E-Mail Dated March 2, 2018 for Document Request Response for Quad Cities Nuclear Power Station ISI Inspection (DRS-M.Domke)
ML18067A207
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 03/02/2018
From: Matthew Domke
NRC/RGN-III
To: Petersen T
Exelon Generation Co, Exelon Nuclear
References
Download: ML18067A207 (3)


Text

ADAMS Accession Number ML18067A207 From: Domke, Matthew To: "Petersen, Thomas A:(GenCo-Nuc)"

Cc: Cruz, Ramon:(GenCo-Nuc)

Subject:

RE: RE: Part 1 of 5 Emails - Quad Cities ISI Inspection Documentation Request Response Date: Friday, March 02, 2018 11:37:48 AM Attachments: RFI part B -and A_Q2R24.docx Good morning Tom, I am attaching a request to fulfill part B of the request for information letter sent November 27, 2017. These docs should be associated with WO 1360248 and hard-copied. I would like them available upon my arrival, March 14th.

Additionally, there are other supporting documents related to part A of the aforementioned request that would be most useful to me as soon as possible. These are also described by the attached. I prefer these documents in soft-copies or electronic format.

Separately, I indicated in the November 27, 2017 RFI a different inspection period than when I plan to arrive. I now intend to conduct a Wed-Wed (3/14-3/21) inspection, minus weekend dates (3/17 & 3/18), instead of the week of 3/12.

I believe my site access is current. If this is not the case, please advise.

Thank you.

Please feel free to contact me with any concerns.

Regards, Matt Domke US NRC RIII 630-829-9562 From: Petersen, Thomas A:(GenCo-Nuc) [1]

Sent: Tuesday, February 27, 2018 2:22 PM To: Domke, Matthew <Matthew.Domke@nrc.gov>

Cc: Cruz, Ramon:(GenCo-Nuc) <Ramon.Cruz@exeloncorp.com>

Subject:

[External_Sender] RE: Part 1 of 5 Emails - Quad Cities ISI Inspection Documentation Request

Response

Understand - Thank you.

From: Domke, Matthew [2]

Sent: Tuesday, February 27, 2018 1:52 PM To: Petersen, Thomas A:(GenCo-Nuc) <thomas.petersen@exeloncorp.com>

Cc: Cruz, Ramon:(GenCo-Nuc) <Ramon.Cruz@exeloncorp.com>

Subject:

[EXTERNAL] RE: Part 1 of 5 Emails - Quad Cities ISI Inspection Documentation Request

Response

Good afternoon Tom, I am recovering from an email outage today, so I just noticed your response to my requests for information.

Ill review and let you and Ramon know what else Ill need for the upcoming inspection.

I am considering arrival for the pre-outage period, but Ill confirm after review of the provided information.

Thank you.

Regards, Matt Domke US NRC 630-829-9562 From: Petersen, Thomas A:(GenCo-Nuc) [3]

Sent: Friday, February 23, 2018 10:46 AM To: Domke, Matthew <Matthew.Domke@nrc.gov>

Cc: Cruz, Ramon:(GenCo-Nuc) <Ramon.Cruz@exeloncorp.com>

Subject:

[External_Sender] Part 1 of 5 Emails - Quad Cities ISI Inspection Documentation Request

Response

7 Files attached.

Please let us know if there are any questions.

Thanks Tom Petersen Regulatory Assurance Lead Exelon Nuclear Quad Cities Generating Station 22710 206th Ave. North, Cordova, IL 61242 Office: 309-227-2825 Thomas.Petersen@exeloncorp.com This Email message and any attachment may contain information that is proprietary, legally privileged, confidential and/or subject to copyright belonging to Exelon Corporation or its affiliates ("Exelon"). This Email is intended solely for the use of the person(s) to which it is addressed. If you are not an intended recipient, or the employee or agent responsible for delivery of this Email to the intended recipient(s), you are hereby notified that any dissemination, distribution or copying of this Email is strictly prohibited. If you have received this message in error, please immediately notify the sender and permanently delete this Email and any copies. Exelon policies expressly prohibit employees from making defamatory or offensive statements and infringing any copyright or any other legal right by Email communication. Exelon will not accept any liability in respect of such communications. -

EXCIP