verification, design verification, and integrated system validation (ISV). The verification and validation (V&V) scenarios are detailed scenarios that are suitable for use on a full-scope simulator.
KEPCO & KHNP 1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2
- 2. SCOPE The V&V scenarios, which are described in Section 5 of this report, include the following information to reasonably assure that the important dimensions of performance are addressed and to allow the scenarios to be accurately and consistently presented in repeated trials:
Description of the scenario and any pertinent prior history necessary for personnel to understand the state of the plant at the startup of the scenario Initial conditions: Precise definition of the plants functions, processes, systems, component conditions, and performance parameters (e.g., similar to the initial conditions at shift turnover)
Events (e.g., failures) that occur during the scenario and their initiating conditions (e.g., based on time, parameter value)
Precise definition of workplace factors (e.g., environmental conditions, such as low levels of illumination)
Needs for task support (e.g., procedures, technical specifications)
Staffing level Details of communication content between control room personnel and remote personnel (e.g.,
load dispatcher via telephone)
Scripted responses for test personnel who act as plant personnel in the scenarios 2.1. Applicable Documents
- 1. NUREG-0711, Human Factors Engineering Program Review Model," Rev. 3, U.S. Nuclear Regulatory Commission, 2012.
- 2. NUREG-0800, "Standard Review Plan," Rev. 2, U.S. Nuclear Regulatory Commission, 2007.
- 3. NUREG-0700, Human-System Interface Design Review Guidelines, Rev. 2, U.S. Nuclear Regulatory Commission, 2002.
- 4. NUREG/CR-6393, Integrated System Validation: Methodology and Review Criteria, U.S. Nuclear Regulatory Commission, 1997.
- 5. APR1400-E-I-NR-14008-P, Human Factors Verification and Validation Implementation Plan, Rev. 2, KHNP, January 2018.
- 6. BTP 7-19, Guidance for Evaluation of Diversity and Defense-in-Depth in Digital Computer-Based Instrumentation and Control Systems, Rev. 6, U.S. Nuclear Regulatory Commission, July 2012.
KEPCO & KHNP 2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2
- 3. SAMPLING of OPERATIONAL CONDITIONS for THE INTEGRATED SYSTEM VERIFICATION TS 3.1. Plant Conditions TS KEPCO & KHNP 3
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 TS KEPCO & KHNP 4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 3.2. Types of Personnel Tasks TS KEPCO & KHNP 5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 TS KEPCO & KHNP 6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 3.3. Situational Factors or Error-Forcing Contexts TS KEPCO & KHNP 7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2
- 4.
SUMMARY
OF THE APR1400 PROBABILISTIC RISK ASSESSMENT 4.1. Total Core Damage Frequency of Initial Events TS 4.2. Analysis of Significances TS KEPCO & KHNP 8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2
- 5. APR1400 HUMAN FACTORS VERIFICATION AND VALIDATION SCENARIOS TS KEPCO & KHNP 9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.1. Small Break Loss-of-Coolant Accident with Computer-Based Procedure and Human-System Interface Display Failure TS KEPCO & KHNP 10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 TS KEPCO & KHNP 11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.2. Anticipated Transient without Scram with Ovation Distributed Control System Failure TS KEPCO & KHNP 12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.3. Excessive Steam Demand Event with Alarm Server Failure TS KEPCO & KHNP 13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.4. Loss of All Feedwater TS KEPCO & KHNP 14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.5. Station Blackout TS KEPCO & KHNP 15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.6. Steam Generator Tube Rupture TS KEPCO & KHNP 16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev. 2 5.7. Main Control Room FIRE TS KEPCO & KHNP 17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 APPENDIX A Small Break Loss-of-Coolant Accident with Computer-Based Procedure Failure and Human-System Interface Display Failure ISV-1 KEPCO & KHNP A1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW......................................................................................................... A3 1.1. Human Factors Verification and Validation Objectives ................................................ A3 1.2. Scenario Overview ...................................................................................................... A4 1.3. Performance Measures ............................................................................................... A5 1.3.1. Important Human Actions (IHA) ................................................................................... A5 1.3.2. Primary Tasks ............................................................................................................. A5 1.4. Other Performance Measures ..................................................................................... A9 1.5. List of Important Human Actions ............................................................................... A10 1.6. Applicable Operational Condition Sampling............................................................... A10
- 2. FACILITATORS INFORMATION ....................................................................... A12 2.1. Scenario Timeline ..................................................................................................... A12 2.2. Procedure Flow path ................................................................................................. A14 2.3. Emergency Plan ........................................................................................................ A14 2.4. Technical Specifications ............................................................................................ A14 2.5. Scenario Termination Criteria .................................................................................... A14 2.6. Anticipated Scenario Length...................................................................................... A14
- 3. SIMULATOR EXERCISE EVALUATION ............................................................ A15 3.1. Evaluation Preparation .............................................................................................. A15 3.2. Evaluation ................................................................................................................. A16 3.2.1. Event-1 Run ESW Pump 02A.................................................................................... A16 3.2.2. Event-2 SG1 Downcomer Radiation Monitor Malfunction .......................................... A17 3.2.3. Event-3 SBLOCA + SIAS Automatic Actuation Failure .............................................. A18 3.2.4. Event 4 Computer Based Procedure System (CBP) Failure ...................................... A33 3.2.5. Event-5 Loss of all Operator Console Displays and LDP with resulting RCS Cooldown at the Safety Console ................................................................................................ A41 3.3. Debrief ...................................................................................................................... A45 3.3.1. Post Exercise Evaluation ........................................................................................... A45 3.3.2. Data Acquisition ........................................................................................................ A45 ISV-1 ATTACHMENT 1 - TRENDING PARAMETERS .................................................... A46 ISV-1 ATTACHMENT 2 - SBLOCA MALFUNCTIONS .................................................... A49 ISV-1 ATTACHMENT 3 - SHIFT TURNOVER SHEET.................................................... A50 ISV-1 ATTACHMENT 4 - ANTICIPATED DIALOG ......................................................... A51 ISV-1 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING .............................................................................. A52 KEPCO & KHNP A2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 1. OVERVIEW 1.1. Human Factors Verification and Validation Objectives TS KEPCO & KHNP A3
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.2. Scenario Overview TS KEPCO & KHNP A4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.3. Performance Measures 1.3.1. Important Human Actions (IHA) TS 1.3.2. Primary Tasks TS KEPCO & KHNP A5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.4. Other Performance Measures TS KEPCO & KHNP A9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 1.5. List of Important Human Actions 1.6. Applicable Operational Condition Sampling TS KEPCO & KHNP A10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 2. FACILITATORS INFORMATION 2.1. Scenario Timeline TS KEPCO & KHNP A12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 2.2. Procedure Flow path TS 2.3. Emergency Plan TS 2.4. Technical Specifications TS TS 2.5. Scenario Termination Criteria 2.6. Anticipated Scenario Length TS KEPCO & KHNP A14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1. Evaluation Preparation TS KEPCO & KHNP A15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2. Evaluation 3.2.1. Event-1 Run ESW Pump 02A TS KEPCO & KHNP A16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.2. Event-2 SG1 Downcomer Radiation Monitor Malfunction TS KEPCO & KHNP A17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.3. Event-3 SBLOCA + SIAS Automatic Actuation Failure TS KEPCO & KHNP A18
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A19
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A20
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A21
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A22
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A23
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A24
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A25
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A26
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A27
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A28
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A29
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A30
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A31
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A32
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.4. Event 4 Computer Based Procedure System (CBP) Failure TS KEPCO & KHNP A33
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A34
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A35
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A36
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A37
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A38
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A39
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A40
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.5. Event-5 Loss of all Operator Console Displays and LDP with resulting RCS Cooldown at the Safety Console TS KEPCO & KHNP A41
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A42
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A43
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A44
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.3. Debrief TS 3.3.1. Post Exercise Evaluation 3.3.2. Data Acuisition TS KEPCO & KHNP A45
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-1 Attachment 1 - Trending Parameters TS KEPCO & KHNP A46
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A47
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP A48
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-1 Attachment 2 - SBLOCA Malfunctions TS KEPCO & KHNP A49
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-1 Attachment 3 - Shift Turnover Sheet TS KEPCO & KHNP A50
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-1 Attachment 4 - Anticipated Dialog TS KEPCO & KHNP A51
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-1 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP A52
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 APPENDIX B Anticipated Transient without Trip with Distributed Control System Failures ISV-2 KEPCO & KHNP B1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW ............................................................................................ B3 1.1. Human Factors Verification and Validation Objectives ................................................ B3 1.2. Scenario Overview ...................................................................................................... B4 1.3. Performance Measures ............................................................................................... B5 1.4. Other Performance Measures ..................................................................................... B9 1.5. List of Important Human Actions ............................................................................... B10 1.6. Applicable Operational Condition Sampling............................................................... B10
- 2. FACILITATORS INFORMATION .......................................................... B11 2.1. Scenario Timeline ..................................................................................................... B11 2.2. Procedure Flowpath .................................................................................................. B12 2.3. Emergency Plan ........................................................................................................ B12 2.4. Technical Specifications ............................................................................................ B12 2.5. Scenario Termination Criteria .................................................................................... B12 2.6. Anticipated Scenario Length...................................................................................... B12
- 3. SIMULATOR EXERCISE EVALUATION ............................................... B13 3.1. Evaluation Preparation .............................................................................................. B13 3.2. Evaluation ................................................................................................................. B13 3.2.1. Event 1 Enter Mode 2 and achieve criticality ............................................................. B13 3.2.2. Event-2 Charging Control Valve (CV-212P) Fails Close ............................................ B14 3.2.3. Event-3 Start a Turbine Driven Main Feedwater Pump (TDMFWP) and stop the Start-up Feedwater Pump (SUFWP) ....................................................................................... B16 3.2.4. EVENT-4 Pressurizer Spray Valve Fails Open With ATWT ....................................... B16 3.2.5. EVENT-5 ATWT ........................................................................................................ B17 3.2.6. EVENT-6 RCS Ovation DCS Failures (common mode failures) ................................ B24 3.3. Debrief ..................................................................................................................... B25 ISV-2 ATTACHMENT 1 - TRENDING PARAMETERS ...................................... B26 ISV-2 ATTACHMENT 2 - MALFUNCTION LIST ............................................... B29 ISV-2 ATTACHMENT 3 - SHIFT TURNOVER SHEET ...................................... B30 ISV-2 ATTACHMENT 4 - ANTICIPATED DIALOG ........................................... B31 ISV-2 ATTACHMENT 5 - GUIDEANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING ............................................................................ B33 KEPCO & KHNP B2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 1. OVERVIEW 1.1. Human Factors Verification and Validation Objectives TS KEPCO & KHNP B3
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.2. Scenario Overview TS KEPCO & KHNP B4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.3. Performance Measures TS KEPCO & KHNP B5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.4. Other Performance Measures TS KEPCO & KHNP B9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.5. List of Important Human Actions TS 1.6. Applicable Operational Condition Sampling TS KEPCO & KHNP B10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 2. FACILITATORS INFORMATION 2.1. Scenario Timeline TS KEPCO & KHNP B11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 2.2. Procedure Flowpath TS TS 2.3. Emergency Plan 2.4. Technical Specifications TS TS 2.5. Scenario Termination Criteria 2.6. Anticipated Scenario Length TS KEPCO & KHNP B12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1. Evaluation Preparation TS 3.2. Evaluation 3.2.1. Event 1 Enter Mode 2 and achieve criticality TS KEPCO & KHNP B13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.2. Event-2 Charging Control Valve (CV-212P) Fails Close TS KEPCO & KHNP B14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.3. Event-3 Start a Turbine Driven Main Feedwater Pump (TDMFWP) and stop the Start-up Feedwater Pump (SUFWP)
TS 3.2.4. EVENT-4 Pressurizer Spray Valve Fails Open With ATWT TS KEPCO & KHNP B16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.5. EVENT-5 ATWT TS KEPCO & KHNP B17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B18
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B19
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B20
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B21
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B22
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B23
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.6. EVENT-6 RCS Ovation DCS Failures (common mode failures)
TS KEPCO & KHNP B24
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.3. Debrief TS 3.3.1 Post Exercise Evaluation 3.3.2 Data Acquisition TS KEPCO & KHNP B25
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-2 ATTACHMENT 1 - TRENDING PARAMETERS TS KEPCO & KHNP B26
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B27
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B28
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS ISV-2 ATTACHMENT 2 - MALFUNCTION LIST KEPCO & KHNP B29
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-2 ATTACHMENT 3 - SHIFT TURNOVER SHEET TS KEPCO & KHNP B30
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-2 ATTACHMENT 4 - ANTICIPATED DIALOG TS KEPCO & KHNP B31
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP B32
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-2 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP B33
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 APPENDIX C Excessive Steam Demand Event with Alarm Server Failures ISV-3 KEPCO & KHNP C1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW......................................................................................................... C3 1.1 Human Factors Verification and Validation Objectives ................................................................ C3 1.2 Scenario Overview....................................................................................................................... C4 1.3 Performance Measures ............................................................................................................... C5 1.4 Other Performance Measures ..................................................................................................... C9 1.5 List of Important Human Actions ................................................................................................ C10 1.6 Applicable Operational Condition Sampling .............................................................................. C10
- 2. FACILITATORS INFORMATION ........................................................................ C12 2.1 Scenario Timeline ...................................................................................................................... C12 2.2 Procedure Flowpath................................................................................................................... C13 2.3 Emergency Plan ........................................................................................................................ C13 2.4 Technical Specifications ............................................................................................................ C13 2.5 Scenario Termination Criteria .................................................................................................... C13 2.6 Anticipated Scenario Length ...................................................................................................... C13
- 3. SIMULATOR EXERCISE EVALUATION ............................................................. C14 3.1 Evaluation Preparation .............................................................................................................. C14 3.2 Evaluation .................................................................................................................................. C14 3.2.1 Event 1 Control rod partial movement surveillance test ............................................................ C14 3.2.2 Event-2 CVCS letdown Heat Exchanger tube leak ................................................................... C15 3.2.3 Event-3 Rapid power decrease in response to LPMS alarms ................................................... C16 3.2.4 Event-4 Two MFWPs Trip with Automatic Initiation Failure of RPCS ........................................ C17 3.2.5 Event-5 Alarm Server A and B Failures ..................................................................................... C18 3.2.6 Event-6 Main Steam Line 2B Break IRC ................................................................................... C20 3.3 Debrief ....................................................................................................................................... C29 3.3.1 Post Exercise Evaluation ........................................................................................................... C29 3.3.2 Data Acquisition ......................................................................................................................... C30 ISV-3 ATTACHMENT 1 - TRENDING PARAMETERS ..................................................... C31 ISV-3 ATTACHMENT 2 - MALFUNCTION LIST ............................................................. C34 ISV-3 ATTACHMENT 3 - SHIFT TURNOVER SHEET .................................................... C35
.................................................................................................................................... C35 ISV-3 ATTACHMENT 4 - ANTICIPATED DIALOG .......................................................... C36 ISV-3 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING ........................................................................................ C38 KEPCO & KHNP C2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 1. OVERVIEW 1.1 Human Factors Verification and Validation Objectives TS KEPCO & KHNP C3
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.2 Scenario Overview TS KEPCO & KHNP C4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.3 Performance Measures TS KEPCO & KHNP C5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.4 Other Performance Measures TS KEPCO & KHNP C9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.5 List of Important Human Actions TS 1.6 Applicable Operational Condition Sampling TS KEPCO & KHNP C10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 2. FACILITATORS INFORMATION 2.1 Scenario Timeline TS KEPCO & KHNP C12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 2.2 Procedure Flowpath TS 2.3 Emergency Plan TS 2.4 Technical Specifications TS 2.5 Scenario Termination Criteria TS 2.6 Anticipated Scenario Length TS KEPCO & KHNP C13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1 Evaluation Preparation TS 3.2 Evaluation 3.2.1 Event 1 Control rod partial movement surveillance test TS KEPCO & KHNP C14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.2 Event-2 CVCS letdown Heat Exchanger tube leak TS KEPCO & KHNP C15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.3 Event-3 Rapid power decrease in response to LPMS alarms TS KEPCO & KHNP C16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.4 Event-4 Two MFWPs Trip with Automatic Initiation Failure of RPCS TS KEPCO & KHNP C17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.5 Event-5 Alarm Server A and B Failures KEPCO & KHNP C18
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C19
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.6 Event-6 Main Steam Line 2B Break IRC TS KEPCO & KHNP C20
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C21
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C22
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C23
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C24
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C25
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C26
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C27
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C28
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.3 Debrief 3.3.1 Post Exercise Evaluation KEPCO & KHNP C29
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.3.2 Data Acquisition TS KEPCO & KHNP C30
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-3 ATTACHMENT 1 - TRENDING PARAMETERS TS KEPCO & KHNP C31
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C32
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C33
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-3 ATTACHMENT 2 - MALFUNCTION LIST TS KEPCO & KHNP C34
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-3 ATTACHMENT 3 - SHIFT TURNOVER SHEET TS KEPCO & KHNP C35
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-3 ATTACHMENT 4 - ANTICIPATED DIALOG TS KEPCO & KHNP C36
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP C37
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-3 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP C38
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 APPENDIX D Loss of All Feedwater ISV-4 KEPCO & KHNP D1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW......................................................................................................... D3 1.1 Human Factors Verification and Validation Objectives ................................................................ D3 1.2 Scenario Overview....................................................................................................................... D4 1.3 Performance Measures ............................................................................................................... D5 1.4 Other Performance Measures ..................................................................................................... D8 1.5 List of Important Human Actions .................................................................................................. D9 1.6 Applicable Operational Condition Sampling ................................................................................ D9
- 2. FACILITATORS INFORMATION ........................................................................ D10 2.1 Scenario Timeline ...................................................................................................................... D10 2.2 Procedure Flowpath.................................................................................................................... D11 2.3 Emergency Plan ........................................................................................................................ D12 2.4 Technical Specifications ............................................................................................................ D12 2.5 Scenario Termination Criteria .................................................................................................... D12 2.6 Anticipated Scenario Length ...................................................................................................... D12
- 3. SIMULATOR EXERCISE EVALUATION ............................................................. D13 3.1 Evaluation Preparation .............................................................................................................. D13 3.2 Evaluation .................................................................................................................................. D14 3.2.1 Event 1 CVCS Letdown Line Leak Upstream Control Valve CV-201P/Q .................................. D14 3.2.2 Event 2 13.8kV SW-02M, SW-02N BUS FAULT ....................................................................... D16 3.2.3 Event 3 MD AFWP 2A and 2B Trip, Loss Of All Feedwater (LOAF) .......................................... D23 3.3 Debrief ....................................................................................................................................... D33 3.3.1 Post Exercise Evaluation ........................................................................................................... D33 3.3.2 Data Acquisition ......................................................................................................................... D33 ISV-4 ATTACHMENT 1 - TRENDING PARAMETERS ..................................................... D34 ISV-4 ATTACHMENT 2 - MALFUNCTION LIST ............................................................. D37 ISV-4 ATTACHMENT 3 - SHIFT TURNOVER SHEET .................................................... D38 ISV-4 ATTACHMENT 4 - ANTICIPATED DIALOG .......................................................... D39 ISV-4 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING .......................................................................................... D40 KEPCO & KHNP D2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 1. OVERVIEW 1.1 Human Factors Verification and Validation Objectives TS KEPCO & KHNP D3
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.2 Scenario Overview TS KEPCO & KHNP D4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.3 Performance Measures TS KEPCO & KHNP D5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.4 Other Performance Measures TS KEPCO & KHNP D8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.5 List of Important Human Actions TS 1.6 Applicable Operational Condition Sampling TS KEPCO & KHNP D9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 2. FACILITATORS INFORMATION 2.1 Scenario Timeline TS KEPCO & KHNP D10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 2.2 Procedure Flowpath TS KEPCO & KHNP D11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 2.3 Emergency Plan TS 2.4 Technical Specifications TS 2.5 Scenario Termination Criteria TS 2.6 Anticipated Scenario Length TS KEPCO & KHNP D12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1 Evaluation Preparation TS KEPCO & KHNP D13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2 Evaluation 3.2.1 Event 1 CVCS Letdown Line Leak Upstream Control Valve CV-201P/Q TS KEPCO & KHNP D14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.2 Event 2 13.8kV SW-02M, SW-02N BUS FAULT TS KEPCO & KHNP D16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D18
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D19
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D20
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D21
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D22
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.3 Event 3 MD AFWP 2A and 2B Trip, Loss Of All Feedwater (LOAF)
TS KEPCO & KHNP D23
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D24
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D25
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D26
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D27
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D28
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D29
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D30
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D31
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D32
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.3 Debrief 3.3.1 Post Exercise Evaluation TS 3.3.2 Data Acquisition TS KEPCO & KHNP D33
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-4 ATTACHMENT 1 - TRENDING PARAMETERS TS KEPCO & KHNP D34
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D35
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP D36
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-4 ATTACHMENT 2 - MALFUNCTION LIST TS KEPCO & KHNP D37
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-4 ATTACHMENT 3 - SHIFT TURNOVER SHEET TS KEPCO & KHNP D38
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-4 ATTACHMENT 4 - ANTICIPATED DIALOG TS KEPCO & KHNP D39
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-4 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP D40
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 APPENDIX E Station Black Out ISV-5 KEPCO & KHNP E1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW......................................................................................................... E3 1.1 Human Factors Verification and Validation Objectives .................................................................E3 1.2 Scenario Overview........................................................................................................................E4 1.3 Performance Measures ................................................................................................................E5 1.4 Other Performance Measures ......................................................................................................E8 1.5 List of Important Human Actions ...................................................................................................E9 1.6 Applicable Operational Condition Sampling .................................................................................E9
- 2. FACILITATORS INFORMATION ........................................................................ E11 2.1 Scenario Timeline ....................................................................................................................... E11 2.2 Procedure Flowpath....................................................................................................................E12 2.3 Emergency Plan .........................................................................................................................E12 2.4 Technical Specifications .............................................................................................................E12 2.5 Scenario Termination Criteria .....................................................................................................E12 2.6 Anticipated Scenario Length .......................................................................................................E12
- 3. SIMULATOR EXERCISE EVALUATION ............................................................. E13 3.1 Evaluation Preparation ...............................................................................................................E13 3.2 Evaluation ...................................................................................................................................E14 3.2.1 Event 1 Equipment Rotation -- Charging Pump from 1A to 1B ..................................................E14 3.2.2 Event-2 CVCS VCT LT-227 Fails Low ........................................................................................E14 3.2.3 Event-3 Deaerator Level Controller LIK-0318NO1 Fails Low ....................................................E15 3.2.4 EVENT-4 100% to 75% Power Operation and Severe Weather (Tornado Warning) .................E16 3.2.5 Event-5 Loss of Offsite Power ....................................................................................................E17 3.2.6 EVENT-6 Station Black Out ........................................................................................................E26 3.3 Debrief ........................................................................................................................................E31 3.3.1 Post Exercise Evaluation ............................................................................................................E31 3.3.2 Data Acquisition ..........................................................................................................................E31 ISV-5 ATTACHMENT 1 - TRENDING PARAMETERS ..................................................... E32 ISV-5 ATTACHMENT 2 - MALFUNCTION LIST ............................................................. E35 ISV-5 ATTACHMENT 3 - SHIFT TURNOVER SHEET .................................................... E36 ISV-5 ATTACHMENT 4 - ANTICIPATED DIALOG .......................................................... E37 ISV-5 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMUMLATION OR TESTING ....................................................................................... E39 KEPCO & KHNP E2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 1. OVERVIEW 1.1 Human Factors Verification and Validation Objectives TS KEPCO & KHNP E3
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.2 Scenario Overview TS KEPCO & KHNP E4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.3 Performance Measures TS KEPCO & KHNP E5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.4 Other Performance Measures TS KEPCO & KHNP E8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.5 List of Important Human Actions TS 1.6 Applicable Operational Condition Sampling TS KEPCO & KHNP E9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 2. FACILITATORS INFORMATION 2.1 Scenario Timeline TS KEPCO & KHNP E11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 2.2 Procedure Flowpath TS 2.3 Emergency Plan TS 2.4 Technical Specifications TS 2.5 Scenario Termination Criteria TS 2.6 Anticipated Scenario Length TS KEPCO & KHNP E12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1 Evaluation Preparation TS KEPCO & KHNP E13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2 Evaluation 3.2.1 Event 1 Equipment Rotation -- Charging Pump from 1A to 1B TS 3.2.2 Event-2 CVCS VCT LT-227 Fails Low TS KEPCO & KHNP E14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.3 Event-3 Deaerator Level Controller LIK-0318NO1 Fails Low TS KEPCO & KHNP E15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.4 EVENT-4 100% to 75% Power Operation and Severe Weather (Tornado Warning)
TS KEPCO & KHNP E16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.5 Event-5 Loss of Offsite Power TS KEPCO & KHNP E17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS TS KEPCO & KHNP E18
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E19
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E20
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E21
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E22
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E23
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E24
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E25
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.6 EVENT-6 Station Black Out TS KEPCO & KHNP E26
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E27
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E28
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E29
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E30
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.3 Debrief 3.3.1 Post Exercise Evaluation TS 3.3.2 Data Acquisition TS KEPCO & KHNP E31
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-5 ATTACHMENT 1 - TRENDING PARAMETERS TS KEPCO & KHNP E32
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E33
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E34
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-5 ATTACHMENT 2 - MALFUNCTION LIST TS KEPCO & KHNP E35
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-5 ATTACHMENT 3 - SHIFT TURNOVER SHEET TS KEPCO & KHNP E36
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-5 ATTACHMENT 4 - ANTICIPATED DIALOG TS KEPCO & KHNP E37
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP E38
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-5 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP E39
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 APPENDIX F Station Black Out ISV-6 KEPCO & KHNP F1
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW......................................................................................................... F3 1.1 Human Factors Verification and Validation Objectives ................................................................. F3 1.2 Scenario Overview........................................................................................................................ F4 1.3 Performance Measures ................................................................................................................ F5 1.4 Other Performance Measures ...................................................................................................... F9 1.5 List of Important Human Actions ................................................................................................. F10 1.6 Applicable Operational Condition Sampling ............................................................................... F10
- 2. FACILITATORS INFORMATION ........................................................................ F11 2.1 Scenario Timeline ....................................................................................................................... F11 2.2 Procedure Flowpath.................................................................................................................... F12 2.3 Emergency Plan ......................................................................................................................... F12 2.4 Technical Specifications ............................................................................................................. F12 2.5 Scenario Termination Criteria ..................................................................................................... F12 2.6 Anticipated Scenario Length ....................................................................................................... F12
- 3. SIMULATOR EXERCISE EVALUATION ............................................................. F13 3.1 Evaluation Preparation ............................................................................................................... F13 3.2 Evaluation ................................................................................................................................... F14 3.2.1 Event 1 Equipment Rotation -- CCWP from 1A & 1B to 2A & 2B ............................................... F14 3.2.2 Event-2 Condenser A Left Hotwell Tube Leak ............................................................................ F15 3.2.3 Event-3 100% to 75% Power Operation ..................................................................................... F16 3.2.4 EVENT-4 RRS Tavg Fail Low ..................................................................................................... F17 3.2.5 Event-5 Steam Generator Tube Leak with Secondary Radiation Monitor Failures .................... F18 3.2.6 Event 6 Steam Generator Tube Rupture (SGTR) ...................................................................... F20 3.3 Debrief ........................................................................................................................................ F38 3.3.1 Post Exercise Evaluation ............................................................................................................ F38 3.3.2 Data Acquisition .......................................................................................................................... F39 ISV-6 ATTACHMENT 1 - TRENDING PARAMETERS ..................................................... F40 ISV-6 ATTACHMENT 2 - MALFUNCTION LIST ............................................................. F43 ISV-6 ATTACHMENT 3 - SHIFT TURNOVER SHEET .................................................... F44 ISV-6 ATTACHMENT 4 - ANTICIPATED DIALOG .......................................................... F45 ISV-6 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING .......................................................................................... F47 KEPCO & KHNP F2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.2 Scenario Overview TS KEPCO & KHNP F4
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.3 Performance Measures TS KEPCO & KHNP F5
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F6
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F7
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F8
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.4 Other Performance Measures TS KEPCO & KHNP F9
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 1.5 List of Important Human Actions TS 1.6 Applicable Operational Condition Sampling TS KEPCO & KHNP F10
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 2. FACILITATORS INFORMATION 2.1 Scenario Timeline TS KEPCO & KHNP F11
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 2.2 Procedure Flowpath TS 2.3 Emergency Plan TS 2.4 Technical Specifications TS 2.5 Scenario Termination Criteria TS 2.6 Anticipated Scenario Length TS KEPCO & KHNP F12
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1 Evaluation Preparation TS KEPCO & KHNP F13
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2 Evaluation 3.2.1 Event 1 Equipment Rotation -- CCWP from 1A & 1B to 2A & 2B TS KEPCO & KHNP F14
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.2 Event-2 Condenser A Left Hotwell Tube Leak TS KEPCO & KHNP F15
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.3 Event-3 100% to 75% Power Operation TS KEPCO & KHNP F16
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.4 EVENT-4 RRS Tavg Fail Low TS KEPCO & KHNP F17
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.2.5 Event-5 Steam Generator Tube Leak with Secondary Radiation Monitor Failures TS KEPCO & KHNP F18
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F19
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 3.2.6 Event 6 Steam Generator Tube Rupture (SGTR)
TS KEPCO & KHNP F20
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F21
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F22
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F23
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F24
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F25
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F26
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F27
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F28
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F29
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F30
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F31
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS TS TS KEPCO & KHNP F32
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS TS KEPCO & KHNP F33
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F34
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F35
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F36
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F37
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.3 Debrief 3.3.1 Post Exercise Evaluation TS KEPCO & KHNP F38
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS 3.3.2 Data Acquisition TS KEPCO & KHNP F39
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-6 ATTACHMENT 1 - TRENDING PARAMETERS TS KEPCO & KHNP F40
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F41
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F42
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-6 ATTACHMENT 2 - MALFUNCTION LIST TS KEPCO & KHNP F43
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-6 ATTACHMENT 3 - SHIFT TURNOVER SHEET TS KEPCO & KHNP F44
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-6 ATTACHMENT 4 - ANTICIPATED DIALOG TS KEPCO & KHNP F45
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 TS KEPCO & KHNP F46
Non-Proprietary Human Factors Verification and Validation Scenarios APR1400-E-I-NR-14010-NP, Rev.2 ISV-6 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP F47
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 APPENDIX G Main Control Room Fire ISV-7 KEPCO & KHNP G1
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TABLE OF CONTENTS
- 1. OVERVIEW......................................................................................................... G3 1.1 Human Factors Verification and Validation Objectives ......................................................... G3 1.2 Scenario Overview..................................................................................................................... G4 1.3 Performance Measures ............................................................................................................. G5 1.4 Other Performance Measures .................................................................................................. G9 1.5 List of Important Human Actions ........................................................................................... G10 1.6 Applicable Operational Condition Sampling ........................................................................ G10
- 2. FACILITATORS INFORMATION ........................................................................ G11 2.1 Scenario Timeline .....................................................................................................................G11 2.2 Procedure Flowpath ................................................................................................................ G12 2.3 Emergency Plan ....................................................................................................................... G12 2.4 Technical Specifications ......................................................................................................... G12 2.5 Scenario Termination Criteria ................................................................................................ G12 2.6 Anticipated Scenario Length .................................................................................................. G12
- 3. SIMULATOR EXERCISE EVALUATION ............................................................. G13 3.1 Evaluation Preparation ........................................................................................................... G13 3.2 Evaluation ................................................................................................................................. G14 3.2.1 Event 1 MFWP B Vibration High and associated 100% to 75% Power Operation ................... G14 3.2.2 Event 2 Charging line leak on the Regenerative Hx Outlet IRC, with containment radiation monitors failed low ..................................................................................................................... G15 3.2.3 Event-3 Downpower from 75% to Hot Standby followed by a cooldown to Mode 4 ................. G16 3.2.4 Event-4 Steam Generator 2 FW Master controller fails low ...................................................... G17 3.2.5 Event 5 Fire in the MCR with Required RCS Cooldown from the RSR .................................... G18 3.3 Debrief ...................................................................................................................................... G20 3.3.1 Post Exercise Evaluation ........................................................................................................... G20 3.3.2 Data Acquisition ......................................................................................................................... G20 ISV-7 ATTACHMENT 1 - TRENDING PARAMETERS ..................................................... G21 ISV-7 ATTACHMENT 2 - MALFUNCTION LIST ............................................................. G24 ISV-7 ATTACHMENT 3 - SHIFT TURNOVER SHEET .................................................... G25 ISV-7 ATTACHMENT 4 - ANTICIPATED DIALOG .......................................................... G26 ISV-7 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING .......................................................................................... G27 KEPCO & KHNP G2
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2
- 1. OVERVIEW 1.1 Human Factors Verification and Validation Objectives TS KEPCO & KHNP G3
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 1.2 Scenario Overview TS KEPCO & KHNP G4
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 1.3 Performance Measures TS KEPCO & KHNP G5
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS KEPCO & KHNP G6
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS KEPCO & KHNP G7
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS KEPCO & KHNP G8
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 1.4 Other Performance Measures TS KEPCO & KHNP G9
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 1.5 List of Important Human Actions TS 1.6 Applicable Operational Condition Sampling TS KEPCO & KHNP G10
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2
- 2. FACILITATORS INFORMATION 2.1 Scenario Timeline TS KEPCO & KHNP G11
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS 2.2 Procedure Flowpath TS 2.3 Emergency Plan TS 2.4 Technical Specifications TS 2.5 Scenario Termination Criteria TS 2.6 Anticipated Scenario Length TS KEPCO & KHNP G12
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2
- 3. SIMULATOR EXERCISE EVALUATION 3.1 Evaluation Preparation TS KEPCO & KHNP G13
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 3.2 Evaluation 3.2.1 Event 1 MFWP B Vibration High and associated 100% to 75% Power Operation TS KEPCO & KHNP G14
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS 3.2.2 Event 2 Charging line leak on the Regenerative Hx Outlet IRC, with containment radiation monitors failed low TS KEPCO & KHNP G15
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS 3.2.3 Event-3 Downpower from 75% to Hot Standby followed by a cooldown to Mode 4 TS KEPCO & KHNP G16
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 3.2.4 Event-4 Steam Generator 2 FW Master controller fails low TS KEPCO & KHNP G17
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS 3.2.5 Event 5 Fire in the MCR with Required RCS Cooldown from the RSR TS KEPCO & KHNP G18
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS KEPCO & KHNP G19
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS 3.3 Debrief 3.3.1 Post Exercise Evaluation TS 3.3.2 Data Acquisition TS KEPCO & KHNP G20
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 ISV-7 ATTACHMENT 1 - TRENDING PARAMETERS TS KEPCO & KHNP G21
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS KEPCO & KHNP G22
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 TS KEPCO & KHNP G23
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 ISV-7 ATTACHMENT 2 - MALFUNCTION LIST TS KEPCO & KHNP G24
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 ISV-7 ATTACHMENT 3 - SHIFT TURNOVER SHEET TS KEPCO & KHNP G25
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 ISV-7 ATTACHMENT 4 - ANTICIPATED DIALOG TS KEPCO & KHNP G26
Non-Proprietary HF V&V Scenarios APR1400-E-I-NR-14010-NP Rev.2 ISV-7 ATTACHMENT 5 - GUIDANCE WHEN DIFFICULTIES OCCUR DURING SIMULATION OR TESTING TS KEPCO & KHNP G27