Confirms Telcon Re IE Bulletin 80-10, Contamination of Nonradioactive Sys & Resulting Potential for Unmonitored, Uncontrolled Release of Radioactivity to Environ. Util Has 30-day Extension to Respond to Items 1 & 2
ML18044A938
Person / Time
Site: Palisades Entergy icon.png
Issue date: 05/23/1980
From: Hoffman D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
IEB-80-10, NUDOCS 8005280610
Download: ML18044A938 (1)


Text

-

consumers Power company General Offices: 212 West Michigan Avenue,.Jackson, Michigan 49201

  • Area Code 517 788-0550 May 23, 1980 Mr James G Keppler Office of Inspection and Enforcement Region III US Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137 DOCKET 50-255 -

LICENSE DPR PALISADES PLANT -

REQUEST FOR EXTENSION OF RESPONSE TIME IE Bulletin 80-10, Contamination of Nonradioactive Systems and Resulting Potential for Unmonitored, Uncontrolled Release of Radioactivity to Environment, requires a response for actions to be taken for Items l and 2 within 45 days from the date of the subject bulletin.

Consumers Power Company requested and was granted a 30-day extension, by telephone conversation between Mr K Baker (NRC) and Mr SRFrost (CPCo), to respond to this bulletin.

This extension was requested because the work involved could not be completed in the required time.

David P Hoffman (Signed)

David P Hoffman Nuclear Licensing Administrator CC Director, Office of Nuclear Reactor Regulation Director, Office of Inspection and Enforcement Resident Inspector-Palisades 8 0052 80 G, ( ()