Notifies That Bechtel Corp Const Phase of long-term Cooling Mods Has Started in Conjunction w/1981 Refueling Outage. Info Serves as Bimonthly Status Rept for Aug-Sept 1981 Per Tech Specs 6.9.3.3.6
ML18046A924
Person / Time
Site: Palisades 
Issue date: 09/17/1981
From: Johnson B
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8109220378
Download: ML18046A924 (1)


Text

consumers Power company General Offices: 212 West Michigan Avenue, Jackson, Ml 49201 * (517) 788-0550 September 17, 1981 Director, Nuclear Reactor Regulation Att Mr Dennis M Crutchfield, Chief Operating Reactors Branch No 5 US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR-20. -

'PALISADES PLANT -

LONG TERM COOLING EQUIPMENT MODIFICATION BIMONTHLY

  • STATUS REPORT The construction phase of the long-term cooling modifications as prepared by Bechtel Corporation has started in conjunction with the 1981 Palisades Plant refueling outage.

This serves as a bimonthly status report for August-September 1981 as re-quired by Technical Specification 6.9.3.3.b.

Brian D Johnson Senior Licensing Engineer CC Director, Region III, USNRC NRC Resident Inspector - Palisades