REGULATORY INF', ATION DISTRIBUTION 'SYSTEM iRIDS)
ACCESSION NBR o 85030 l0085" DOC ~ DATE! 85/02/26 NOTARIZED! YES DOCKET' FACIL:50-259 Browns Ferry Nuclear Power Stationi Unit ip Tennessee 05000259 AUTH,NAME AUTHOR AFFILIATION DOMERiJ ~ AD Tennessee Valley Authority REC IP ~ NAME~
RECIPIENT AFFILIATION DENTON,H,R.
Office of Nuclear Reactor Regulationr Director
SUBJECT:
Advises that 850111 requested for extension of deadline to 8501130 for compliance w/10CFR50
~ 09 re electrical equipment environ qua'lification withdrawn'xtension modified to allow operati'on until 850712, DISTRIBUTION CODE!
A048D COPIES RECEIVED LTR
" ENCL SIZE'o '
TITLE: OR/Licensing Submittal!
Equipment Qualification NOTES:NMSS/FCAF
- 1cy, 1cy NMSS/FCAF/PM'L;06/26/73 05000259 RECIPIENT ID CODE/NAME NRR ORB2 BC 12 INTERNAL: ACRS 15 ELD/HDS4 12 GC 13 NRR/DE/EQB 07 NRA/DSI/AEB RGN2 COPIES LTTR ENCL 8
1
.2 1
1 RECIPIENT'D CODE/NAME CLARKgR 01 ADM/LFMB ELD SHIELDS g H NRR KARSCHiR Nfff&&L R
14 oz COPIES L'TTR ENCL' 1
1 1
1 EXTERNAL: LPDR NSIC NOTES; 03 05 NRC PDR 02 TOTAL NUMBER OF COPIES REQUIRED:
LTTR 26 ENCL
p u
It t
TENNESSEE VALLEYAUTHORITY CHATTANOOGA, TENNESSEE 37401 400 Chestnut Str eet Tower II Febr uary 26, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washingt;on, D.C.
20555
Dear Mr. Denton:
In the Matter of the Tennessee Valley Authority Docket Nos. 50-259 By my letter to you dated January 11,
- 1985, we submitted a request for extension of the deadline for compliance with 10 CFR 50.49, electrical equipment environmental qualification, for Browns Ferry Nuclear Plant.
That request was to extend the deadline to November 30, 1985 for units 1, 2, and 3.
This letter provides clarification of our request for extension for unit 1.
Unit 1 is currently scheduled to shut down to start its cycle 6 refueling outage on June 1,
1985.
Because of possible unplanned trips on unit 1 or extensions in the unit 2 outage, it may be advantageous to operate unit 1 past June 1.
To provide this needed schedular flexibility, we requested that the extension on unit 1 be granted to November 30, 1985.
As discussed in a February 6,
1985 meeting with your staff on the Browns Ferry Integrated
- Schedule, the extension is not needed to November 30, 1985.
By this letter we hereby modify our extension r equest for unit 1 to allow operation to July 12, 1985 instead of November 30, 1985.
This shutdown date is consistent with that specified in TVA letter from J.
W. Hufham to you dated February 22, 1985 regarding the unit 1 Appendix J extension request.
If you have any questions, please get in touch with us through the Browns Ferry Project Manager.
Very truly yours, TENNESSE VALLEY AUTHORITY
,; 'Subscribed
'an( sworn to ef e
me this
.~ day of J.
A. Domer Nuclear Engineer 1985.
Notary Public My Commission Expires co:
See page 2
S5OSOa0085 85022m PDR ADOCK 05000259 P
PDR An Equal Opportunity Employer
~
~ k C'
Mr. Harold R. Denton February 26, 1985 cc:
U.S. Nuclear Regulatory Commission Region II ATTN:
Dr. J. Nelson Grace, Regional Administrator 101 Marietta Street, NN, Suite 2900 Atlanta, Georgia 30323 Mr. R. J. Clark Browns Ferry Project Manager U.S. Nuclear Regulatory Commission 7920 Norfolk Avenue
- Bethesda, Maryland 20814