ML18036B125

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/92-43,50-260/92-43 & 50-296/92-43 on 921214-18.Violations Noted.Major Areas Inspected:Completed Work Records,Surveillance Repts & Certifications for Matl & Personnel Used on Project
ML18036B125
Person / Time
Site: Browns Ferry  
Issue date: 01/08/1993
From: Blake J, Economos N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18036B123 List:
References
50-259-92-43, 50-260-92-43, 50-296-92-43, NUDOCS 9301200059
Download: ML18036B125 (15)


See also: IR 05000259/1992043

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSlON

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

'+a*++

Report Nos.:

50-259/92-43,

50-260/92-43,-

and 50-296/92-43.

Licensee:

Tennessee

Valley Authority

3B Lookout Place

1101 Market Street

Chattanooga,

TN

37402-2801

Docket Nos.:

50-259,

50-260

and

50-,296

Facility Name:

Browns Ferry 1,

2,

and

3

License Nos.:

DPR-33,= DPR-52,=

and

DPR-68

'nspection

Conducted:

Inspector:

N.- Economos

Dec

er 14-18,

1992

at

Signed

Approved by:

J.

J

Bl ke, Chief

Mat

i

s

and Processes

Section

Eng neering

Branch

Division of Reactor Safety

ate Signed

SUMMARY

Scope:

This routine,'nannounced

inspection

was conducted

onsite in order to observe

weld. overlay activities

on recirculation

and residual

heat

removal-=(RHR) pipe

welds.

Areas

examined during this inspection

included completed

weld

overlays,

observation of surface

examination

on completed welds, fit up and

welding of structural

members

(beams)

to

a safety related

support,

review of

work specifications,

completed

work records,

surveillance reports,

and

certifications for material

and personnel

used

on this project.

Results:

The completed

weld overlays exhibited

good physical characteristics

and met

minimum dimensional

requirements.

Fabrication records

and completed

nondestructive

test records

were in order.

Welders,

NDE technicians

and

gC

inspectors

were adequately qualified to perform their assigned

tasks.

One violation was identified for failure to follow installation specification

requirements

paragraph

3.

9301200059

930112

PDR

ADOCK 05000259

PDR

REPORT DETAILS

1.

Persons

Contacted

Licensee

Employees

  • H. Bajestani,

Technical

Support Nanager

  • P. Burrell, Engineering

R. Craig, guality Assurance

  • H. Harrell, Operations

Hanager

"J. Johnson,

guality Assurance

E. Knuttel, Licensing Engineer

  • G. Pierce,

Nanager,

Site Licensing

T. Pitchford, Project Coordinator,

Pipe Replacement

  • J. Smithson, Hodifications Engineer

J. Wallace,

Compliance

Engineer

  • S. Wetzel, Site Licensing

Other licensee

employees

contacted

during this inspection

included .

engineers,

mechanics,

technicians,

and administrative

pei sonnel.

Contractors

General Electric, Nuclear

Energy

(GENE)

  • R. Cameron,

gC Nanage,

Level III Examiner,

NDE

L. Grycko, Welding Specialist

J.

Nason,

equality Engineer,

Project Hodifications

R. Lietzak,

gC Supervisor

E. Ridgell, Acting Compliance

Nanager

NRC Resident

Inspectors

  • C. Patterson,

Senior Resident

Inspector

  • Attended exit interview

2.

Weld Overlay on Recirculation

and Residual

Heat

Removal

Piping Unit 3

This report is

a continuation of work activities performed

by regional

inspectors

to observe

and monitor the progress

on the replacement

of

recirculation piping and certain sections of reactor water cleanup

piping.

Similar work performed

in this area

has

been

documented

in

Region Report 92-31,

a

~

Codes

and Standards

The applicable

codes

and standards

used and/or referenced

in the

application of weld overlay are

as follows:

American Society of Hechanical

Engineering Boiler and Pressure

Vessel

(ASHE),

BEPV)

Code Sections III, V, and XI, 1986 Edition.

ASME,

B&PY Code Section II (89); Section

IX, Latest Edition.

American National Standards

Institute

(ANSI)- B31. 1,

1967 Edition.

. American Society for Nondestructive

Testing

(ANST) SNT-TC-lA, 1984

(GE)

'E-NE-532-101-0792,

Standard

Overlay Design for the

Browns Ferry

3

Recirculation

and

RHR System

Welds

GE-25A5195 Rev.

0 BFN-3, Weld Overlay for Recirculation

and

RHR

Piping System

Welds

NUREG 0313

Rev. 2,'"Technical

Report

on Material Selection

and

Processing

Guidelines for

BWR Coolant Pressure

Boundary Piping."

I

US-NRC Generic -Letter 88-01,

"NRC Position

on

IGSCCC in

BWR

Austeni tic Stainless

Steel

Piping.

4

- Background:

The need to apply weld overlay on

some of the welds in the

recirculation

and

RHR systems

resulted

from the presence

of code

rejectabl,e,

intergranular

stress

corrosion cracks

(IGSCC), that

were found during volumetric inservice examinations.

When cracks

of significant magnitude

are discovered

in

BWR piping,

NUREG-0313,

Rev.

2, provides guidelines for repairs

or replacement

of the

affected piping that must

be performed before'he

plant can

be

returned to service.

The weld overlay reinforcement,

or repair, consists

of applying

weld metal

over the weld and for a specified

minimum distance

beyond the weld on both sides.

This is done completely

around the

outside surface of the pipe overlapping

each 'pass.

IGSCC-

resistant,

low-carbon, high-ferrite type 308L weld metal is used,

and the process

is usually performed with an automatic welding

machine

using the

Gas Tungsten

arc

(GTAW) process.

Weld overlay

is performed with cooling water in the pipe during welding.

Th'is

assures

high compressive

residual

stresses

on the pipe inside

diameter,

which tend to retard

IGSCC growth during future plant

operation.

Weld Overlay Design Criteria:

NUREG-0313,

Rev.

2, provides

two acceptable

overlay designs

which

are identified=-as

STANDARD overlay

and

DESIGN overlay.

The

STANDARD overlay, selected

by the licensee,

assumes

that the

cracks were"completely through the wall for 360

.

Accordingly the

overlay weldment is designed

to provide a,nominal

margin of 2.77

against limit load failure.

The method of calculation is based

on

methods

and criteria in IWB-3640, -3641,

3642 of ASHE Section XI.

.The controlling

GE specification,

GE-NE-523-101-0792

provided the

'echnical

basis for the design of the subject weld overlays

and

'he

analyses

performed.

These

included

a shrinkage

analysis to

determine

the influence of shrinkage

from the process

on the

piping systems

involved and

a flood-up evaluation to assure

structural integrity of the piping systems prior to and during the

weld overlay application.

By review of the

GE specification,

and other related

documents,

the inspector ascertained

that

GE had determined

the overlay

designs

were consistent

with- applicable

code

and regulatory

requirements,

that all shrinkage

stresses

associated

with the

welding process

were well below material yield strength

and

as

"such acceptable,

and that flood-up- evaluation

confirmed that net

section failure of the pipe at the cracked sections

would not

occur prior to and during weld overlay repair.

The actual

thickness of the overlays

was designed

so that

a factor of safety"

of 3.0 is maintained

against

net section collapse for normal

and

upset, load conditions,

and of 1,5 on emergency

and faulted load

conditions.

The

GE specification

also required the

use of 308L filler metal

welding wire with high delta ferrite content.

.Specific acc'eptance

criteria were established

on the ferrite content of the first

layer in that the average ferrite content

had to exceed

8FN with

no individual reading 'being less

than

5FN.

Production Welding {IP55050)

a.

Weld Operator Proficiency Review

The document

used-to describe

requirements for the fabrication of

field weld-.overlays is GE-25A5195,

Rev.

0.

As such, this

'pecification

referenced

the applicable

codes identified earlier

in this report; material

requirements;

qualification requirements;

general

welding requirements

which included process

control, heat

input distortion control, repairs,

and weld surface finish

conditions;

and

gA requirements.

Additional welding requirements

were included in GE's general

welding procedure

GWP-86-5.0

BF,

Rev.

1.

Weld procedure

specification,

WPS No. 8.8.20

- BF,

Rev.

B, with procedure

qualification records

PgR{s) 82-12-1

and 82-12-2 were used to

qualify welding operators

and-fabricate

the overlay weldments.

Metal deposition

was accomplished

with the machine

gas

tungsten'rc

welding

{GTAW), process

using pulse

mode- and remote control.

Filter metal

used,

was 308L low carbon stainless

steel wire, 0.035

inch diameter with ferrite content in the

9FN range.

In addition to the areas

addressed

above,

paragraph

3.5.3 of

specification

GE-25A5195

Rev.

0 provided requirements

for mockups,

simulating the production weldment configuration

and

space

b.

"

limitations, to be welded, with the approved welding procedure,

in

order to demonstrate

acceptable

proficiency.

This proficiency was

to be demonstrated

by each welding operator

scheduled

to work on

this project.

Paragraph

3.5.3.7, of the specification,

provides

an alternative

to mockup qualification.

This alternative

method requires that

the contractor

(GE) prepare

a formal document for the

TVA engineer

to review and approve prior to commencing production welding.

The

document is to contain

a detail record of the operator's

weld

overlay experience

or. recent experience

in operating the

same type

of equipment,

in- the

same environment

as

a weld'overlay,

and

as

a

minimum, provide adequate

description of the work experience

to

allow verification that mockup requirements

had

been

met for each

situation for which relief from mockup fabrication

w'as requested.

On December

17,

1992,

the inspector discussed

this area of the

specification with the cognizant

GE welding specialists

to

determine

which of the two options

was followed,

so

as to proceed

with the retrieval

and review of the. appropriate

records,

From

this discussion,

the inspector ascertained

that

GE had elected to

pursue

the alternative to mockup qualification approach.

Also at

this time, the inspector ascertained

that overlay proficiency-

mockup welds were performed in the lab shop but that this was done

on an, informal basis,

meaning that detail records of each

operator's activity/participation had not been generated.

Moreover,

the inspector

was informed that

TYA had performed

an

ultrasonic examination

on

a proficiency mockup,

but neither

GE nor

TYA could retrieve the record

because

the examiner

was

on vacation

and

was not expected

to return to work until sometime

near

the end

of December.

Additional discussions

with GE's cognizant quality

engineering

personnel

and supervision disclosed that. the formal

document,

described

in paragraph

3.5.3.7 of the subject

specification,

which was required

by the

GE specification,

to be

generated

by

GE and'ubmitted

to TVA for review and app'roval prior

to the start of production welding,

was never

issued,

On

December

18,

1992,

GE,issued

nonconformance

report

5-1BNH9-116

.

Rev.

0, to address

this finding and take appropriate

corrective

action.

At.the time of this finding seven of the nine'elds

had

been

completed.

On December

18,

1992 the inspector

informed the

licensee that

a failure to follow installation

specification/procedures

for activities affecting quality was

a

violation of Title Ten Code of Federal

Regulations,

Part

50

(10

CFR .50), Appendix B, Criterion V.

This violation was

identified as 50-296/92-43-01:

Failure to Implement Weld Overlay

Installation Specification

Requirements.

Inspection of In-Process

and Completed

Welds.

At the time of this inspection,

seven of the nine welds designated

for weld overlay had

been w'elded,

ground flat for inservice

"

inspection

purposes,

thicknesses

had

been

taken

and recorded,

and

Weld

5

liquid penetrant testing had'been

completed.

The'nspector

examined

each of the completed

welds for appearance,

surface

condition of the overlay material

near

and adjacent to the overlay

for evidence of undercut, identification, weld width, uniformity

and cleanliness.

Weld identification and results

obtained

from

fabrication records

and the specification, were

as follows:

Overall

Minimum

Thickness

Ferrite

0~ii

id

h

Thi

k

~lb

N

b

~li k

GR-3-03 .'lbow to Valve

6 %"

0.50

0.500"-0.705"

9.5

1/16"

GE-3-54

GR-3-60

Elbow to Pipe

7.0"

~

0.45"

0.472"-0.658"

9.6

3/64"

Elbow to Pipe

7.0"

0.45"

0.480"-0.578"

10.7

1/16"

GR-3-57

Valve to Pipe

6j"

Elbow to

Pump

. 7.0"

DSRHR-3-11

Elbow to Pipe

7.0"

GR-3-27

Pump to Pipe

7)"

0.45"

0.494"-0.674"

10.7

1/8"

0.109"

0.45"

0.493"-,0.708"

10.7

7/32"

0.50"

0.561"-0.797"

10.0

1/4"

0.40"

0.403"-0.634"

10.5

C.

A nonconformance

report

(NCR),

No. 067,

had

been

issued to

document

a

PT indication found in the toe of overlay GR-3-57,

extending out to the valve body.

Details of the indication were

documented

in

PT report OL-3-57-1.0-1-58 PT-l, dated

October

15,

1992.

The indication was

removed

by excavation to

a depth of less

than 0.035."

No repair welding was required.

Welds GR-3-54

and

-60 had undergone

baseline ultrasonic

examination to satisfy

ASHE Code Section

XI requirements.

The

examination

involved automatic

and manual

scanning

techniques,

using

0

,

60 L, 70

RL and

OD creeping

wave 85

transducers.

No

indications greater

than

20% of .full screen

height were

observed/documented.

Those indication that were observed

in the

greater

than

20% range

were evaluated/dispositioned

as surface

irregularities resulting in nonrelevant lift-offtype indicatioris.

Procedures

and Documents

Reviewed

The inspector

reviewed the following documents

and procedures

for

technical

content,

completeness

and accuracy.

DCN-W18848

019155A

Weld Overlays for Unit 3

RHR and Recirculation Piping

Safety Assessment/Safety

Evaluation for Temporary

Supports

GE-TVA-5.0 Rev.

Cleanliness

Control

6

II

N-UT-24 Rev.

8

Ultrasonic measurement

of Wall Thickness

TVA-25.0

Rev.

C. General

Visual Examination

TVA-26.0

Rev.

B. General

Liquid Penetrant

Examination

In addition to the above,

the inspector reviewed

GE's Special

',

Process

Manual, containing weld procedure

specifications

and

associated

procedure qualification records

(PAR) used for the

overlay welds

and other welding in progress

at the time of this

.

inspection.

Through this review, the inspector

noted that the two

. PgR(s),

used for the qualification of weld procedure specification .,

(WPS-8.8.20

-

BF Rev. B), used

on the overlays,

were missing from

the manual.

This occurred*even

though the manual

was

a controlled

copy and

had

been

reviewed

by the appropriate

personnel.

Upon

further review,

GE determined that

PgRs

were missing from two

other weld procedure specifications,

WPS-3.3.6-BF

and WPS-8.8. 13-

BF.

Following a document search/investigation

and through

discussions

with document-control

management

(DCRH),

GE determined

that the

PgRs

had

been incorrectly removed

from the

WPS package

by

OCR'ersonnel,

and mis-filed with the general

welding procedures.

Copies of the missing

P(Rs were

made available for inclusion in

the subject manual,

which corrected

the problem.

GE instructed

DCRH personnel

on the proper handling of these

documents.

d.

Record

Review

For each of the seven

completed

weld overlays,

the inspector

reviewed the fabrication records

including travelers, joint and

special

process

control sheets

and non'destructive

examination

records

to assure

that critical inspections,

measurements,

and'old

points, etc

, were being performed in the prescribed

manner

and

on

a timely basis.

In addition, the inspector

reviewed

performance qualification records for fifteen (15), weld operators

who participated

in the weld overlay application.

All had

attended

the prejob briefing held

on September

3,

1992

and

had

qualified to weld under the applicable

weld specification.

guality records

in the form of 'certified material test reports for

the filler metal

used

were reviewed

and found to be in order-

these

were

as follows:

ER308L

Size

0. 035'S

Heat

XT6207

Ferrite

No.

'ther quali'ty records

reviewed'included

those for liquid penetrant

. materials

and ultrasonic equipment listed below:

Liquid Penetrant:

~Aent

Cleaner

Penetrant

1

Developer

Ultrasonics:

Manufacturer

Sherwin/OR-60

Sherwin/DP-40

Sherwin/0-100

Batch

No.

224-F4. and 24-L4

18-D1

,126-BG

Instrument

Model:

Tran sducers

USK70

S/N E17127

S/N E16545

S/N 54304,

0.5" diam.

4KHz,

0

54303,

2(5x10)

2MHZ

Calibration Blocks

BL O'BF-83

Simulator 6026-83

Within the areas

examined violations or deviations

were not identified

except for the one identified in sub-paragraph

3; a.

Pipe Anchor Support

- Penetration

X14, Unit 3

{IP55100)

Other work in progress

at the time of this inspection

included the

fabrication of anchor ring

No. 3-,47B406-273

and pipe anchor support

structure

in penetration X14.. The support

and anchor ring will secure

the six inch (6"), reactor water cleanup

(RWCU) pipe going through this

penetration.

This work was being performed

under Design

Change Notice

(DCN), W18484. and

Work Plan 3783-92.

The applicable. drawing was

No. 3-48E1032-2.

Work was being documented

on Traveler

N X14ANC.

The

controlling standard for fabrication

and erection

was the AISC 8th

. Edition and TVA's specification

G-29C.

NDE requirements

for structural

steel joints called for visual inspection

per G-.29C.

The 'inspector

observed

the fit-up.of horizontal

beam

No.

9 (WBx3lx4'-6") to embed

No.

EMB-3-48NI008-126.

The

beam

was fit-up and tack welded in place,

well

within the applicable tolerance,

The inspector

reviewed

an

NCR issued

to document rejectable

indications

(gouges)

in the two embeds,

No. 3-

48N1008-126

and

-128, in the area of the penetration.

The gouges

were

weld repaired

and ground flush.

Within the areas

inspecte'd violations

or deviations

were not identified.

'

8

Inspection

on Completed

Welds:

(57060PT),

(57050VT)

In addition to the above work effort,

GE was involved in the

installation/replacement

of small

bore piping in the

RWCU system located

in'the non-regenerative

heat

exchanger,

room and the

pump room.

Work was

being performed

under:OCN

No. M17810A, Project

No. 92NJ815500.

In the

heat exchanger

room, the inspector

observed

visual

and liquid penetrant

examination of five (5) welds.

Twd of these

were

on instrument lines,

and three

on vent and drain line', of the

RWCU system.

Meld

identification and location were

as follows.

Instrument Line

Weld

G001

G015

G024

G025

G030

MAPS

MP370392-1

Rev.

0

WP370392-15

Rev.

1

WP370592-24

Rev..O

WP370592-24

Rev.

0

WP370592-24

Rev.. 0

Size

One Inch

'ne

Inch

, One Inch

One Inch

'ne

Inch

~Te

Socket

Weld

Socket

Weld

Socket

Wel.d

Socket

Weld

Socket

Weld

~lne ection

VT/PT

VT/PT

VT/PT

YT/PT

YT/PT

Welds

G025

and

G030 exhibited rejectable

PT -indications that were

removed

by grinding,

and weld repaired.

A subsequent

PT examination

showed both welds were acceptable.

guality records

including those of

liquid penetrant materials,

identified earlier in this report,

and

examiner certifications

were reviewed for- completeness,

accuracy

and

compliance with applicable

standards.

Within the areas

inspected,

violations or deviations, were not

identified.

Review of Onsite Audit Activities, (40704) Unit 3

The inspector

reviewed reports of audits/surveillance

p'erformed

by

GE

'and

TVA on work activities related to the pipe replacement

project

and

the ongoing -weld overlay effort.

The review included reports of audits

performed

from June to. November of 1992.

Activities audited

by both

organizations

included machining, welding, review of field generated

records (travelers),

material certifications,

review of radiographs,

weld repairs,

an'd implementation of the

gA program requirements.

Problem areas identified were'nvestigated

and dispositioned

in

a

satisfactory

and timely manner.

Within the areas

inspected,

violations or deviations

were not

identified.

7.

Exit Interview

d results

were summarized

on December

18,

1992,

h

1

Th 'o

d

b d

ssed

in detail the inspection results

d 'th'

t'o

o

'

d 'his report.

Dissenting-comments

were

information is not contained

in

is repor

.

- not received

from. the licensee.-

(Open) Violation 50--396/92-43-01:

Failure to Impl ement Meld, Overlay

Specification

Requirements

'