Forwards Application for Amend to License DPR-20,revising Surveillance Frequency for Diesel Generator from 18 Months to Once Per Refueling Cycle.Fee Paid
ML18051B491
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/02/1985
From: Vandewalle D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Office of Nuclear Reactor Regulation
Shared Package
ML18051B492 List:
References
NUDOCS 8508060186
Download: ML18051B491 (2)


Text

.,

consumers Power David J VandeWalle company- --- Direcio_r _of _ _ __ _ _________ . _ _ _

Nuclear Licensing General Offices: 1945 West Parnall Road. Jackson, Ml 49201 * (517) 788-1636 August 2, 1985 Director, Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT -

TECHNiCAL SPECIFICATION CHANGE REQUEST - DIESEL GENERATOR SURVEILLANCE Attached are three (3) originals and thirty-seven (37) conformed copies of a request for change to the Palisades Technical Specifications. The request changes the 18 month diesel generator surveillance inspection to each refueling cycle. This change was previously submitted as part of a change request, on May 5, 1985, and the NRC granted a one time change to the license (Amendment No. 77 dated July 7, 1983) which allowed the change only for the operating cycle the plant was then in.

The proposed change revises the surveillance frequency specified for the diesel generator in Technical Specification 4.7.1 (c) from 18 months to once per refueling cycle. The effect of the change is to preclude plant shutdown for the sole purpose of performing preventive maintenance on the diesel generators at a specified 18 month interval, when the specified interval, itself, is not critical. The proposed frequency of each refueling cycle, during shutdown, is in accordance with the manufacturer's recommendations.

The 18 month surveillance comes due on September 24, 1985 for one of the diesel generators and*on November 1, 1985 for the other. The refueling outage is scheduled to begin on November 30, 1985. We request your prompt action in reviewing and approving this change request as failure to meet the surveillance requirement would cause entering a 7-day Limiting Condition of Operation.

A check in the amount of $150.00 is enclosed as required by 10CFR170.21 *

...... ~a~. ~~di u}aJL.

Director, ~ar Licensing A j)f19JY CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades f loof.,, I){fl ~"j Attachment r-ceHs~o~e~ou6fto~1~a~6~a~so~eo;::-:2=--~~-1-.:*_

OC0885-0257-NL04 PDR ADDCK 05000255 ' I p PDR LJ

ATTACHMENT

- Consumers- Power Company Palisades Plant Docket 50-255 PROPOSED TECHNICAL SPECIFICATION PAGE CHANGES August 2, 1985 1 Page IC0885-0257-NL04