1 ClinchRiverESPHFNPEm Resource From:

Schiele, Raymond Joseph <rjschiele@tva.gov>

Sent:

Wednesday, February 07, 2018 9:53 AM To:

Fetter, Allen Cc:

Stout, Daniel Paul

Subject:

[External_Sender] FW: Updated Schedule for Alan Attachments:

NRC Chapter Review Schedule_Visual Aide.pptx Allen, please find attached a visual representation of the ACRS schedule for planning purposes. When would be a good time to discuss? I am in meetings most of today, but will make time Thanks Ray From: Klein, Spencer Paul Sent: Wednesday, February 07, 2018 7:30 AM To: Schiele, Raymond Joseph

Subject:

Updated Schedule for Alan See attached Spencer Klein Associate Project Manager Clinch River Small Modular Reactor Project Tennessee Valley Authority 1101 Market Street Chattanooga, TN 37402 423-751-8197 (w) 865-466-9248 (m) spklein@tva.gov NOTICE: This electronic message transmission contains information that may be TVA SENSITIVE, TVA RESTRICTED, or TVA CONFIDENTIAL. Any misuse or unauthorized disclosure can result in both civil and criminal penalties. If you are not the intended recipient, be aware that any disclosure, copying, distribution, or use of the content of this information is prohibited. If you have received this communication in error, please notify me immediately by email and delete the original message.

Hearing Identifier:

ClinchRiver_ESP_HF_NonPublic Email Number:

478 Mail Envelope Properties (0FA7144D673855418F1030CB8FBF3E612DF4AC98)

Subject:

[External_Sender] FW: Updated Schedule for Alan Sent Date:

2/7/2018 9:53:17 AM Received Date:

2/7/2018 9:59:48 AM From:

Schiele, Raymond Joseph Created By:

rjschiele@tva.gov Recipients:

"Stout, Daniel Paul" <dpstout@tva.gov>

Tracking Status: None "Fetter, Allen" <Allen.Fetter@nrc.gov>

Tracking Status: None Post Office:

TVACHAXCH8.main.tva.gov Files Size Date & Time MESSAGE 1358 2/7/2018 9:59:48 AM image001.png 2604 image002.png 1234 image003.png 1971 image004.png 1977 image005.png 2065 image006.png 2130 image007.png 1985 image008.png 1922 NRC Chapter Review Schedule_Visual Aide.pptx 8380447 Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

NRC Issues ESP NRC Advanced Safety Evaluation Report Review Schedule PSER &

RAIs ACRS Meetings FSER Phase B Complete SER w/ no OIs Mandatory ASLB Hearing 2016 2017 2018 2019 2020 ESPA Submitted 5-12-16 2.1 & 2.2 Geography and Demography and Nearby Industrial, Transportation, and Military Facilities 2.4 Hydrologic Engineering 2.5 Geology, Seismology, and Geotechnical Engineering 3.5.1.6 Aircraft Hazards 11.4.1 & 11.4.2 Radiological Effluent Releases (Gaseous & Liquid) 13.6 Physical Security 15.0.3 Radiological Consequences of DBAs 17.0 Quality Assurance 2.3 Meteorology 13.3 Emergency Planning 13.3.4.3.1 Methodology for EPZ Sizing Phase B PM, LA, QTE, BC, OGC concurrence (90 days +/-)

(10/20/18 -T)

Phase A (8/4/17 - A)

Phase C (3/26/19 - T)

Phase D (8/17/19 - T)

PLACE THE TITLE OF THE PRESENTATION HERE l 2 Chapter Section(s)

TVA Tech Reviewer(s)

TVA Team Lead NRC Tech Reviewer(s),

Office/Division NRC Team Lead Interface Chapter(s)

PM SER Sections, ADAMS Package Number(s)

Phase B Advanced SE w/ no OIs (Tech Branch BC transmittal date to DNRL)

PM, LA, QTE, BC, OGC concurrence (90 days +/-)

2.1: Geography and Demography 2.2: Nearby Industrial, Transportation, and Military Facilities Enercon/Bechtel John Thomas/Alex Young Seshagiri Tammara (Rao),

NRO/DSEA Michael Dudek Allen Fetter Phase A - ML17116A283 Phase B - ML17289B043 2/22/2018 (EPM) 2.3: Meteorology Enercon John Thomas/Alex Young Kevin Quinlan, Mike Mazaika, &

Jason White, NRO/DSEA Brad Harvey 11.4.2, 13.3, &

15.0.3 Mallecia Sutton Phase A - ML17215A906 Phase B - ML17289B135 5/21/2018 (EPM) 2.4: Hydrologic Engineering BWSC/Bechtel D. Lundy/John Thomas/Alex Young Joe Giacinto, Yuan Cheng, &

Steve Breithaupt, NRO/DSEA Laurel Bauer (acting) 11.4 Mallecia Sutton Phase A - ML17215A906 Phase B - ML17289B135 5/21/2018 (EPM) 2.5: Geology, Seismology, and Geotechnical Engineering Bechtel/Rizzo/

URS Wally Justice Gerry Stirewalt, David Heeszel, Ricardo Rodriguez, & Weijun Wang, NRO/DSEA Laurel Bauer (acting) 2.4 Allen Fetter Phase A - ML17216A186 Phase B - ML17289B214 5/21/2018 (2.5.4 & 2.5.5) (EPM) 5/21/2018 (2.5.1, 2.5.2, & 2.5.3) (EPM) 3.5.1.6: Aircraft Hazards Bechtel John Thomas/Alex Young Seshagiri Tammara (Rao),

NRO/DSEA Michael Dudek Allen Fetter Phase A - ML17116A306 Phase B - ML17289B272 2/22/2018 (EPM) 11.4.1: Radiological Effluent Release (liquid) 11.4.2: Radiological Effluent Release (gaseous)

Bechtel John Thomas/Alex Young Rich Clement, NRO/DSEA Michael Dudek 2.3 & 2.4 Mallecia Sutton Phase A - ML17216A553 Phase B - ML17289A671 2/22/2018 (EPM) 13.3: Emergency Planning Enercon Archie Manoharan Bruce Musico & Dan Barss, NRO DCIP Joe Anderson/Dan Barss 2.3 Mallecia Sutton Phase A - ML17214A319 Phase B - ML17291A039 6/26/2018 (EPM) 13.3.4.3.1: Methodology for EPZ Siting (input to EP)

Enercon John Thomas/Archie Manoharan Michelle Hart, NRO/DSEA Michael Dudek Mallecia Sutton Phase A - ML17214A751 Phase B - ML17291A069 6/26/2018 (EPM) 13.6: Physical Security Pat Asendorf Kevin Casey David Diec, NRO DCIP Alison Rivera Mallecia Sutton Phase A - ML17200D087 Phase B - ML17291A090 4/18/2018 (EPM) 15.0.3: Radiological Consequences of Design Basis Accidents Bechtel John Thomas/Alex Young Seshagiri Tammara (Rao),

NRO/DSEA Michael Dudek 2.3 Allen Fetter Phase A - ML17178A395 Phase B - ML17291A146 2/22/2018 (EPM) 17.0: Quality Assurance Aaron England/Rob Seipel Roger Scott Nicholas Savwoir, NRO DCIP Terry Jackson Allen Fetter Phase A - ML17215B021 Phase B - ML17291A527 5/21/2018 (EPM)