ML18030B154

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/86-03,50-260/86-03 & 50-296/86-03 on 860113-17.Violations Noted:Failure to Follow Procedures for Housekeeping in Radiation & Contaminated Areas & for Removal of Temporary Attachments on Recirculation Sys Pipe
ML18030B154
Person / Time
Site: Browns Ferry  
Issue date: 02/24/1986
From: Blake J, Coley J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18030B152 List:
References
50-259-86-03, 50-259-86-3, 50-260-86-03, 50-260-86-3, 50-296-86-03, 50-296-86-3, GL-84-11, IEB-83-02, IEB-83-2, NUDOCS 8603040375
Download: ML18030B154 (15)


See also: IR 05000259/1986003

Text

gA~ "~ou.

(4

Mp0

I

0O

Op

Op

+>>*<<+

r

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MAR IETTA ST R E ET, N.W.

ATLANTA,GEORGIA 30323

Report Nos.:

50-259/86-03,

50-260/86-03,

and 50-296/86-03

Licensee:

Tennessee

Valley Authority

6N38

A Lookout Place

1101 Market Street

Chattanooga,

TN

37402-2801

Docket Nos.:

50-259,

50-260

and 50-296

License Nos.:

DPR-33,

DPR-52,

and

DPR-68

Facility Name:

Browns Ferry 1, 2, and

3

Inspection

Conducted:

January

13-17,

1986

Inspector:

J. L.

Approved by:

J. J.

B ak

,

ection Chief

Engine ri g Branch

Divis on of Reactor Safety

ate Signe

c(

Da

e Signed

SUMMARY'cope:

This routine,

unannounced

inspection entm led 35 inspector-hours

on site

in the

areas

of observation

of liquid penetrant

examinations,

review of

radiographic film, followup

on

items of noncompliance

and unresolved

items,

followup on IE Bulletins, and followup on inspector identified problems.

Results:

Two violations

were identified - Failure to follow procedures

for

housekeeping

in radiation

and contaminated

areas

- paragraph

5.a.

and Failure to

follow procedure

for removal of temporary

attachments

on recirculation

system

pipe spool piece - paragraph

5.b.

BE 0S040m5

8~0228

PDR

ADQCK 05000259

8

PDR

REPORT DETAILS

Persons

Contacted

Licensee

Employees

  • R. L. Lewis, Browns Ferry Nuclear Plant

(BFNP), Plant Manager

  • J. R. Nebrig,

BFNP, Modification Supervisor

  • B. C. Morris, BFNP, Compliance Supervisor
  • R. Latimer, Inservice Inspection (ISI) Supervisor
  • 0. L. Butler, ISI Technical

Section

Engineer

  • E. D. Crane,

ISI Programs

Section

Engineer

Other

licensee

employees

contacted

included

engineers,

technicians,

and

office personnel.

NRC Resident

Inspectors

  • G. L. Paulk, Senior Resident

Inspector

  • C. A. Patterson,

Resident

Inspector

  • Attended exit interview

Exit Interview

The inspection

scope

and findings were summarized

on January

17,

1986, with

those

persons

indicated in paragraph

above;

The inspector

described

the

areas

inspected

and

discussed

in detail

the

inspection

findings listed

below.

No dissenting

comments

were received

from the licensee.

(Open) Violation 260/86-03-01,

Failure to Follow Procedures

for Housekeeping

in Radiation

and Contaminated

Areas - paragraph

5.a.

(Open) Violation 260/86-03-02,

Failure to Follow Procedure

for Removal of

Temporary Attachments

on Recirculation

System

Pipe

Spool

Piece - paragraph

5.b.

(Open)

Unresolved

Item 260/86-03-03,

Radiographic

Evaluation of Defects Fail

to Indicate Basis of Acceptance - paragraph 6.b.(2).

The licensee

did not identify as proprietary

any of the materials

provided

to or reviewed

by the inspector during this inspection.

Licensee

Action on Previous

Enforcement Matters

(92702)(92701B)

Units 1, 2,

and

3

(Closed)

Violation

259,

260,

296/82-33-01,

Inadequate

Nondestructive

Examination Procedure.

TVA's letter of response

dated

November 24,

1982

has

been

reviewed

and determined

to be acceptable

by Region II.

The inspector

held discussions

with the ISI project supervisor

and examined

the corrective

actions

as stated

in the letter of response.

The inspector

concluded that

TVA had determined

the full extent of the subject

noncompliance,

performed

the necessary

survey

and follow-up actions to correct the present

conditions

and

developed

the necessary

corrective actions

to preclude

recurrence

of

similar circumstances.

The corrective actions identified in the letter of

response

have

been

implemented.

(Closed)

Violation

260,

296/84-11-01,

Reactor

Vessel

Support

Skirt

Examination.

TVA's letter of response

dated

May 24, 1984,

has

been

reviewed

and

determined

to

be

acceptable

by

Region II.

The

inspector

held

discussions

with the

ISI project supervisor

and

examined

the corrective

actions

as stated

in the letter of response.

The inspector

concluded that

TVA had determined

the full extent 6f the subject

noncompliance,

performed

the necessary

survey

and follow-up actions to correct the present

conditions

and

developed

the

necessary

corrective actions

to preclude

recurrence

of

similar circumstances.

The corrective actions identified in the letter of

response

have

been

implemented.

(Closed) Violation 259/84-31-01,

Failure to Establish

gC Hold points

and to

Use gualified Visual

Examiners for Performing

Dimensional

Verification on

Critical Systems,

Structures

and Components.

TVA's letter of response

dated

October

19,

1984,

has

been

reviewed

and

determined

to

be

acceptable

by

Region II.

The

inspector

held

discussions

with modifications

project

engineer

and

examined

the corrective actions

as

stated

in the letter of

response.

The inspector

concluded that

TYA had determined

the full extent

of the subject

noncompliance,

performed

the necessary

survey

and follow-up

actions

to correct

the

present

conditions

and

developed

the

necessary

corrective

actions

to preclude

recurrence

of similar circumstances.

The

corrective

actions

identified

in

the letter

of

response

have

been

implemented.

(Closed)

Violation 259/84-31-02,

guality

Assurance

Breakdown

in

Work

Performed

on Unit

1 Overlay Repair Welds.

TVA's letter of response

dated

October

19,

1984,

has

been

reviewed

and

determined

to

be

acceptable

by

Region II.

The

inspector

held

discussions

with modifications'roject

engineer

and

examined

the corrective

actions

as

stated

in the letter of

response.

The inspector

concluded that

TVA had determined

the full extent

of the subject

noncompliance,

performed

the necessary

survey

and follow-up

actions

to correct

the

present

conditions

and

developed

the

necessary

corrective

actions

to preclude

recurrence

of similar circumstances.

The

corrective

actions

identified

in

the letter

of

response

have

been

implemented.

(Closed)

Violation 260/85-33-01,

Visual

and

Ultrasonic

Examination

of

Overlay

Repair

Weld

GR-2-15

Were

not Adequately

Controlled to Insure

a

Meaningful Examination.

TVA's letter of response

dated August 19, 1985,

has

been

reviewed

and determined

to

be acceptable

by Region II.

The inspector

held discussions

with the ISI project supervisor

and examined

the corrective

actions

as stated

in the letter of response.

The inspector

concluded that

TVA had determined

the full extent of the subject

noncompliance,

performed

the necessary

survey and follow-up actions to correct the present conditions

and

developed

the

necessary

corrective actions

to preclude

recurrence

of

similar circumstances.

The corrective actions identified in the letter of

response

have

been

implemented.

(Closed)

Unresolved

item 259, 260/81-07-04,

ISI Schedule.

TVA's Browns Ferry

ISI schedule

has

been

incorporated

in Tables

A, 8,

C,,

0

5

E to the ISI

program

(SI-4.6.G

Rev.

7, dtd 2-8-85).

This program outlines details for

planning

and

performing

the first

10 year

inservice

nondestructive

examinations

of Browns Ferry Nuclear Plant,

American Society of Mechanical

Engineers

(ASME)

Code,

class I,

2

and

3

components.

This

program

incorporates

Units I, 2,

and

3 into concurrent

cycle (letter to

NRC

LOO-801231-705)

beginning

July I,

1980.

By extending

the

inspection

interval

one year

(IWA-2400), the

fO month

inspection

cycle will begin

July I, 1981.

4.

Unresolved

Items

~

Unresolved

items

are matters

about

which more information is required to

determine

whether it is acceptable

or may involve violations or deviations.

New unresolved

items identified during this

inspection

are

discussed

in

paragraph 6.b.(2).

Independent

Inspection Effort - Unit 2"

The inspector

conducted

a

general

inspection

of the reactor building to

observe

activities

such

as

housekeeping,

welding, material

identification

and control

and material storage.

'a

~

Housekeeping

and Material Storage

TYA's Operational guality Assurance

Manual, Part II, Section

1.2 states

that:

"housekeeping

encompasses

all activities related

to control of

cleanliness

of facilities, cleanliness

of material

and equipment, fire

prevention,

fire protection,

control

of

access,

protection

of

equipment,

radioactive

contamination

control,

and

storage

of solid

radioactive waste."

Examples

of

poor

housekeeping

in

the

areas

defined

above

were

identified by the inspector.

Listed below are

the specific locations

and discrepancies

observed:

(I)

Unit 2,

dress

out

area

on

second

floor of reactor

building:

Anti-C clothing, clean air respirators,

tape

and trash

observed

on

floor and

benches.

This

area

was

examined

at the start

and

completion

of the

work shift with

no

apparent

improvement

identified.

(2) ,Unit 2, drywell access

room:

Trash

on floor throughout

access

room,

however,

one

area specifically roped off and

posted

as

a

"Highly Contaminated

Area,"

had

an

unusual

amount

of dirt,

grinding dust,

used grinding wheels, tools,

and several cigarette

butts

on the floor and

on supports

in the area.

The inspector

held

discussions

with the

drywell

health

physicist

and

his

supervisor

to determine if they were

aware that personnel

may

be

smoking in a highly contaminated

area or what would happen to the

loose contamination if a air hose

was to break in this area.

The

supervisor

stated

that the cigarette

butts

probably

had entered

the access

room from the

second floor as

a result of removing the

ceiling plugs.

The inspector

inquired as to how long it had

been

since

the

plugs

had

been

moved

and

discovered

that this

had

occurred several

months prior.

The health physicist also stated

that the housekeeping

conditions

observed

in the access

rooS had

been reported

several

times

and

no

action

had

been

taken

to

have

the

area

cleaned.

TVA's

BFNP

Standard

Practice

No. BF-14.3 requires all assigned

areas

to be

inspected

at least

once

a month for housekeeping

requirements

and

documented

on

a

Form 96.

(3)

Onit

2 drywell:

Among items

observed

laying on the floor was

a

partially filled aerosol

can of highly flaomable

DUBL CHEK,

Cleaner/Remover

60.

This item was

observed

laying

on the floor

during the inspector's

morning entry

and at the completion of the

work shift.

TVA's

BFNP Standard

Practice

No. BF-14.36 states

that,

"Aerosol

cans

shall

be stored

in flammable-liquid storage

cabinets

or in an area

away from all sources

of heat

and each

area

where

flammable

or combustible

liquids are stored

or dispensed

shall

be

marked, with danger

signs

stating

no

smoking

or

open

flames."

(4)

Unit

2 drywell:

Vertical

run of 6-inch reactor water clean

up

(RWCU) pipe at point where

RCWU connects

to the 20-inch residual

heat

removal

(RHR)

system.

A liquid penetrant

examination

had

been

performed

by

BFNP quality control examiners

on welds located

on

a platform above

the point where the

RWCU connects

to the

RHR.

The examiner

had

completed

the examination,

however liquid penet-

rant material

was left running

down

RWCU piping two platforms

below the

examination

area.

TVA's liquid penetrant

procedure

No. N-PT-1 requires,

in part, that after final examination,

the

test surface shall

be cleaned with one of the approved cleaners."

Items listed in paragraphs

5.a. (1) thru 5.a.(4)

were reported

to

the licensee

as

examples

in violation 50-260/86-03-01,

Failure to

Follow Procedure

of Housekeeping

in Radiation

and

Contaminated

Areas.

b.

Welding and Material Identification and Control

(55050)

The inspector

observed

two fillet welds

each approximately 1-inch long

welded on a pipe spool piece

between recirculation

system welds

GR-2-54

and GR-2-55.

C.

The fillet welds

appeared

to have

been

associated

with some

form of

temporary

attachments

that

had

not

been

removed

in accordance

with

TVA's General

Specification

G-28 or

TVA's

BFNP, Modification and

Addition Instruction ¹22.

The inspector also observed that one of the

welds

had

been

welded

on the spool

piece longitudinal weld seam.

This

installation practice is not condoned

by the

BFNP welding department.

The inspector

held discussions

with

a welding department

supervisor

and

a field engineer

to determine

what activity would have

been

needed

for the temporary attachments.

The above discussions

revealed that

no

temporary

attachments

had

been

authorized

for installation

on this

pipe.

The inspector

reported

this

item

as violation 260/86-03-02,

Failure to Follow Procedures

for the

Removal of Temporary Attachments

on Recirculation

System

Piping

Spool

Piece.

However,

during

the

inspector's exit interview with BFNP management,

the inspector

informed

the licensee

that closure of this item will be based

on the licensee

determining

the

source

of this welding

and taking corrective action

that will prevent

unauthorized

welding

and

possibly

the

use

of

incompatible materials.

During

the

inspector

surveillance

of the

reactor

building,

the

medical/fire

alarm

was activated.

However,

the inspector

could not

hear the public address

(PA) system.

The inspector also observed

that

no one

was responding

to the alarm.

Licensee

personnel

were questioned

at

the radiation

control

points" on the first and

second

floor to

determine if they

had

received

additional

instructions

that

the

inspector

may have missed.

However, the inspector

found that

none of

these individuals

had

heard

the

PA system.

The individuals questioned

by the inspector

considered

this normal and, therefore,

no longer take

the

alarms

seriously,

unless

someone "comes

and

gets

them.

The

inspector left Unit

2 reactor

building

and

went to the

resident

inspectors

office and discovered

that the alarm

was for a fire in the

Unit 2 reactor building.

The inspector also discovered that

NRC has

an

open

item with the

licensee

on this matter

based

on

a previously

observed

event.

This item was discussed

in detail with BFNP management

during the exit meeting.

However,

the licensee's

position is that

a

response

team

could get

personnel

out of an

area

before

they could

become

victims of an unusual

event

is not

a position

shared

by the

inspector

and defeats

the purpose of 'alarms.

Resolution of this item

wi 11

be

handled

by the present

open

item and the resident

inspectors

awareness

that this discrepancy

has

not been properly addressed

by the

licensee.

Within the areas

examined,

no violations or deviations

were observed

except

as noted in paragraphs

5.a.

and 5.b.

above.

6.

Nondestructive

Examination (Unit 2)

During the

week of January

13-17,

1986,

the licensee

did not perform any

inservice

inspection

examinations.

The inspector,

however,

was able to

audit examiners

by observing liquid penetrant

examinations

on safety-related

piping

where

arc strikes

had

been

removed

and

by reviewing previously

accepted

radiographic film on Unit 2 piping welds.

The applicable

code for

the examinations

observed

is the American Society of Mechanical

Engineers

(ASME) Code,

Sections

V and XI, 1974 edition with addenda's

through

summer

1975.

a.

Liquid Penetrant

Examination

(57060)

Procedure

review

(2)

The inspector

reviewed

the licensee's

liquid penetrant

procedure

No. N-PT-l, Revision 6, "Liquid Penetrant

Examination

Using the

Color Contrast

Solvent

Removable

Method," to determine if the

licensee's

examination

procedure

had

been

qualified

and

was

consistent

with the applicable

code requirements

in the following

areas:

specific

types of penetrant

materials

used,

materials

analyzed

for sulfur and total

halogens,

pre-examination

surface

cleaning,

minimum drying time specified,

dwell times specified,

method for removing

penetrant

prescribed,

method of developer

application,

time period specific before final interpretation,

light intensity prescribed,

and acceptance

criteria specified.

Observation of liquid penetrant

examinations

The inspector

observed

the 'Tiquid penetrant

examinations

on weld "

joint numbers

DSRHR-2-9

and

KR-2-37.

The examination

included

approximately

2 inches

of base

metal

on each

side of each weld.

The entire

weld areas

were

examined

because

so

many arc strikes

had

been

removed that it became difficult to separate

the

ground

areas.

The inspector

observed

the examination to determine if the

examiner

performed

the following procedure

parameters

correctly:

surface

preparation/cleaning

method,

penetrant

application,

minimum dwell observed,

temperature

of surface within procedure

qualification, penetrant

removal, drying time, developer applica-

tion, developing time, evaluation of indications,

and post exami-

nation cleaning

was performed.

Within this area of examination,

no violation or deviation was observed.

b.

Radiographic

Examination

Procedure

review

The

inspector

reviewed

the

licensee's

radiographic

procedure

No. N-RT-1, Revision 3, "Radiography

Examination of Nuclear

Power

Plant

Components,"

to ascertain if the procedure

was approved

and

consistent with the applicable

code requirements

in the following

areas:

weld surface

condition,

type of material

radiographed,

material

thickness

range,

type of radiation

source,

effective

focal

spot or effective

source

size, film type,

minimum source

distance,

type

and thickness

of intensifying screens

and filters,

film density

1 imits,

use

of

locati on

markers,

geometrical

unsharpness

limitations, and selection

and

use of penetrameters.

Review of radiographs

The inspector

reviewed radiographic film for the following welds:

Weld Joint

Identification

DSRWCU-2-7

DSRWCU-2-4

2-TWL-9-10x1

2-TWL-1-10X1

DSRHR-2-5

DSRHR-2-5A

Size

6" diameter

x .432" thickness

6" diameter

x .432" thickness

2" diameter

x .218" thickness

2" diameter

x .218" thickness

24" diameter

x 1.50" thickness

24" diameter

x 1.50" thickness

The inspector

reviewed the above film to verify the following:

Penetrameter

type, size,

placement

Penetrameter

sensitivity

Film density, density variation-

Fi 1m identification

Film quality

Weld coverage

Interpretation of radiographic indications

During the above review, the inspector

noted that the film readers

sheet

for completed

weld No.

DSRHR-2-5A indicated that

each film

segment

was rejected

and the authorized

Nuclear Inspector also

had

not

signed

the

sheet.

The inspector

was

then

shown

a

sheet

entitled

"Weld

DSRHR-2-5A

RT Defect Evaluation,"

however,

the

only conclusion

reached

on this sheet

was that the indication was

a defect that

was

not located

at the

pipe I.D. the

ASME Code,

Section

XI, Article

IWA-3000 states

that;

"Where

acceptance

standards

for a particular

component

or examination

category

are

in the

course

of preparation,

evaluation

shall

be

made of any

indications

detected

during any inservice examination that exceed

the acceptance

standards

for materials

and welds specified in the

Section III edition applicable

to the construction

of the

com-

ponent in order to determine disposition.

Such disposition shall

be subject

to review

by the enforcement

authori ty having juris-

diction at the plant site."

The defect that the inspector observ-

ed

was over

30 inches of lack of fusion.

The inspector

informed

the

licensee

that

he would like to

see calculations

ipdicating

that the weld was acceptable

for use-as-is.

The licensee

stated

that, these results

were not available at the

BFNP, but would have

to be sent

from Chattanooga,

Tennessee.

This item was reported

as

Unresolved

Item 260/86-03-03,

Radiographic

Evaluation of Defects

Fail to Indicate Basis of Acceptance.

Within the areas

examined,

no violations or deviations

were identified.

IE Bulletin (92703) Units

1

8

2

(Closed)

IE Bulletin 83-02, Intergranular

Stress

Corrosion Cracking

(IGSCC)

in Large

Oi ameter

Recirculation

System

Piping at

BWR Pl ants.

TVA has

completed all actions

required

by Bulletin 83-02

as reported in TVA letters

to

NRC, Serial

No. A27-840522-016

dated

May 22,

1984 for Unit

1 and Serial

No. L44-850305-812

dtd March 5,

1985 for Unit 3.

All subsequent

licensee

actions

addressing

IGSCC should

be in accordance

with Generic Letter 84-11.

Within the area

examined,

no violations or deviations

was identified.

Inspector

Followup Items

(92701B) Units 1, 2,

and

3

(Closed)

IFI 259,

260,

296/83-41-04,

Verification of Adequacy of Rompas

Blocks.

The

inspector

reviewed

records

which verified

the

angular

measurement

marks

and side drill hole location

on rompas

block S/N TVA-4.

Comparisons

had

been

made

between

rompas

block

S/N 6028-83

which

had

a

certificate of compliance

from the vendor

and

rompas

block S/N TVA-4

which'as

manufactured

by

TVA and

found to

be within tolerance.

The inspector

also verified that

TVA had

a certificate of. compliance for each

rompas block

used in the ISI program.

(Closed)

IFI 259,

260,

296/85-18-03,

gualification Records

for Inservice

Inspection

Personnel.

This

item dealt with an inspector's

concern

that

TVA's ISI division uses

a computer printout for maintaining of ISI examiners

certification in lieu of having

each

examiners

qualification folder at

a

specific site. 'VA's position for using

a 'computer printout in lieu of

personnel

qualification folders

was

based

on the required mobility of their

examiners.

An examiner

may

be required to go to several different sites

in

one

week

because

of

a certification specialty.

This creates

significant

problems

administratively in maintaining certification folders current at

each

site.

TVA proposed

to

keep

the official folder at the

Sequoyah

Training Center.

The training center would notify the supervisor of the ISI

division of a change

in an examiner certification utilizing a

TVA Form 1453

(PD-11-83).

The ISI division supervisor will be responsible

for maintaining

. the printout current

and for ensuring that each site gets

a current printout

monthly.

The printout will indicate

each

examiners

certification,

any

limitation to that certification,

date certification expires

and date

eye

re-examination

is

due.

TVA's method for ensuring

that fully certified

examiners

are

used for ISI examinations

appears

adequate

and this item is

considered

closed.

Within the areas

examined,

no violation or deviation

was identified.