Forwards LER 98-001-00,concerning Engineered Safety Feature Actuations That Occurred When 2B Reactor Protection Sys Bus Transferred to de-energized Source
Date released: 09/27/2018 Download: ML18039A309


LER 98-001-00:on 980308,ESF Actuations Occurred When 2B RPS Bus Was Transferred to de-energized Source.Caused by Failure of Preparing Clearance to Exercise Proper Attention. 2B RPS Bus Restored to Transformer Source
ML18039A310
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 04/07/1998
From: Root C
TENNESSEE VALLEY AUTHORITY
To:
References
Download: ML18039A310 (8)
Forwards LER 98-001-00,concerning Engineered Safety Feature Actuations That Occurred When 2B Reactor Protection Sys Bus Transferred to de-energized Source
ML18039A308
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 04/07/1998
From: Crane C
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
Download: ML18039A308 (6)