consumers Power company General Offices: 1945 West Parnall Road, Jackson, Ml 49201 * (517) 7a$-0550 January 25, 1984 Dennis M Crutchfield, Chief Operating Reactor Branch No 5 Nuclear Reactor Regulation US Nuclear Regula~ory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALIS.ADES PLANT - REQUEST FOR A CONCURRENCE ON THE INTERPRETATION OF 10 CFR 50 APPENDIX J III.D.2(b)ii FOR OUTAGES GREATER THAN 72 HOURS Consumers Power Company in a letter dated January 19, 1984, requested an exemption from 10 CFR 50 Appendix J III.D.2(b)ii for short duration outages of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or less.
Consumers Power Company's interpretation of this regulation as it pertains to outages greater than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is as follows:
In the event of a scheduled or non-scheduled outage of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or more, Consumers Power Company makes the interpretation that the full air lock test at P, required by 10 CFR 50 Appendix J III.D.2(b)ii, can be performedaprior to the end of the outage provided the following conditions are met: (1) The full air lock leak test at P will not be
'completed any sooner than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> prior to leaving coldashutdown;. (2)
After the full test at P, the air lock must be treated as if containment integrity is required an~ tested in accordance with 10 CFR 50 Appendix J III.D.2.(b)iii; (3) Activity through the air lock must be kept to a minimum after completion of the full air lock test.
Performing the full air lock test before the end of the outage will permit schedule flexibility.
Consumers Power Company would appreciate NRC concurrence in this matter.
Brian D Johnson Staff Licensing Engineer CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades
-8401300223-840125 I
PDR ADOCK 05000255 P
PDR OC012384-NL01