ML18058A394

From kanterella
Jump to navigation Jump to search
Forwards Safety Insp Rept 50-255/92-14 on 920324-0403.No Violations Noted.Areas Examined Were Primarily in Response to Generic Ltr 89-10
ML18058A394
Person / Time
Site: Palisades Entergy icon.png
Issue date: 04/29/1992
From: Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Slade G
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18058A397 List:
References
GL-89-10, NUDOCS 9205050082
Download: ML18058A394 (14)


See also: IR 05000255/1992014

Text

' . I

~*

' i. ..

,..-

APR 2 9 l99l

' *

Docket No. 50-255

'-= Consumers Power company

ATTN:

Mr. Gerald B. Slade

General Plant Manager

Palisades Nuclear Plant

27780 Blue Star Memorial Highway

Covert, MI

49043

Dear Mr. Slade:

This letter refers to the routine safety i'nspection conducted by

Messrs. G. D. Replogle and J. F. Smith, and Miss C. A. Gainty of

this office on March 24 through April 3, 1992.

The inspection

included a review of activities authorized for your Palisades

Nuclear Generating Plant.

At the conclusion of the inspection,

the findings were discussed with those members of your staff

identified in the enclosed report.

The areas examined during the inspection are identified in the

report.

These areas consisted primarily of a review of the

Palisades Motor Operated Valve Program established in response to

Generic Letter 89-10.

Within this area, the inspection consisted

of a selective examination of procedures and representative

records, observations, and interviews with your personnel.

No violations of NRC requirements were identified during th~

course of this inspection.

In accordance with 10 CFR 2.790 of the Commission's regulations,

a copy of this letter, and the enclosed inspection report will be

placed in the Public Document Room.

We will gladly discuss any questions you have concerning this

inspection.

Enclosure:

Inspection

Report-Ne~-50-255/92014(DRS)

See Attached Distribution

. ll-

RIII

~

~'iig e/jk

04/28/92

9~05050082 920429

POR

ADOCK "05000255

G

PDR

Sincerely,

M. A. Ring, Chief

Engineering Branch

' *-- Consumers Power Company

Distribution

cc w/enclosure:

David P. Hoffman, Vice President

Nuclear Operations

P. M. Donnelly, Safety

and Licensing Director

DCD/DCB (RIDS)

OC/LFDCB

Resident Inspector, RIII

James R. Padgett, Michigan

Public Service Commission

Michigan Department of

Public Health

Palisades LPM, NRR

SRI, Big Rock Point

w. Hodges, RI

A. Gibson, RII

s. Collins, RIV

R. Zimmerman, RV

T. Scarbrough, NRR

2

APR 2 9 1992

J

.:....

' **

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No.: 50-255/92014(DRS)

Docket No.: 50-255

License No.: DPR-20

Licensee:

Consumers Power Company

212 West Michigan Avenue

Jackson, MI

49201

Facility Name:

Palisades Nuclear Generating Plant

Inspection At:

Palisades Site, Covert, MI

through April 3, 1992

Approved

obson, Chief

s & Processes Section

Inspection Summary

t(-2 Y-~ z..._

Date

l./- -:i.y- f 1....

Date

Inspection conducted March 24 through April 3, 1992 (Report No.

50-255/92014(DRS))

Areas Inspected:

Announced safety inspection of the licensee's

response to Generic Letter (GL) 89-10, "Safety-Related Motor-

Operated Valve (MOV) Testing and Surveillance" (2515/109) and

licensee actions on previously identified items of noncompliance

(92701) .

Results:

No violations or deviations were identified.

One open

item was disclosed (Paragraph 3.a. (2) (b)).

The licensee demonstrated strengths in the following areas:

0

The technical knowledge and expertise of the MOV coordinator

was exceptional.

0

Steps taken to address inaccurate actuator information

supplied by the vendor weie excellent.

9205050088 920429

PDR

ADOCK 05000255

G

PDR

<.

I

Inspection Summary

2

0

The scope and intent of the self-assessment addressing the

recommendations of GL 89-10 were excellent, although

followup actions were deficient.

The licensee demonstrated weaknesses in the following areas:

0

0

0

The program implementation had not shown significant

progress for the past two years.

Evaluation of test data had not started at the time of the

inspection.

Analysis and calculations addressing degraded voltage,

design basis requirements, thrust requirements, and thermal

overload sizing were not complete at the time of the

inspection and may adversely impact the schedule for

completion of the program .

1.

2 .

3.

TABLE OF CONTENTS

Persons Contacted ......................*.**... ~********

1

Licensee. Action on Previous Inspection Findings .....***

1

Inspection of the Palisades Program Developed in

Response to Generic Letter 89-10 ..........*.**......*

1

a.

Generic Letter 89-10 Program Review .....*.***.**.*

1

(1) Scope of the Generic Letter Program .**...**...

2

(2) Design Basis Reviews .....*.***.*......***..***

2

(3) MOV switch Settings .........******..*..**.....

4

(4) Design Basis Differential Pressure and Flow

Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

5

(5) Periodic Verification of MOV Capability ***.*..

5

(6) MOV Failures, Corrective Actions and

Trending. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

6

( 7) Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

6

b.

Associated Programmatic Reviews .*.******..*..****.

6

(1) Design Control for Thermal overload

Protect ion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

6

(2) MOV Setpoint Control .............*.*......***.

6

( 3) *Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

7

( 4) Training. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

8

(5) OJ?eratin<! Experience and Ven,dor Notification..

8

(6) D1agnost1cs............................ ... . . . . .

8

4.

Licensee Self-Assessment~ ............*..*.*.**....*..**

9

5.

Open Items . ................ * .... * ............. *. . . . . . . . . . .

9

6.

Exit Meeting ... ~.......................................

9

i

DETAILS

1.

Persons Contacted

Consumers Power Company (CPCo)

  1. T. Palmisano, Administrative and Planning Manager
  1. G. Brock, Electrical Engineer
  1. P. Donnelly, Director, Plant Safety and Licensing
  1. B. Gerling, Safety Analysis Supervisor
  1. J. Kuemin, Licensing Administrator

K. Osborne, Systems Engineer Manager

  1. P. Rigozzi, Training Administrator
  1. G. Smith, Systems Engineer
  1. B. Vanwagner, Systems Engineer
  1. E. Zernick, Performance Assessment

U. S. Nuclear Regulatory Commission CNRC)

J. Heller, Senior Resident Inspector

  1. R. Roton, Resident Inspector
  1. Denotes those attending the exit meeting on April 3, 1992.

2.

Licensee Action on Previous Inspection Findings (92701)

(Closed) Violation 50-255/89007-0JCDRS):

Low temperature

overpressurization setpoints for M0-27B and M0-27C in the

primary coolant system exceeded the technical specification

allowable value on several occasions.

The inspector's

review of the corrective action confirmed that the necessary

technical specification change had b~en processed to

preclude a recurrence of the problem.

This violation is

closed.

3.

Inspection of the Program Developed in Response to Generic

Letter 89-10

a.

Generic Letter (GL) 89-10 Program Review

The NRC inspectors reviewed the commitments contained

in the licensee's response submitted to the NRC by

letter dated December 20, 1989.

No exceptions were

taken to the recommendations outlined in the GL.

The NRC inspectors reviewed procedure EM-28-01, "Motor

Operated Valve Program" Rev. o, dated December 19,

1990.

The document did not reflect the actual program.

being implemented at the time of the inspection.

For

example, the licensee planned to revise all of the

"Design Basis DP Documents."

However, the program

1

document referenced only the old dp documents and made

no mention of the revisions.

Another example was that

the program document specified preventive maintenance

frequencies of two and four years depending on the type

of maintenance performed, while the aqtual frequencies

were every two and four refueling outages,

respectively.

Revisions to the program document should

be made so that the document accurately reflects the

program being implemented.

The program implementation had not shown significant

progress for the past two years.

The inspectors

considered the lack of progress for such a sustained

period of time to be a weakness.

(1)

Scope of the Generic Letter Program

The Palisades plant had a total of 62 MOVs.

Sixteen were in the circulating water system and

were not safety-related.

The inspectors reviewed

the engineered safety, chemical volume and

control, and auxiliary feedwater systems as a

sample check for the completeness of the scope of

the GL 89-10 program.

No problems were found.

The NRC inspectors reviewed written justification

for the exclusion of 12 MOVs from differential

pressure (dp) testing and found it to be within

the guidelines of the GL with one exception.

PORV

block valves M0-1042A and M0-1043A were grouped

based on dp testing performed on M0-1042A and an

extensive dimensional analysis of the two MOVs.

The licensee claimed that because tpe MOVs

appeared to be identical, testing of M0-1043A was

not necessary.

However, industry test data has

shown that apparently identical MOVs often do not

perform in an identical manner when subjected to

design basis testing.

Valve M0-1043A should be

tested if practicable or justified for exclusion

from dp testing in accordance with the

recommendations outlined in. the GL.

The inspectors determined that the scope of the

program was consistent with the guidance of GL 89-

10, with the exception of valve grouping.

(2)

Design Basis Reviews

(a)

Differential Pressure Requirements

Work had not started on updated design basis

documents (DBDs) to address maximum operating

2

conditions.

However, the NRC inspectors

found the methodology for revising the DBDs

to be conservative.

(b)

Reduced Voltage Capability

Procedure number EM-28-0l, "Motor Operated

Valve Program," Rev. O stated that degraded

voltage was not considered in the design

basis calculations because the voltage at the

motor terminals was assumed to be greater

than 90%, which was consistent with the

Limitorque recommendations.

However, no

engineering analysis was performed to support

this assumption.

surveillance Report S-QC-

89-07, dated March 9, 1990 identified this to

be a deficiency.

Corr.ective actions were not

taken at that time, but funding for future

analysis was requested prior to this NRC

inspection.

The NRC inspectors and the licensee performed

separate degraded voltage calculations for a

sample of six MOVs to determine actual worst

case motor terminal voltages.

The results

from the two analysis methods agreed within

acceptable margins.

Four of the calculations

showed the degraded voltage values available

at the motor terminals to be less than 90% of

the nominal 460V rating.

The worst case

voltage available for M0-3008 was only 60% of

the nominal voltage.

The licensee committed

to perform detailed degraded voltage analysis

for all MOVs in the GL 89-10 program at

Palisades.

The NRC inspectors found, through

calculations, that MOVs M0-0501 and M0-0510

(MSIV bypass valves) may not develop enough

thrust under degraded voltage conditions to

close during a design basis event (steam line

break).

Furthermore, during static testing

the MOVs appeared to have unusually high stem

factors, which may indicate degradation of

the stems and/or stem nuts.

An analysis was

performed to show that the position of the

MOVs would be insignificant during the

postulated event, however, the portion of the

analysis addressing the event at the end of

core life (ECL) was not expected to be

finished until September 30, 1992 (prior to

ECL).

This will be considered an open item

3

  • "'

(c)

pending further NRC review of the completed

analysis. (50-255/92014-0l(DRS))

The program did not-consider the effects of

high ambient temperatures on the performance

of MOV motors.

However, Limitorque was

performing testing and analysis to address

this issue.

Information from the testing

should be incorporated into the program when

it becomes available.

Completed Design Basis Review

Revised DBDs were not complete at the time of

the inspection.

However, old DBDs were

available for reference which were prepared

in response to NRC Bulletin (IEB) 85-03.

The

NRC inspectors reviewed several of the old

design basis documents and found them to be.

conservative, although lacking in detail.

In

general, the old DBDs did not address valve

mispositioning.

The licensee planned to

incorporate mispositioning into the new DBDs

if the results of the mispositioning appeal,

currently being reviewed by the NRC staff,

dictates.

(3)

MOV Switch Settings

Actuator thrust calculations (used to set torque

switches) were not complete at the time of the

inspection but were scheduled to be finished by

the end of 1992.

The methods for calculating thrust included

provisions for adding a 30\\ margin to the*

calculated minimum required thrust to account for

diagnostic equipment inaccuracies, torque switch

repeatability,- and MOV degradation.

The

inspectors indicated that the 30% margin may not

be enough to envelop large inaccuracies that may

be experienced by the Motor Operated Valve

Analysis and Test System (MOVATS) that was used

during testing.

Steps should be taken to ensure

that margins used are adequate.

The licensee planned to use valve f.actors of 0.4

for flex-wedge gate valves, 0.2 for parallel disc

gate valves, and 1.1 for globe valves.

A

coefficient of friction for the stem/stem nut

interface of 0.2 was assumed.

These factors are

considered to be acceptable provided the

4

evaluation of test data shows them to be

conservative.

Rate-of-loading was not addressed in the program,

although an effeGt from rate-of-loading was

apparent in the test data.

Additional margin

should be added to calculations to envelop this

effect, when applicable.

(4)

Design Basis Differential Pressure and Flow

Testing

The NRC inspectors reviewed the methods for dp

testing several MOVs and found them to be

conservative.

(5)

Periodic Verification of MOV Capability

The plan for periodic verification of MOV

capability included static diagnostic testing of

MOVs every fourth refueling outage.

The period

recommended by the GL was every third refueling

outage.

The licensee committed to change the

period to conform with the recommendations of the

GL.

The NRC inspectors informed the licensee that

static testing was not currently an acceptable

method of periodic verification because of

uncertainties in the performance of MOVs under

static and design basis conditions.

In some cases, baseline static testing was

performed on MOVs prior to maintenance (a degraded

condition), while dp testing was performed after

maintenance.

The condition of the MOV during a

static baseline test should be the same as it was

when the MOV was dp tested.

Comparing test

results after maintenance to baseline test data

taken before maintenance makes detection of MOV

degradation unlikely.

Steps should be taken to

ensure that the data taken during baseline testing

is meaningful.

Most of the MOVs tested under differential

pressure conditions were tested in response to IEB

85-03.

Although the testing satisfied the

recommendations of GL 89-10, some MOVs were tested

as early as 1987.

These MOVs may require re-

testing in 1992 to meet the schedule for periodic

verification.

5

(6)

(7)

MOV Failures, Corrective Actions and Trending

MOV failures were reviewed and found to be

properly analyzed and documented.

The corrective

actions were specified and scheduled to ensure

completion.

The licensee did not have a program in place to

evaluate test data.

A program, with definitive

acceptance criteria, should be developed to

evaluate valve and stem factors experienced during

design basis and static testing.

The lack of an

evaluation program is considered to be a weakness.

Schedule

Fourteen MOVs that still re'quire dp testing were

scheduled to be tested within a time frame

consistent with the GL.

However, at the time of

the inspection, the revised DBDs, thrust

calculations, degraded voltages calculations and

.thermal overload (TOL) sizing calculations were

not started.

The results of the revised DBDs and

calculations may require torque switch setting

adjustments and/or TOL replacements for a large

number of MOVs.

Because of this, completion of

all the work necessary to close out the.GL, within

the schedule, may be improbable.

The lack of

updated design basis analysis and calculations

were considered to be a weakness.

b.

Associated Programmatic Reviews

(1)

Design Control for Thermal Overload Protection

The NRC inspectors reviewed documents that

addressed the methods for the design control of

TOLs.

At the time of the inspection, TOLs were

bypassed except for indication purposes.

However,

the program document noted plans to use TOLs in

MOV circuits in the future and to size TOLs based

on guidance from IEEE 741-1990.

Based on the

intentions specified in the program document,

design control for TOL protection appeared to be

acceptable.

(2)

MOV Setpoint Control

The methods for ensuring integrity of setpoint

calculations and setpoint control were reviewed.

Both the calculation of the settings and the

setting of the MOV switches are prescribed in

6

formal procedures which require authorization by

cognizant personnel to institute changes.

The

record of switch settings is maintained in a

controlled document which cannot be changed

without proper authorization.

The MOV setpoint

control program appeared to be protected from

unauthorized modification.

(3)

Maintenance

Several minor deficiencies were noted during plant

walkdowns.

Three MOVs were leaking oil from the

actuators, two MOVs were oriented such that the

spring pack was located below the actuator (which

could make hydraulic lock of the spring packs more

likely), and one valve stem appeared to be without

lubrication.

The licensee agreed to evaluate the

deficiencies and take appropriate corrective

actions where warranted~

The nominal stem lubrication frequency (every two

refueling outages) was longer than the 18 month

frequency recommended by Limitorque.

Furthermore,

the frequency was not consistent with the program

document which specified the lubrication of MOV

stems every 24 months.

The licensee agreed to

change the frequency of stem lubrication to an

i~terval not to exceed the Limitorqua

recommendations.

The lubrication frequency may be

increased in the future if information from

various industry testing programs indicates that

an extended frequency is warranted.

Testing was not performed after packing

adjustments unless the originally specified

packing gland torque w~s exceeded.

Test data was

presented which showed that the stem load due to

packing increased only slightly after adjustment.

However, the test data was limited in that testing

was only performed on one MOV and neglected the

effects of various foreign materials (such as

boric acid crystals that may be present at the

stem/packing interface) or packing damage (that

may occur as a result of a packing leak).

The

justification for not testing after minor packing

adjustments was found unacceptable because of the

lack of sufficient test da~a.

The licensee will

be expected to develop better justification to

support its position or develop plans to test MOVs

after *minor packing adjustments.

Adequate

justification may include an engineering

evaluation after adjustments to ensure that

7

substantial margin is available in the event that

packing loads are greater t'han anticipated.

Periodic refurbishment of actuators was not

performed.

Instead, refurbishment requirements

were based solely on trending results from

diagnostic test data.

Since some forms of

degradation are not detectable (in diagnostic

data) until the valve is rendered inoperable,

trending alone may not be sufficient.

A

supplemental periodic visual inspection of a

sample of MOVs would strengthen the existing

program.

(4)

Training

The NRC inspectors reviewed course outlines,

technical texts, training facilities, training

records, examinations, and descriptions of on-the-

job training provided to. personnel performing work

associated with the Palisades MOV program.

The

MOV training program at Palisades was considered

acceptable.

(5)

Operating Experience and* Vendor Notification

The NRC inspectors reviewed applicable procedures

and discussed the process for handling various

information notices from different so~rces.

The

licensee had taken steps to ensure that

information received was screened, evaluated and

maintained by appropriate organizations and that

appropriate actions were planned.

The* Palisades

program for the processing and control of

operating experience and vendor notifications

appeared to be acceptable.

Some Limitorque nameplates, and other information

documents issued by Limitorque, are known to have

inaccurate information.

However, steps had been

taken to ensure that the information used from

these sources was accurate.

These steps included

a visual examination of actuator parts during

refurbishment and a review of motor current

traces.

Palisades' extensive effort to address

this issue was considered t.o be a strength.

(6)

Diagnostics

Palisades currently uses VOTES diagnostic

equipment to test MOVs under both static and

dynamic conditions.

However, most of the

8

diagnostic testing previously performed used

MOVATS diagnostic equipment.

MOVATS equipment has

come under scrutiny with regard to its published

inaccuracies.

Since all of the design basis

diagnostic testing was performed at or near full

flow/dp conditions, the effects of the

inaccuracies may be insignificant.

However, if

degraded voltage concerns arise, the data from

MOVATS testing may be necessary to show

operability.

In these inst.ances, appropriate

values ~or diagnostic equipment inaccuracies

should be used.

Most static baseline diagnostic tests (performed

in the same general time frame as the design basis

dp tests) specified MOVATS diagnostic equipment

for data collection.

Subsequent static testing

specified the use of VOTES equipment.

Steps

should be taken to ensure that the comparison of

data from the two different diagnostic equipment

systems is meaningful.

4.

Licensee Self-Assessment

The self-assessment in the area of MOVs was evaluated by

review of Surveillance Report S-QC-89-07 dated March 9,

1990.

Although other surveillance was conducted on portions

of the program, this was the only report dedicated to

evaluation of the plant's compliance with the

recommendations of GL 89-10.

The scope and intent of the

effort was excellent in that it compared the program to

specific NRC commitments.

Howe.ver, some followup corrective

actions were deficient.

For example,* corrective actions for

degraded voltage issues were inadequate.

5.

Open Items

An open item is a matter that requires further review and

evaluation by the inspector, including an item pending

specific action by the licensee.

An open item disclosed

during this inspection is discussed in Paragraph 3.a. (2) (b).

6.

Exit Meeting

The inspectors met with licensee representatives (denoted in

Paragraph 1) at the conclusion of the inspection on April 3,

1992.

The inspectors summarized the purpose and scope of

the inspection and the findings.

The inspectors also

discussed the likely informational content of the inspection

report with regard to documents or processes reviewed by the

inspectors during the inspection.

The licensee did not

identify any such documents or processes as proprietary.

9