Southern Nuclear FEB 0 5 2018 Docket Nos.:
52-025 52-026 Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6459 tel 410-474-8587 ceii myox@southernco.com ND-18-0031 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Construction Activities Schedule Six-Month Update for Completion of the Inspections, Tests, and Analyses (ITA)
Ladies and Gentlemen:
In accordance with 10 CFR 52.99(a), Southern Nuclear Operating Company (SNC), as a Combined License (COL) holder under 10 CFR 52, hereby submits the six-month construction schedule for completing the Inspections, Tests, Analyses (ITA) in the Nuclear Regulatory Commission (NRC) approved Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) for Vogtle Electric Generating Plant (VEGP) Units 3 and 4.
Enclosures 1 and 2 contain the ITA completion schedules for VEGP Unit 3 and Unit 4, respectively. Enclosure 3 providesa Reader's Guidefor understanding the detailed construction information contained within each ITAcompletion schedule.
The enclosed ITA completionschedules are based on projected construction activitiesas of January 1,2018. The enclosed ITA completion schedules continue to track Unit 3 and Unit 4 reference ITAAC that were consolidated by license amendments 85 and 84 (respectively).
These ITAAC are individually depicted as being closed on August 24, 2017, the date the license amendment request was approved. The activity dates are established by, and are the property of SNC, and are based on the VEGP 3 and 4 integrated project construction schedule. As schedule changes occur, they will be reflected infuture ITAAC completion schedule updates.
The construction schedule information provided in Enclosures 1 and 2 is considered proprietary and exempt from mandatory public disclosure pursuantto the provisions of 10 CFR 2.390(a)(4) and 10 CFR 9.17(a)(4). In accordance with the approach described in SECY-06-0114 and NEI 08-01, the construction schedule information was demonstrated to be proprietary based on affidavits provided bySNC to the NRC on October 6, 2017 (ADAMS ML17279A661).
U. S. Nuclear Regulatory Commission ND-18-0031 Page 2 of 4 Accordingly, the enclosures should be withheldfrom public disclosure and non-proprietary versions are not being provided. This letter contains no regulatory commitments.
Should you have questions regarding the enclosed Information, please contact me at (706) 848-6459.
Respectfully submitted.
Michael J. Yox Regulatory Affairs Director Vogtle 3&4 MJY/RAS/amm
Enclosures:
- 1) Vogtle Electric Generating Plant (VEGP) Unit 3 - ITAAC Completion Schedule {Withhold from Public Disclosure}
- 2) Vogtle Electric Generating Plant (VEGP) Unit 4 - ITAAC Completion Schedule {Withhold from Public Disclosure}
- 3) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 ITAAC Completion Schedules - Reader's Guide
U. S. Nuclear Regulatory Commission ND-18-0031 Page 3 of 4 To:
Southern Nuclear Operating Companv/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)
Mr. M. D. Rauckhorst (w/o enclosures)
Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)
Mr. D. L. McKinney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. D. Williams Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. 0. Chamberlain Mr. D. R. Culver Mr. R. L. Belike Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:
Nuclear Reouiatorv Commission Mr. W. Jones (w/o enclosures)
Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. T. C. Brimfield Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Oalethorpe Power Corporation Mr. R. B. Brinkman Municipal Electric Authorltv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson
U. S. Nuclear Regulatory Commission ND-18-0031 Page 4 of 4 Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Orlani (w/o enclosures)
Mr. D. C. Durham (w/o enclosures)
Mr. M. M. CorlettI Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Baich Bingham