Confirms Intention to Submit Completion Schedule for Info Requested in Generic Ltr 86-06,Section IV Re Implementation of TMI Action Item II.K.3.5.Statements in 850614 & 0702 Ltrs Re Isolation of Component Cooling Water Corrected
ML18052A620
Person / Time
Site: Palisades Entergy icon.png
Issue date: 07/28/1986
From: Kuemin J
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.05, TASK-TM GL-86-06, GL-86-6, NUDOCS 8608010262
Download: ML18052A620 (1)


Text

-

consumers Power POWERINli NllCHlliAN'S PROliRESS General Offices: 1945 West Parnell Road, Jackson, Ml 49201 * (517) 788-0550 July 28, 1986

Director, Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT -

SCHEDULE FOR IMPLEMENTATION OF TM! ACTION ITEM II.K.3.5, AUTOMATIC TRIP OF REACTOR COOLANT PUMPS - RESPONSE TO GENERIC LETTER NO. 86-06 The subject Generic Letter requested a completion schedule for information requested in section IV be developed with our NRC Project Manager.

At the request of the Project Manager,.we confirm our intention to submit the requested information by November 6, 1986.

Consumers Power letters of June 14, 1985 and July 2, 1985 responded to NRC letter of April 26, 1985 requesting additional information on NUREG-0737 item II.K.3.5.

Our response to question 1 of the NRC letter (contained in both responses) stated that component cooling water (CCW) to the primary coolant pumps isolated on a containment isolation signal, and that the isolation actuation had been modified to include low CCW discharge pressure and a containment isolation signal.

These statements were incorrect.

The original design for CCW isolation was on a safety injection signal (SIS) and was modified to require SIS and a concurrent low CCW 4ischarge pressure signal.

Presently the isolation signal is again being modified.

The new actuation will be on Containment High Pressure (CHP).

Included will be a manual key-lock bypass of the isolation signal in order to restore CCW to the primary coolant pumps.

This modification is expected to be completed before the end of the present outage.

~/~*~'

~ames L Kuemin Staff Licensing Engineer CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades OC0786-0124-NL04.-.-,-=-~-=-~~~~~~~