. *I consumers Power company General Offices:
1945 West Parnall Road, Jackson, Ml 49201 * (517) 788-1636 June 20, 1985
- Director, Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT -
NUREG-0737 ITEM II.K.3.30 SMALL BREAK LOCA MODELS, AND ITEM II.K.3.31 PLANT SPECIFIC ANALYSES David J VandeWalle Director of Nuclear Licensing Consumers Power Company letters dated December 19, 1980 and January 22, 1982 contained our commitment to support the activities of the Combustion Engineering Owners Group (CEOG) in their efforts to satisfy the requirements of TMI Action Plan, Item II.K.3.30 for CE designed plants.
The.following reports and letters were generated by the CEOG to address the requirements of NUREG-0737 item II.K.3.30:
- 1.
Letter from Mr A E Scherer (C-E) to Mr J R Miller (NRC) dated April 15, 1982 transmitting CEOG report CEN-203-P, Revision 1-P, "Response to NRC Action Plan Item II.K.3.30 - Justification of Small Break LOCA Methods."
- 2.
Letter from Mr R W Wells* (Chairman of CEOG)-* to -Mr C 0 Thomas_ (NRC) dated April 28, 1984 transmitting CEOG report CEN-203-P, Revision 1-P, Supplement 1-P, "Response to NRC Request Number 1 for Additional Information on CE Report CEN-203-P."
- 3.
Letter from Mr R W Wells to Mr C 0 Thomas dated November 30, 1984 transmitting CEOG report CEN-203-P, Revision 1-P, Supplement 2-P,
""Further Response to NRC Request Number 1 for Additional Information on CE Report CEN.,-203-P, Revision 1-P."
- 4.
Letter from Mr R W Wells to Mr C 0 Thomas dated March 11, 1985 containing the commitment to perform a post-test analysis of Sem~scale Test S-UT-8.
Consumers Power Company has been and continues to be a participating member in the CEOG activities related to this issue including the post-test analysis of Semiscale Test S-UT-8.
As such, we believe that there exists adequate basis OC0685-0231-NL04
~tl586250246 850620
\\
. ~;.. ADOCK 0500~~~5
- I I
- ~
Director, Nuclear Reactor Regulation Palisades Plant NlJREG-0737 II.K.3.30, II.K.3.31 June 20, 1985 2
on which to conclude the acceptability of the CE small break LOCA model (CEFLASH-4AS as described in CENPD-137P, "Calculative Methods for the CE Small Break LOCA Evaluation Model," August, 1974 (Proprietary)) in meeting the requirements of item II.K.3.30, pending completion of the forementioned post-test analysis.
In addition, it is our conclusion that no plant specific analysis of small break LOCAs is required in order to satisfy item II.K.3.31 for Palisades Plant.
This conclusion is based on the results of item II.K.3.30 and the conclusion of the reference small break LOCA analysis (CENPD-137-P) that small breaks are not limiting from the point of view of 10 CFR 50.46 and Appendix K compliance for the CE 2560 Mwt class of plants.
The applicability of this conclusion to current Palisades fuel designs is addressed in more detail in our letter dated August 21, 1978 and the NRC safety evaluation report for Palisades License Amendment No. 43.
Director, Nuclear Licensing CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades OC0685-0231-NL04