ML18052A144

From kanterella
Jump to navigation Jump to search
Provides Supplemental Response to Generic Ltr 83-28,Items 2.1 & 2.2 Re NPRDS Program Implementation Schedule.Input of Equipment Info Into Engineering Data Base & Reporting of Equipment Failures Will Be Up to Date by 860501,not 851101
ML18052A144
Person / Time
Site: Palisades Entergy icon.png
Issue date: 10/31/1985
From: Kuemin J
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Office of Nuclear Reactor Regulation
References
GL-83-28, NUDOCS 8511050037
Download: ML18052A144 (1)


Text

i.;,i..

(

consumers Power company General Offices: 1945 w~!rt Parnell Road, Jackson, Ml 49201 * {517) 1sa-osso

....October 31, 1985

Director, Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT -

NPRDS PROGRAM IMPLEMENTATION SCHEDULE -

SUPPLEMENTAL RESPONSE TO GENERIC LETTER 83-28 ISSUES 2.1 AND 2.2 UPDATE Consumers Power Company letter. of May 15, 1985 stated input of equipment information into the engineering data base would be complete and reporting of equipment failures would be up-to..:date by November 1, 1985.

Input of equipment.

information into the engineering data base has been completed on schedule, however, we will not be current in the reporting of equipment failures by November 1.

Our revised commitment to INPO is to complete the failure reporting backlog by May 1, 1986.

The revised schedule is due to the need tq review 1,500 maintenance orders that had not been accounted for in our May 15 letter.

  • ~/.~

VJames L Kuemin Staff Licensing Engineer CC Administrator, Region III,.USNRC NRC Resident Inspector - Palisades