consumers Power POW ERi Nii MICHlliAN'S PROliRESS General Offices: 1945 West Parnall Road, Jackson,' Ml 49201 * (517) 788-0550 April 20, 1990 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT -
SIGNIFICANT PROJECTS AT PALISADES DURING 1990/1991 REQUIRING PLANT SECURITY SUPPORT In response to a recent request from Region III Plant Physical Protection Management, the following is a preliminary schedule of significant projects that require plant security support at Palisades during 1990 and 1991:
Preliminary Schedule Project
- Security Building Modification Modification Start April 1990
- Auxiliary Building Personnel May 1990 Access Opening
- Containment Construction Opening October 1990
- Protected Area Fence Modification June 1990
- Construction of Dry Fuel Storage April 1991 Facility 9004260222-900420 PDR ADOCK 05000255 F
PDC OC0490-0328-NL04 A CMS' ENERGY COMPANY Complete
- 1.
Search Area Expansion June 1990
- 2..Locker Room Expansion September 1990 June 1990 November 1990 December 1990 August 1991
~*
Nuclear Regulatory Commission Pali.sades Plant
~ Significant Projects at Palisades During 1990/1991 Requiring Plant Security Support April 20, 1990 Project
- The Security Access Control sys-tem is being evaluated to deter-mine whether it needs to be upgraded/modified to support the Steam Generator Replacement Proj-ect.
If the system needs to be upgraded/modified, the work should be completed by date indicated.
Brian D Johnson Staff Licensing Engineer CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades OC0490-0328-NL04 Preliminary Schedule Start Complete September 1990 2