ML18033B555

From kanterella
Jump to navigation Jump to search
Notice of Violation from Insp on 900916-1015.Violation Noted:Failure of Supervisor to Sign Hold Order Contrary to Workplan 0252-90 & Failure to Perform Adequate Impact Evaluation
ML18033B555
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 11/08/1990
From: Wilson B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18033B554 List:
References
50-259-90-29, 50-260-90-29, 50-296-90-29, NUDOCS 9011190184
Download: ML18033B555 (4)


Text

ENCLOSURE 1

NOTICE OF VIOLATION Tennessee Valley Authority Browns Ferry 1, 2, and 3

Docket Nos.

50-259, 50-260, and 50-296 License Nos.

DPR-33, DPR-52, and DPR-68 During the Nuclear Regulatory Commission (NRC) inspection conducted on September 16 -

October 15,

1990, a

violation of 'RC requirements was identified.

The violation involved failure to comply with procedures for an adequate hold order, boundary while conducting work activities.

In accordance with the "General Statement of Policy and Procedure for NRC Enforcement

'ctions,"

10 CFR Part 2, Appendix C (1990),

the violation is listed below:

Technical Specification, Section 6.8.1, Procedures, requires that written procedures shall be established, implemented and maintained covering those recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.

Appendix A of Regulatory Guide 1.33 includes administrative procedures and procedures for controlling repair activities of safety-related equipment.

Site Directors Standard Practice (SDSP)-7.9, Integrated Schedule and Work Control, Section 6.4. 1, requires that an impact evaluation be performed on all activities that have potential for affecting equipment operations'hich may affect the safe and reliable operation of the unit except as specifically exempted.

Attachment C to SDSP-7.9 is used to document that evaluation.

Section 7.0 specifies the Tagging and Support Coordinator's duties in reviewing, correcting, and issuing hold order boundaries.

SDSP-14.9, Equipment Clearances, Section

6. 1 provides both general and special requirements for removing equipment from service to allow work to safely proceed.

Contrary to the above,. these requirements were not met for the following two examples:

l.

On August 25,

1990, the requirements were not met in that Wor kplan 0252-90 was determined to be in progress without appropriate supervision having signed onto an existing hold order.

2.

On September 16,

1990, the requirements were not met in that an inadequate impact evaluation resulted in licensee personnel cutting energized electrical leads that were part of the D Diesel Generator initiation logic circuits.

This"activity resulted in an'nplanned engineered safety feature actuation.

This is a, Severity Level IV Violation (Supplement I) ap'plicable to all three Units.

'~>1290g F'DR gag~~

>0210:=;

Q K ()qp()g~,-~

PZlg

Enclosure 1

Pursuant to the provisions of 10 CFR 2.201, you are hereby required to submit a

written statement or explanation to the Nuclear Regulatory Commission, ATTN:

Document Control

Desk, Washington,

'DC

20555, with a

copy to the Regional Administrator, Region II, and a

copy to the NRC Resident Inspector, Browns Ferry, within 30 days of the date of the letter transmitting this Notice.

This reply should be clearly marked as a "Reply to a Notice of Violation" and should include:

(1) admission or denial of the violation, (2) the reason for the violation if admitted, (3) the corrective steps which have been taken and the results

achieved, (4) the corrective steps which will be taken to avoid further violations, and (5) the date when full compliance will be achieved.

Where good cause is shown, consideration will be given to extending the response time.

FOR THE NUCLEAR REGULATORY COMMISSION TVA Projects t

Dated at Atlanta,,georgia thi s gA day of Pii~r 1990