Informs NRC of Delay in Completing 25 Action Items to Comply W/Technical Positions 9.5-1,App A,Contained in . Provides Status of All 25 Items,Half of Which Are Completed
ML18078A648
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/12/1979
From: Librizzi F
Public Service Enterprise Group
To: Lear G
Office of Nuclear Reactor Regulation
References
NUDOCS 7901170219
Download: ML18078A648 (1)


Text

OPS~G Public Service Electric and Gas Company 80 Park Place Newark. N.J. 07101 Phone 201/430-7000 January 12, 1979 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Gentlemen:

Mr. George Lear, Chief Operating Reactors Branch #3 Division of Operating Reactors SALEM NUCLEAR GENERATING STATION UNIT NO. 1 ATORY O ne*,,~~ F~i E ""':;"Y REGUL

'*\\

\\) ~\\(J ~~~* LUf' DOCKET 50-272 FIRE PROTECTION EVALUATION COMPARISON TO BTP 9.5 APPENDIX A This letter is to inform you that we are unable to meet the commitment made in our September 14, 1977 letter to complete the 25 action items to comply with the Branch Technical Posi-tion 9.5-1, Appendix A.

The following is a status of the 25 action items:

1,2,3,4,5,6,13,14,15,17,20,21,24 Completed 11,12,16,18,23,25 7

8 9,10,19 22 To be completed during the refueling outage.

A unit outage is required to do the work.

A completion date cannot be given due to a strike at a vendor's plant.

Deleted -

The Dimethylamine storage tanks have been removed.

Will be completed before April 1.

Halon extinguishers are now commercially available and have been ordered.

No delivery date has been given.

Every effort will be made to complete these action items as soon as possible.

7901 1 7 0 2 \\"

The Energy People Very truly yours,

.. <..:.... :. i_ t--_.. -*-

l Frank P. Libfizzi General Manager -

Electric Production 95-2001 (400Ml 9-77