Forwards Reactor Internals Noise Monitoring Test,Jan-Dec 1981.
ML18046B325
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/24/1982
From: Johnson B
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML18046B326 List:
References
NUDOCS 8203050289
Download: ML18046B325 (1)


Text

consumers Power company General Offices: 1945 West Parnell Road, Jackson, Ml 49201 * (517) 788-0550 February 24, 1982 James G Keppler, Administrator Region III US Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137 DOCKET 50-255 - LICENSE DPR PALISADES PLANT REACTOR INTERNALS NOISE MONITORING TESTS Palisades Plant Technical Specification 4.13.D.3 requires the results of the Reactors Internals Noise Monitoring Tests to be submitted to t~e NRC Region III Office on an annual basis.

The results of the test demonstrates that the reactor core barrel is tightly clamped with no other anomalous vibrations occurring during the testing period. The attached test fulfills the requirements of the subject Technical Specification.

Brian D Johnson Senior Licensing Engineer CC Director, Office of Nuclear Reactor Regulation Director, Office of Inspection and Enforcement NRC Resident Inspector - Palisades ATTACHMENT Reactor Internals Noise Monitoring Test a.f) o/fl I FEB 2 <6 *1982i 8203050289 820224 PDR ADOCK 05000155