DCL-18-016, Withdrawal of License Amendment Request 13-02 Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. Provide Risk-Informed Extended Completion Times - Times RITSTF Initiative 48

From kanterella
(Redirected from ML18066A938)
Jump to navigation Jump to search

Withdrawal of License Amendment Request 13-02 Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. Provide Risk-Informed Extended Completion Times - Times RITSTF Initiative 48
ML18066A938
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/07/2018
From: Welsch J
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-18-016
Download: ML18066A938 (2)


Text

Pacific Gas and Electric Company*

March 7, 2018 PG&E Letter DCL-18-016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 James M. Welsch Vice President Nuclear Generation and Chief Nuclear Officer Withdrawal of License Amendment Request 13-02 Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424 805.545.3242 E*Mail: James.Welsch@pge.com 10 CFR 50.90 Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. "Provide Risk-Informed Extended Completion Times-RITSTF Initiative 48"

Reference:

PG&E Letter DCL-13-1 06, "License Amendment Request 13-02, Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, 'Provide Risk-Informed Extended Completion Times-RITSTF Initiative 48,"' dated November 25, 2013

Dear Commissioners and Staff:

On November 25, 2013, Pacific Gas and Electric Company (PG&E) requested approval (Reference 1) of a proposed amendment to Facility Operating License Nos. DPR-80 and DPR-82 for Diablo Canyon Power Plant (DCPP) Units 1 and 2, respectively. The license amendment request (LAR) proposed to adopt Risk Informed Completion Times in accordance with TSTF-505, Revision 1, "Provide Risk-Informed Extended Completion Times-RITSTF Initiative 48."

Subsequent to this submittal, numerous changes have been proposed by the NRC Staff as part of the NRC review of the pilot plant application. Additionally, a recent change in regulatory position regarding the modeling of incipient fire detection systems in the fire probabilistic risk assessment will require PG&E to perform additional analyses. Therefore, based on discussions with the NRC Staff, PG&E is hereby withdrawing LAR 13-02. However, PG&E plans to resubmit the revised LAR later in 2018.

PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.

A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Document Control Desk March 7, 2018 Page 2 PG&E Letter DCL-18-016 If you have any questions or require additional information, please contact Mr. Hossein Hamzehee at 805-545-4720.

Sincerely,

~~

James M. Welsch Vice President, Nuclear Generation and Chief Nuclear Officer mjr/4557/50467285 cc: