ML18059A969

From kanterella
Jump to navigation Jump to search
Forwards Exam Rept 50-255/OL-94-01 on 930328.Weakness Noted. Abnormally High Number of Simulator Modeling Deficiences Identified by NRC During Exam & Administration.One SRO Candidate Failed Exam
ML18059A969
Person / Time
Site: Palisades 
Issue date: 04/25/1994
From: Burgess B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Thomas J. Palmisano
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18059A970 List:
References
NUDOCS 9405040003
Download: ML18059A969 (2)


Text

Docket No. 50-255 Consumers Power Company ATTN:

Mr. T. Palmisano Acting General Manager Palisades Nuclear Generating Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

Dear Mr. Palmisano:

SUBJECT:

EXAMINATION REPORT April 25, 1994 On the week of March 28, 1993, the NRC administered examinations to employees of your organization who had applied for licenses to operate your Palisades Nuclear Generating Plant. At the conclusion of the examination, the examination questions and preliminary findings were discussed with those members of your staff identified in the enclosed report.

One Senior Reactor Operator candidate failed the examination.

All other candidates passed.

There was an abnormally high number of simulator modeling deficiencies identified by the NRC during examination development and administration.

These deficiencies were discussed with the training staff and are identified in Enclosure 2~. The simulator instructors had to work around the deficiencies to simulate requested malfunctions and events for the examinations.

Additionally, a reactor startup scenario was developed and validated for the reactor to reach ~riticality. However, when that exact scenario was*

administered for the examination reactor criticality could not be achieved for unknown reasons.

These deficiencies contributed to unnecessarily long hours d~ring examination development and validation.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosures will be placed in the NRC Public Qocument Room.

OSG039 9405040003 940425 PDR ADOCK 05000255 V

PDR

Consumers Power Company 2

April 25, 1994 Should you have any questions concerning this examination, please contact us.

Enclosures:

1.

Examination Report No. 50-255/0L-94-0l(DRS)

2.

Simulation Facility Report

3.

Examinations and Answer Keys (SRO/RO) cc w/enclosures 1 and 2:

R. A. Fenech, Vice President Nuclear Operations

  • David W.

Ro~ers, Safety and.

Licensing Director OC/LFDCB Resident Inspector, RIII James R. Padgett, Michigan Public Service Commission Michigan Department of Public Health Palisades, LPM, NRR SRI, Big Rock Point G. E. Grant, Rill R. M. Gallo, LOLB A. H. Hsia, Project Manager, NRR W. Kropp, Section Chief, DRP Sincerely, Original signed by ~ruce L. Burgess Bruce L. Burgess, Acting Chief Operations Branch M. Morgan, Contract Exam Supervisor, PNL cc w/enclosures 1, 2, and 3:

Donald D. Hice, Plant Training Manager bee w/enclosures 1, 2 and 3:

PUBLIC - IE42

~~I

~rtz 04/p/94 Riil B£dick 04/'V~/94 RI~

Kropp 04,b /94 R,1~

~E)&S 04/J.,/94