GSl-191 Commitment Changes
ML18036A188
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 01/31/2018
From: Flaherty M
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML18036A188 (5)


Text

,A

  • ' 7

~~ Exelon Generation January 31, 2018 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Mark D. Flaherty Site Vice President Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657

' 410 495 5200 Office 443-534-54 75 Mobile www.exeloncorp.com mark.flaherty@exeloncorp.com 10 CFR 50.46 Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2

Subject:

Reference:

Renewed Facility Operating License Nos. DPR-53 and DPR-69 NRC Docket Nos. 50-317 and 50-318 Calvert Cliffs GSl-191 Commitment Changes

1.

Letter from M. D. Flaherty (Exelon) to Document Control Desk (NRC), dated May 2, 2016, Calvert Cliffs GSl-191 Resolution Plan In Reference 1, Calvert Cliffs Nuclear Power Plant made five commitments on our risk-informed resolution to Generic Safety Issue 191 (GSl-191) and response to Generic Letter 2004-02. Two of these commitments now need to be revised to tie their completion to the approval of our upcoming GSl-191 license amendment request.

This reflects that the Nuclear Regulatory Commission approval might involve additional plant changes or insulation remediation to be accomplished.

Attachment (1) shows the commitment change for the two commitments being revised.

Attachment (1) also shows the entire revised list of GSl-191 commitments.

Should you have questions regarding this matter, please contact Mr. Larry D. Smith at (410) 495-5219.

Document Control Desk January 31, 2018 Page 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on January 31, 2018.

Respectfully, gJ-.,S) 1--l~

Mark D. Flaherty Site Vice President MDF/KLG/bjm

Attachment:

(1)

List of Regulatory Commitments cc:

NRG Project Manager, Calvert Cliffs NRG Regional Administrator, Region I NRG Resident Inspector, Calvert Cliffs S. Gray, MD-DNR

ATTACHMENT (1)

LIST OF REGULATORY COMMITMENTS Calvert Cliffs Nuclear Power Plant January 31, 2018

ATTACHMENT (1)

LIST OF REGULATORY COMMITMENTS The table below lists the action committed to in this submittal. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.*

E..

C x1stmg omm1tments to b Ch e

ange d Regulatory Commitment Date Calvert Cliffs will complete any necessary insulatio.n 5/1/2018 (Unit 1) replacements or remediation, or other identified plant changes no later than the 2018 refueling outage for Calvert Cliffs Unit 1. This completion date is predicated on the successful completion of our Option 2 approach.

Calvert Cliffs will complete any necessary insulation 5/1/2019 (Unit 2) replacements or remediation, or other identified plant changes no later than the 2019 refueling outage for Calvert Cliffs Unit 2. This completion date is predicated on the successful completion of our Option 2 approach.

Revised Commitments Regulatory Commitment Completion Calvert Cliffs will complete any necessary insulation No later than the second refueling replacements or remediation, or other identified plant outage for Unit 1 following NRG changes for Calvert Cliffs Unit 1. This completion date is issuance of the Safety Evaluation predicated on the successful completion of our Option 2 on the Calvert Cliffs Option 2b approach.

GSl-191 license amendment request and acceptance of the Calvert Cliffs Generic Letter 2004-02 final submittal.

Calvert Cliffs will complete any necessary insulation No later than the second refueling replacements or remediation, or other identified plant outage for Unit 2 following NRG changes for Calvert Cliffs Unit 2. This completion date is issuance of the Safety Evaluation predicated on the successful completion of our Option 2 on the Calvert Cliffs Option 2b approach.

GSl-191 license amendment request and acceptance of the Calvert Cliffs Generic Letter 2004-02 final submittal.

1

ATTACHMENT (1)

LIST OF REGULATORY COMMITMENTS Calvert Cliffs Entire GSl-191 Commitments Regulatory Commitment Calvert Cliffs will complete any necessary insulation replacements or remediation, or other identified plant changes for Calvert Cliffs Unit 1. This completion date is predicated on the successful completion of our Option 2 approach.

Calvert Cliffs will complete any necessary insulation replacements or remediation, or other identified plant changes for Calvert Cliffs Unit 2. This completion date is predicated on the successful completion of our Option 2 approach.

Calvert Cliffs will establish plant-specific in-vessel debris limits for Calvert Cliffs Units 1 and 2 in accordance with the approved WCAP-16793 methodology. The plant-specific in-vessel debris limits will be submitted with the Calvert Cliffs final submittal for GL 2004-02.

If the Calvert Cliff's Option 2b risk-informed approach is not successful for resolving the GSl-191 issue, then Calvert Cliffs will submit a new resolution plan.

If the Calvert Cliff's Option 2b risk-informed approach is successful for resolving the GSl-191 issue, then Calvert Cliffs will submit a final updated supplemental response to support closure of GL 2004-02 for Calvert Cliffs Units 1 and

2.

2 Completion No later than the second refueling outage for Unit 1 following NRG issuance of the Safety Evaluation on the Calvert Cliffs Option 2b GSl-191 license amendment request and acceptance of the Calvert Cliffs Generic Letter 2004-02 final submittal.

No later than the second refueling outage for Unit 2 following NRG issuance of the Safety Evaluation on the Calvert Cliffs Option 2b GSl-191 license amendment request and acceptance of the Calvert Cliffs Generic Letter 2004-02 final submittal.

No later than three months after NRG issuance of the Safety.

Evaluation on the South Texas Project Risk-Informed GSl-191 Pilot Project and the Safety Evaluation on WCAP-17788, whichever is later.

No later than three months after NRG issuance of the Safety Evaluation on the South Texas Project Risk-Informed GSl-191 Pilot Project and the Safety Evaluation on WCAP-17788, whichever is later.

No later than three months after NRG issuance of the Safety Evaluation on the South Texas Project Risk-Informed GSl-191 Pilot Project and the Safety Evaluation on WCAP-17788, whichever is later.