ML18059A981

From kanterella
Jump to navigation Jump to search
Discusses Insp Rept 50-255/94-02 on 940110-0211 & Forwards Notice of Violation & Proposed Imposition of Civil Penalty. Weaknesses in Mgt Oversight & Communications Resulted in Engineering Organization Not Understanding Sys Design
ML18059A981
Person / Time
Site: Palisades 
Issue date: 05/06/1994
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Fenech R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18059A982 List:
References
EA-94-041, EA-94-41, NUDOCS 9405120280
Download: ML18059A981 (4)


See also: IR 05000255/1994002

Text

UNITED STATES *

NUCLEAR REGULATORY COMMISSION

Docket No. 50-255

License No; DPR-20

EA 94-041

Consumers Power Company *

REGION Ill

801 WARRENVILLE ROAD

LISLE, ILLINOIS 60532-4351

May 6, 1994

ATTN:

Mr. Robert A. Fenech

Vice President - Nuclear

Operations

1945 West Parnall Road

Jackson, Michigan

49201

Dear Mr. Fenech:

SUBJECT:

NOTICE OF VIOLATION AND PROPOSED IMPOSITION OF CIVIL PENALTY -

$50,000

(INSPECTION REPORT NO. 50-255/94002(DRS))

This refers to th~ service water ~ystem operational performance inspection

(SWSOPI) conducted from January _10 through February 11, 1994, at Pali sades

Nuclear Plant.

The report documenting this inspection was sent to you by

letter dated Maich 4, 1994.

During the inspection, a violation .of NRC

requirements was identified.

An enfo~cement conference was held on March 11,

1994, to discuss the apparent violation, its causes, and your corrective

actions.

'The inspection identified five*examples where prompt corrective actions were

not taken for significant conditions adverse to quality.* On~ example involved*

a single failure vulnerability that could have led to the loss of all

engineered safeguards system pumps.

Four additional examples were identified

by your service water Safety System Design Confirmation (SSDC) program in June

1989, and the component cooling water SSDC in June 1990.

All examples

exhibited inadequate engineering evaluations and lack of management

involvement in the SSDC process.

We have concluded that weaknesses in management oversight and communications

resulted in your engineering organization's not understanding the system's

de~ign and a failure to adequately define who was r~sponsible for maintaining

the design.

These failures directly contributed to your failure to recognize

  • and promptly correct the design deficiencies.

We recognize you have taken

significant actions to address management and engineering issues at Palisades.

However; deficiencies o~ this nature take time to resolve and in the interim

you are susceptible to additional problems, thus additional scrutiny of

engineering activities is essential.

The enclosed Notice of Violation and Proposed Imposition of Civil Penalty

(Notice) describes one violation involving five examples of failure to take

. appropriate and timely corrective action to correct significant conditions

    • aaver*se*'i-o -qua-nt_x .. The Rroblem *i,s considered to represent a significant

9405120280~40506 \\. Y 1),

. PPR

ADOCK Q:?Q00255 * '* ;:,

. )

'. Ci .

PDR

  • *9

.

\\'- **1rD-ffl 7- ~ ~:----~*~ -.. :- , .. *--- -

t1Jl

II~

Consumers Power Company

- 2 -

breakdow~irt the control of your corrective action program.

Therefore, in

accordance with the "General Statement of Policy and Procedure for NRC

Enforcement Actions," (Enforcement Policy) 10 CFR Pa-rt 2, Appendix C, the

problem has been categorized at-Severity Level III.

The base value of a civil penalty for a Severity Level III violation or

problem is $50,000, with consideration for additional escalation and

mitigation as set forth in the Enforcement Policy.

In this case, we

considered escalating the civil penalty due to the NRC's identifying the

problem, your poor past performance, and the length of time that most of the

problem went uncorrected.

We considered mitigation because of your prompt

corrective action following our identification of the problem.

As a result of

these considerations and the application of these factors, the base penalty

could have been increased significantly under the normal application of the

Enforcement Policy.

We acknowledge your completed and ongoing corrective actions which include

opening CCW valves CV-0913 and CV-0950, completing a pump cooling requirements

analysis by April 30, 1994, reevaluating all SSDC findings by August l, 1994,

coordinating the pump inservice testing program with system performance

verifications, enhancing the work order review process by June 1, 1994,

conducting an individual accountability meeting with all employees, requiring

systems engineers to walk down their systems and review all system work

orders, and providing continuing training of system engineers on lessons

learned regarding operability issues.

We also acknowledge that you are

actively developing a Performance Improvement Plan and expect to have it

finalized by mid-May 1994.

In addition to these corrective actions, we are.

aware of numerous senior management changes recently undertaken at Palisades

and understand that these changes were made to increase the focus toward

identifying and correcting problems and improving overall performance.

Because of the very significant and broad managerial changes you have made in

an attempt to correct overall past poor performance at Palisades, and to

encourage you to continue with such aggressive actions to improve performance,

I have been authorized after consultation with the Director, Office of

Enforcement, and the Deputy Executiye Director for Nuclear Reactor Regulation,

Regional Operations and Research, to exercise discretion under Section VII of

the Enforcement Policy and issue the enclosed Notice in the base amount of

$50,000 for the problem descrfbed above, notwithstanding the fact that the

normal application of the escalation and mitigation factors would have

resulted in a substantially higher civil penalty.

Iri exercising this

discretion, I emphasize that the NRC expects Consumers Power Company to

continue its recent aggressive actions to improve performance at Palisades and

that .the __ effectiveness of implementation of these actions will be examined

closely by the NRC.

You are required to respond to this letter and should follow the instruction~

specified in the enclosed Notice when preparing your response.

In your

response, you should document the specific action taken and any additional

actions you plan to prevent recurrence. After reviewing your response to this

Notice, including your proposed corrective actions and the results of future

..

Consumers Power Company

- 3 -

inspections, the NRC will determine Whether further NRC enforcement action is

necessary to ensure compliance with NRC regulatory requirements.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of

this letter, its enclosure, and your response will be placed in the NRC Public

Document Room.

The response directed by this letter and the enclosed Notice are not subject

to the clearance procedures of the Office of Management and Budget as required

by the Paperwork Reduction Act of 1980, Public Law No.96-511.

Enclosure:

Notice of Violation and Proposed

Imposition of Civil Penalty

cc w/enclosure:

Thomas Palmisano, Acting General

Manager

David W. Rogers, Safety

and Licensing Director

OC/LFDCB

Resident Inspector, Riii

James R. Padgett, *Michigan Public

Service Commission .

Michigan Department of

Public Health

Palisades, LPM, NRR

SRI, Big Rock Point

G. E. Grant, Riii

o n . Martin

Regional Administrator

Consumers Power Company

DISTRIBUTION:

POR

SECY

CA

JTaylor, EOO

,./

JMil ho an, OEDR

Jlieberman, OE

LChandler, OGC

JGoldberg, OGC

WRussell, NRR

LReyes, NRR

LTremper, OC

Enforcement Coordinators

RI, Rll, RIV, WCFO

Fingram, GPA/PA

OW i 11 i ams , 0 I G

BHayes, 01

EJordan, AEOO

MSatorius, OE

EA File

[~cs. * f

  • ~tate of Mi chi gan

RAO: RI II

SLO:RIII

PAO:RIII

-4-