MONTHYEARML18355A9932018-12-21021 December 2018 State of Vermont Notice of Withdrawal of the States Petition for Leave to Intervene and Hearing Request ML18348B1522018-12-14014 December 2018 Third Joint Status Report ML18319A0132018-11-15015 November 2018 Second Joint Status Report ML18319A0142018-10-30030 October 2018 Amendment to Settlement Agreement ML18225A2602018-08-13013 August 2018 Joint Status Report ML18225A2612018-07-31031 July 2018 Settlement Agreement Amendment (Attachment to Joint Status Report) ML18068A2092018-03-0707 March 2018 Motion to Hold in Abeyance Action on New England Coalitions Petition for Leave to Intervene and Hearing Request in Consideration of Anticipated Withdrawal ML17212B1512017-07-31031 July 2017 New England Coalition'S Reply to Applicant'S Answer Opposing New England Coalition'S Request for Hearing and Petition for Leave to Intervene ML17205A6472017-07-24024 July 2017 Applicant'S Answer Opposing New England Coalition'S Request for Hearing and Petition for Leave to Intervene ML17198G9752017-07-17017 July 2017 State of Vermont'S Reply in Support of the State'S Petition to Intervene and Hearing Request ML17191B4892017-07-10010 July 2017 Applicants Answer Opposing Vermont Petition for Leave to Intervene ML17163A2882017-06-12012 June 2017 Applicants' Response to New England Coalition'S Request for Extension ML16131A7932016-05-10010 May 2016 Notice of Withdrawal of Daniel D. Straus ML16123A3812016-05-0202 May 2016 NRC Staff Updated Notice of Appearance for Beth Mizuno, Mitzi Young and Jeremy Wachutka ML16015A4422016-01-15015 January 2016 Answer of the States to Entergy Motion to Strike Reply of the States' Reply ML16007A6012016-01-0707 January 2016 Combined Answer of Petitioners in Opposition to Entergy'S and NRC Staff'S Motions to Strike Portions of Petitioners' Reply Brief ML15362A6462015-12-28028 December 2015 NRC Staff Motion to Strike Portions of Dec 17 2015 Reply of the State of Vermont, the Vermont Yankee Nuclear Power Corporation and Green Mountain Power Corporation ML15351A5312015-12-17017 December 2015 Reply of the Commonwealth of Massachusetts and the States of Connecticut and New Hampshire to NRC Staff'S and Entergy'S Answers to Vt'S Pet. for Rev. of Use of Vt. Yankee Decommissioning Trust Fund ML15351A5302015-12-17017 December 2015 Reply of the State of Vermont, the Vermont Yankee Nuclear Power Corporation, and Green Mountain Power Corporation in Support of Petition for Review of Use of Vermont Yankee Decommissioning Trust Fund ML15344A4942015-12-10010 December 2015 Notification of Issuance of Exemption ML15341A3002015-12-0707 December 2015 Entergy Answer Opposing November 4, 2015 Petition Filed by State of Vermont, Vermont Yankee Nuclear Power Corporation and Green Mountain Power Corporation ML15341A3612015-12-0707 December 2015 NRC Staff Answer to Vermont Petition for Review of Entergy Nuclear Operation Inc., Planned Use of the Vermont Yankee Nuclear Decommissioning Trust Fund ML15336A9152015-12-0202 December 2015 Notice of Appearance, Matthew R. Ring ML15336A7122015-12-0202 December 2015 Commission Notification of Significant Licensing Action ML15309A7592015-11-0505 November 2015 State of Vermont'S Response to NRC Staff'S Motion to Vacate LBP-15-24 ML16137A5782015-11-0404 November 2015 Petition for Review of Entergy'S Planned Use of the Vermont Yankee Decommissioning - Exhibit 3: Declaration of William Irwin, Sc.D. Chp (April 20, 2015) ML16137A5732015-11-0404 November 2015 Petition for Review of Entergy'S Planned Use of the Vermont Yankee Decommissioning - Exhibit 2: State of Vermont'S PSDAR Comments (March 6, 2015) ML16137A5542015-11-0404 November 2015 Petition of the State of Vermont, the Vermont Yankee Nuclear Power Corporation, and Green Mountain Power Corporation for Review of Entergy Nuclear Operation, Inc.'S Planned Use of the Vermont Yankee Nuclear Decommissioning Trust Fund ML15288A2222015-10-15015 October 2015 State of Vermont'S Response to Entergy'S Motion to File Reply Brief ML15275A4382015-10-0202 October 2015 State of Vermont'S Response to Entergy'S Motion to Withdraw ML15275A4402015-10-0202 October 2015 VT Exhibit 2 ML15275A4392015-10-0202 October 2015 VT Exhibit 1 ML15257A2722015-09-14014 September 2015 Notice of Intent to Participate as a Party ML15219A7122015-08-0707 August 2015 State of Vermont'S Reply in Support of Motion for Leave to File a New Contention and Add Bases and Support to Existing Contentions ML15216A5592015-08-0404 August 2015 NRC Staff Commission Notification of Issuance of EA and Fonsi for Publication in Federal Register ML15212A2812015-07-31031 July 2015 NRC Staff Answer to the State of Vermont Motion for Leave to File New and Amended Contentions ML15212A8252015-07-31031 July 2015 Entergy Answer Opposing State of Vermont New Contention V and Additional Bases for Pending Contentions I, III, and IV ML15188A5272015-07-0707 July 2015 Entergy Answer Opposing Vermont'S Appeal of the Atomic Safety and Licensing Board'S May 18, 2015 Memorandum and Order Denying Petition for Leave to Intervene and Hearing Request ML15188A5332015-07-0707 July 2015 NRC Staff Brief in Opposition to State of Vermont Appeal of LBP-15 18 ML15163A3342015-06-12012 June 2015 the State of Vermont'S Brief in Support of Notice of Appeal of Atomic Safety and Licensing Board'S May 18, 2015 Memorandum and Order Denying Petition for Leave to Intervene and Hearing Request ML15163A3332015-06-12012 June 2015 the State of Vermont'S Notice of Appeal of Atomic Safety and Licensing Board'S May 18, 2015 Memorandum and Order Denying Petition for Leave to Intervene and Hearing Request ML15142A9022015-05-22022 May 2015 State of Vermont'S Reply to NRC Staff and Entergy Answers to Petition for Leave to Intervene and Hearing Request ML15135A4982015-05-15015 May 2015 Entergy Answer Opposing Vermont Petition to Intervene ML15135A5232015-05-15015 May 2015 NRC Staff Answer to State of Vermont Petition for Leave to Intervene and Hearing Request ML15131A3982015-05-11011 May 2015 NRC Staff'S Answer to Vermont'S Notice of Supplemental Authority ML15131A3812015-05-11011 May 2015 Entergy'S Response to State of Vermont Notice of Supplemental Authority ML15126A5702015-05-0606 May 2015 Notice of Appearance for Beth Mizuno on Behalf of NRC Staff ML15126A4352015-05-0606 May 2015 Notice of Appearance for Anita Ghosh on Behalf of NRC Staff ML15126A2202015-05-0606 May 2015 Notice of Appearance for Mitzi a Young on Behalf of NRC Staff ML15097A5372015-04-0707 April 2015 Notice of Appearance Mitzi A. Young 2018-08-13
[Table view] |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE NRC HEARING OFFICER In the Matter of )
)
ENTERGY NUCLEAR VERMONT )
YANKEE, LLC AND ENTERGY ) Docket No. 50-271-LT-2 NUCLEAR OPERATIONS, INC.; )
CONSIDERATION OF APPROVAL ) March 7, 2018 OF TRANSFER OF LICENSE AND )
CONFORMING AMENDMENT )
)
(Vermont Yankee Nuclear Power Station) )
MOTION TO HOLD IN ABEYANCE ACTION ON NEW ENGLAND COALITIONS PETITION FOR LEAVE TO INTERVENE AND HEARING REQUEST IN CONSIDERATION OF ANTICIPATED WITHDRAWAL New England Coalition respectfully provides notice that because it has entered into a Settlement Agreement with the applicants for license transfer of the Vermont Yankee Nuclear Power Station, New England Coalition will, pending Vermont Public Utilities Commission (VPUC) approval of the settlement terms, withdraw its petition for leave to intervene and hearing request. A copy of the settlement has been provided by the State of Vermont in its, Notice of Anticipated Withdrawal of the States Petition for Leave to Intervene and Hearing Request, filed earlier today, March 7, 2018.
Terms of the Settlement Agreement, in New England Coalitions view, substantially alleviate the organizations concerns with the proposed license transfer or prescribe compensatory actions that will serve to mitigate anticipated risks.
The VPUC has set a hearing schedule on the matter which will terminate with technical hearings in May 2018 and New England Coalition expects that VPUC will issue a final order before July 31, 2018.
New England Coalition - 03/07/2018 - Page 2 The Settlement Agreement specifies that if the VPUC materially alters the terms of the Agreement or does not issue an order by July 31, 2018 approving the agreement substantially in its entirety, then any party may, within ten days, withdraw. If no party withdraws and the Settlement Agreement remains in place, New England Coalition will promptly submit its formal withdrawal from this proceeding.
If however the VPUC does not uphold the settlement, New England Coalition will then (within two weeks) notify the Hearing Officer and the parties and pursue its Petition for Leave to Intervene and Request for a Hearing.
Conclusion - In light of the foregoing discussion of a pending Settlement Agreement and in the interest of judicial economy, New England Coalition respectfully moves that consideration of its Petition for Leave to Intervene and Request for a Hearing be held in abeyance until such time as the VPUC issues a final order and time for any party wishing to withdraw from the Settlement Agreement has lapsed.
Respectfully submitted,
/Signed (electronically) by/
Raymond Shadis Pro Se Representative New England Coalition Post Office Box 76 Edgecomb, Maine 04556 Dated at Edgecomb, Maine this 7th day of March 2018 2
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )
)
ENTERGY NUCLEAR VERMONT )
YANKEE, LLC AND ENTERGY ) Docket No. 50-271-LT-2 NUCLEAR OPERATIONS, INC.; )
CONSIDERATION OF APPROVAL ) March 7, 2018 OF TRANSFER OF LICENSE AND )
CONFORMING AMENDMENT )
)
(Vermont Yankee Nuclear Power Station) )
CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305, I certify that copies of New England Coalitions Motion to Hold in Abeyance Action on New England Coalitions Petition for Leave to Intervene and Hearing Request in Consideration of Anticipated Withdrawal have been served upon the Parties Listed filing in the Electronic Information Exchange, the NRCs e-filing system, in the above-captioned proceeding, this Seventh day of March 2018.
/Signed (electronically) by/
Raymond Shadis Pro Se Representative New England Coalition Post Office Box 76 Edgecomb, Maine 04556 Dated at Edgecomb, Maine this 7th day of March 2018