Submittal of Final After Action Report/Improvement Plan for the Clinton Power Station Radiological Emergency Preparedness Exercise Held on November 1, 2017
ML18037A707
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/30/2016
From: Odeshoo J
Federal Emergency Management Agency
To: Ricker J
Office of Nuclear Reactor Regulation, State of IL, Emergency Management Agency
References
Download: ML18037A707 (1)


Text

Jennifer Ricker, Interim Director Illinois Emergency Management Agency 2200 South Dirksen Parkway Sp!ingfield, lliinois 62703

Dear Ms. Ricker:

U.S. Department of Homeland Security Region V 536 South Clark Street, 6th Floor Chicago, IL 60605 FEMA JAN ~*O 2018 Enclosed is the Final After Action Report/Improvement Plan for the Clinton Power Station Radiological Emergency Preparedness Exercise held on November 1, 2017.

There were no Level 1 or Level 2 Findings identified for the State oflliinois or DeWitt, McLean, and Macon Counties.

There was one Level 2 Finding for Piatt County. The associated *criterion was successfully redemonstratedon November 1, 2017.

Based on the results of the exercise, the planning and preparedness for the State of lliinois and affected local jurisdictions provide reasonable assurance that appropriate measures can be taken to protect public health and safety. Therefore, Title 44 CFR Part 350 approval of the off site radiological emergency response plans and preparedness for the State of Illinois remain in effect.

If you have any questions, please contact Sean O'Leary, Chair, Regional Assistance Committee, at (312) 408-5389.

Enclosure cc:

DHS/FEMA He~dquarters NRC Region III Sincerely, Janet M. Odeshoo Deputy Regional Administrator NRC Headquarters Document Control Desk www.fema.gov