Forwards Insp Rept 50-255/96-17 on 970110 & Notice of Violation
ML18066A888
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/20/1997
From: Caldwell J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Thomas J. Palmisano
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18066A889 List:
References
NUDOCS 9703030112
Download: ML18066A888 (5)


See also: IR 05000255/1996017

Text

February 20*, 1997

Mr. T. Palmisano, General Manager

Palisades Nuclear Generating Plant

27780 Blue Star Memorial Highway

Covert, Ml* 49043-9530

SUBJECT:

NRC INSPECTION REPORT 50-25.5/96017(DRP)

. AND NOTICE OF VIOLATION

Dear Mr. Palmisano:

On January 10, 1997, the NRC completed an inspe_ction at your Palisades Nuclear

Generating Plant. The en~losed report presents the results of that inspection.

During this inspection period, the license~ completed a 56 day refueling outage. Following

. startup from the refueling outage, there were equipment problems that led to two forced

outages, but overall t_he inspectors viewecj the refueling outage as successful .

  • Based on the results of this inspection, the NRC has determined that a violation of NRC

requfrements occurred. The violation is cited in*the enclosed Notice of Violation (Notice),

and the circumstances surrounding it are described in detail in the enclosed report. The

violation is of concern because of your staff's failure to properly maintain adequate control

  • and over~ight of primary coolant system temperature.

.

.

.

.

.

In add~tion, we are concerned with the large number of rework items following the

refueling outage that necessitated two forced outages. We are also concerned with

adequacy of control and oversight of core operating parameters; specifically, radial peaking *

factors and primary.coolant system temperature. An unresolved item was identified

concerning adequate oversight of radial peaking factors. This item was identified by your.

staff after approximate.Iv seven hours had elapsed prior to taking appropriate action. *

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your ,respon~e. In your response, you should document

  • the specific actions taken and any additional actions you plan to prevent recurrence. Your

response may reference or include previous docketed correspondence, if the

correspondence adequately addresses the required response. After reviewing your

response to this Notice, including your proposed corrective actions *and the results of

- future inspections, the NRC will determine whether further NRC enforcement action is

necessary to ensure compliance with NRC regulatory requirements.

. .

-

.

...*

.

  • ,

9703030112 970220

PDR

ADOCK 05000255

G

PDR

. I ltml lml l1D IRDI lml lnE IRU lilll lllll ~ 1111

t

7

.

I

I

\\

1

I

1

.t

.. .>

T. Palmisano

-2-

In acc~rdance wi~h 10 CFR 2.790 of the NRC's "Rules of. Practice," a'copy ~f this letter,.

and the enclosed inspection report, will be placed in the NRC Public Document Room

(POR). *

Docket No: 50-255

License No. DPR-.20

Enclosures:

1 . Notice of Violation

2. lnspecti.on Report

No. 50-255/960.17(DRP)

Sincerely,

/s/John A. Grobe for

James L. Caldwell, Director

Division . of Reactor Projects*

  • cc w /end:

Robert A. Fenech, Vice President,

Nuclear Operations

Thomas C. Berdine, Manager, Licensing Dept.

. Service Commission

Michigan Department of

Public Health

Department of Attorney General (MU:

Docket File w /encl

DRP w/encl

. G. E. Grant, Riii* w/encl.

Project Manager, NRR w/encl

Riii Ent. Coordinator, w/en.cl

CAA 1 w/encl (E-mail)

DRS (3) w/encl

Pl.IBLIC IE-Of w/encl

OC/LFDCB w/encl

SRI Palisades, Big Rock w/encl

A. B. Beach,- w/encl

~W~ L. Axelson, w/encl

Riii PRR w/encl *

TSS w/encl

Document: R:\\insprpts\\powers\\pali\\pal96017 .drp *

To receive a copy of this document, indicate in the box .!"C" = Copy without attach/encl

"E" = *Copy with attach/encl ."N" = No copy

OFFICE

Riii

NAME

Maynen*

DATE

. 2/l /97

T. Palmisano

-2-

In accordance with 10 CFR 2.790 of the NRC's *Rules of Practice," a copy of this letter,

and the enclosed inspection report, will be placed in the NRC Public Document Room*

(PDR).

.

. Sincerely,

  • Docket No. 50-255

. License No. DPR-20

  • enclosures:

l. Notice of Violation

2. Inspection Report

No. 50-255/96017(DRP)

James L. Caldwell, Director

Division of Reactor Projects

-

cc w/encl::

Robert A. Fenech, Vice President,

Nuclear Operations

Thomas C. Berdine, Manager, Licensing Dept.

James R. Padgett, Michigan Public

Service Commi$5ion

Michigan Department of

Public Health

...

. Department of Attorney General (Ml)' . * * **

Docket File w /encl *

DRP w/encl

G. E. Grant, Riii w/encl

Project Manager, NRR W/encl

Riii Enf. Coordinator,. w /encl

CAA 1 w/encl (E-mail)

QRS (3) w/encl

PUBLIC IE-01 w/encl

OC/LFDCB w/encl *

SRI Palisades,.Big Rock w/encl

A. B. Beach, w/encl

W. L. Axelson; w/encl

Riii PRR w/encl *

TSS w/encl

Document: R:\\insprpts\\powers\\pali\\pal96017 .drp

To-receive a copy of this document, indicate in the box *c*

  • E* = Copy with attach/encl *N* = No copy. *

= Copy *without *attach/encl

. .

-

.

.

.

OFFICE

. Riii *

I

Riii

I

Riii

. ,

,

.

..

NAME

Maynen

Burgess

Grobe/Caldwell

...

DATE

21 /97

2//97

21 /97.

OFFICIAL RECORD COPY

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION 111

801 WARRENVILLE ROAD

LISLE. ILUNOIS 60532-4351

February 20, 1997

  • Mr. T. Palmisano, General Manager

Palisades Nuclear Generating Plant

- 27780 Blue Star Mf;tmorial Highway

Covert, Ml 49043-9530

SUBJECT:

NRC INSPECTION REPORT 50-255/96017(DRP)

AND NOTICE OF VIOLATION

  • Dear Mr. Palmisano:

On January 10, 1997; the NRC completed an inspection at your Palisades Nuclear

Generating Plant. The enclosed report presents the results of that inspection .. ;;

During this inspection period, the licensee completed a 56 day refueling outage.' Following

startup. from the refueling out.age, there were equipment problems that led to tw.o forced

. outages, but overall the inspectors viewed the. refueling outage as successful.

Based on the results of this inspection, the NRC has determined that *a ~iolation of NRC

requirements occurred. The. violation is cited in the enclosed Notice. of Violation (Notice),

and the circumstances surrounding it are described in detail in the enclosed report. The

violation is of concern because of your staff's failure to properly maintain adequate control

and oversight of primary coolant system temperature.

In addition; we are concerned with the large number of rework items following the

refueling outage that *necessitat~q two forced outages. We are also concerned with

adequacy of control and oversight of c*ore operating parameters, specifically, radial peaking

factors and primary coolant system temperature. An unresolved item was identified

concerning adequate oversight of radial peaking factors. This item was identified by your:

staff after approximately seven hours had elapsed prior to taking appropriate action.

You are* required to respond to this letter and should follow the instructions specified in the

~nclosed Notice when preparing your response. In your response, you should document

  • the specific actions taken and any additional actions you plan to prevent recurrence~ Your

response may reference or include previous docketed correspondence_, if the

correspondence adequately addr.esses the required response. After reviewing your

response to this Notice, including your proposed corrective actions and the results of

future irispection.s, the NRC wili determine whether. further NRC enforcement action is

necessary to en.sure compliance with NRC regulatory requirements.

.

I

T. Palmisano

-2-

  • ir; accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter;

and the enclosed inspection report, will be placed in the NRC Public Document Room

(PDR).

..

Sincerely,

~{?~

k?a'me~ L. Caldwell, Director.

Division of Reactor: Projects .

Docket No. 50-255

License No. DPR-20

Enclosures:

. 1. Notice of ViolatiOn

2. Inspection Report

No. 50-255/96017(DRP)

cc w/encl:

Robert A. Fenech, Vice President~

Nuclear Operations

Thomas C. Bordine, Manager, Licensing. Dept,

Service Commission

Michigan Department of

  • Public Health

Department of Attorney General (Ml)

- '