ML18026A309

From kanterella
Jump to navigation Jump to search
Final Deficiency Rept Re Electrical Cable Damaged During Pulling Operations.Serviceability of Installed Cables Will Be Achieved by Compliance W/Field Procedure FP-E-5 During Const Phases.Supporting Documentation Encl
ML18026A309
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 09/29/1980
From: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
10CFR-050.55E, 10CFR-50.55E, ER-100450, ER-100508, PLA-546, NUDOCS 8010070300
Download: ML18026A309 (20)


Text

Z

~S>

REGULA TQ INFQR.'}AT ION 0 ISTRI BUT ION TE~

(R IDS)

ACCESSION NBR:80 10070300 DQC ~ DATEo 80/09/29 IVOTARIZED: ivQ DOCKET FACIL:50 387 Susquehanna Steam Electric Stationi Unit

}R Pennsylva 050 50-388 Susquehanna Steam Electric Stationi unit 2p Pennsylva 00 8

AUTH,NAWE AUTHOR AFFILIATIQN CURTISRIV,n, Pennsylvania Po~er R Light Co.

REC IP ~ iVAHE RECIPIENT AFFILIATION GRIERPB ~ H ~

Region

}E Philadelphian Office of the i)irector SUBJECl': Final deficiency pulling ooeration achieved oy compl phase,Suooorting DISTPIBUTION CODE:

801'9S TITLE: Construction Defici reot re electrical cable damaged during s+Servicibility of installea cables will be iance w/Field Procedure FP E-5 ouring const documentation encl'OPIES RECEIVED:LTR j. E'iCI. j.

SIZE: gg ency Report (10CFR50.55E)

NOTES:Send ILE 3 cooies FSAR 8 all

amends, 05000387 05000388 RECIP IEV T ID CODE/ VA!4IE ACTION:

A/0 LICENSNG 04 RUSHBROOKiA ~

Oo COPIES LTTR ENCL 1

1 1

1 RECIPIENT ID CODE/NA'iIlE YOUNGBLQOOiB 05 STARKeR ~

07 COPIES LTTR ENCL 1

1 1

INTERNAL: AO/RC I/IE ASLBP/J ~ HARD EOQ 4

STAFF HYD/GEQ 8R I.IC QUAI, BR NRC PDR P

T REV EG FI OS DEV 17 19 22 12 02 13 01 21 AEOO 18 D/DIR HU.I FAC}5 EQUIP QUAL 8R I4} E 09 HPA 20 QELO 21 QA BR 14 RUTHERFQRDPW ~ IE 1 1 1 1 1 1 2 2 1 1 1 1 1 1 1 1 EXTERNAL: ACRS NSIC 16 16 16 08 1 1 LPOR 03 1 1 I @~ "8580 % ~ ~ TOTAl NU4lBER OF COPIES REQUIRED: L T TR 40 ENCL 40

TWO NORTH NINTH STREET, ALLENTOWN, PA. 18101 PHONE: (215) 821-SIS I NOIIMANW. CURTIS Vice Prestcent-Engtneenng 8 Ccnstrecttcn.attctear 821-5381 September 29, 1980 Mr. Boyce H. Grier Director, Region I U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 SUSQUEHANNA STEAM ELECTRIC STATION FINAL REPORT OF A DEFICIENCY'ELATING TO CABLE DAMAGED DURING PULLING OPERATIONS ERs 100450/100508 FILE 840-4/900-10 PLA-546

Reference:

PLA-383 dated July 17, 1979

Dear Mr. Grier:

This letter serves to provide the Commission with a final report of a deficiency relating to electiical cable damaged during pulling operations. The condition was originally reported in the above referenced letter. The informa-tion contained herein is submitted in compliance to the provisions of 10CFR50.55(e). Attachment (1) to this letter contains the problem description, possible causes and safety implications alon'g with our corrective action plan. Attachment (2) consists of a tabulation of cables that failed megger testing subsequent to cable pulling operations. Attachment (3) tabulates cables considered to have sustained damage during the pulling operation and delineates the nature of the damage along with the dispo-sition of each Nonconformance Report generated. We trust the Commission will find the information forwarded by this letter to be satisfactory. Very truly yours, yg/V 5 N. W. Curtis Vice President-Engineering & Construction-Nuclear Attachment s FLW:mcb PENNSYLVANIA POWER 8 LIGHT COMPANY ~OXOOY 0300

Mr. Boyce H. Grier September 29, 1980 cc: Mr. Victor Stello (15) Director-Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Mr. G. McDonald, Director Office of Management Information & Program Control U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Mr. Robert M. Gallo U. S. Nuclear Regulatory Commission P. 0. Box 52 Shickshinny, Pennsylvania 18655

Attachment '. to PLA"546 CABLE DAMAGE SUSTAINED DURING PULLING OPERATIONS On June 15,

1979, MCAR 1-35 reported that severe cable damage resulted from pulling cable through conduit at Susquehanna SES Unit 1.

The concern expressed in the MCAR was whether all damaged cables will be identified by megger tests when the suspect cables are routed through PVC conduit in which ground conductors are not required for the cable installation. The MCAR indicated that cable damage was detected by "visual inspec-tion of the cable jacket or by megger tests" during normal QC inspection activities and cable pulling operations, and was documented on Non-Conformance Reports (NCR's) attached to the MCAR. As indicated in the NCR's, the cable damage includes: cable with cut/ tom outer jacket, cut/tom conductor insulation and/or broken conductor standing. It also includes cable which failed the megger tests. Cause: Based on several investigations made at the jobsite during the week of June 18,

1979, and subsequently, and a review of the relevant NCR's, it has been determined that the cable damage resulted from one or a combination of the factors listed below:

1. Too many bends between pull points. 2. Too small bending radius some 90 elbows. 3. Lack of adequate as-built data on which calculations could be based. The type of cable pulling compounds used. 5. Use of two conductor "flat" cable (Type D12). 6. Mixing of large and small diameter cables in the same conduit. 7. Combining cables of differing length and destination in the same conduit. 8. Use of small diameter single conductor cable in long and complex raceway installations (particularly Type Dll). Anal sis of Safety Im lications: The reported cable damage was found during cable pulling operations and QC inspection activities. The damage was documented on Non-Conformance Reports (NCR's) per Bechtel procedures.

A revie~ of NCR's identified by the Field, and issued between ll/14/78 and 6/6/80, indicates the following: 1. PP&L has considered two (2) categories of Class lE cable damage from the NCR's identified as being reportable under 10CFR50.55(e). These categories are addressed in detail in Tables I and II (Attachments 2 and 3 to this report). and are summarized below: a) Table I lists the NCR's which reported the cables that failed the megger tests. o Total scheme cables listed in Table I..................49 o Number of scheme cables dispositioned to reject and rework.............................................40 o Number of cables dispositioned to be acceptable.........7 o Number of cables with no damage detected and have since passed a megger test..............................2 Of the 40 scheme cables rejected, 26 were type Dll. b) Table II lists the NCR's which reported the cables that were damaged during pulling. o Total of scheme cables listed in Table II..............65 o Number of scheme cables dispositioned to reject and rework......................................43 o Number of cables dispositioned to be acceptable.............................................22 Seven of the 43 rejected cables were type Dll which failed the megger test. 2. Tables I and II (Paragraph 1-a and 1-b above) indicate that there were 114 scheme cables reported in the NCR's. NCR disposition indicates that 29 of these cables have been verified to be acceptable. In addition, there were 2 cables which have passed the megger tests with no damage detected. These cables were dispositioned for a re-megger test at a higher value (see NCR-5424). The remaining 83 cables were dispositioned to reject and rework. 3. Approximately one half of the damaged scheme cables were detected visually with the remaining ones discovered through megger tests and rejected. 4. Of the 83 damaged scheme cables rejected, approximately 80% occurred on 600 V Power and Control Cable, f!2AViG and smaller, manufactured by AIM Corporation. 5. The nature of the cable damage was varied, and the cause of the damage could not be attributed to one single factor. 6. Raychem is the only supplier of cable that 'did not exhibit cable damage or overtensioning. 7. Based on the May, 1980 circuit schedule, more than 4,800 safety-related scheme cables are shown as pulled.

The data above indicates that the rate of 1/C 810 megger test failure is higher than for the other cable types. Review of documents indicates that this is the smallest and weakest cable used in the SSES Project. It also indicates that this cable is one of the cables most commonly used in both the 480 V and 120 V power and control cabling system.

Hence, this cable is the most susceptible to damage, especially in long, complex raceway system.

To prevent and/or minimize this type of cable damage in the future, steps have been taken as reported in the next section. Low voltage megger tests are performed on all power cables to locate direct short-circuits and to facilitate the pre-operational, functional testing and startup procedures. NPE has determined the cable damage identified in this NCAR 1-35 to be reportable under 10 CFR 50.55(e). Corrective Action: The adequacy of the project cabling system will have been assured when all integrated startup procedures, including pre-operational and functional testing planned and scheduled for the future, are successfully completed. During the construction phase of a project, the servicibility of the installed (pulled) cables can be achieved by compliance with the following procedures, which are in Field Procedure FP-E-5: 1. Visual inspection of raceways to ensure the removal of burrs and other foreign material that may be damaging to the cable (Field Procedure FP-E-5, Paragraph 7.1.5 and 7.1.6), 2. Cable pulling operation monitoring to assure proper rigging,

handling, and application of pulling compound to the cable

~ (Field Procedure FP-E-5, Part II, Paragraph 7.7.7 and 7.1.24). 3. Verification of adequate data used for the determination of maximum allowable tensile stress and sidewall pressure (FP-E-5, Part II, Paragraph

7. l. 7).

4. Tensiometer monitoring on machine 'pulls to verify that the maximum allowable tensile stress and sidewall pressure are not exceeded (FP-E-5, Part II, Paragraph 7.1.25). 5. Visual inspection of the cable that has emerged from the race-way at the pulling end for indications of cable damage (FP-E-5, Part II, Paragraph 7.1.25). 6. iMegger testing of 600 V and higher power, cable (9 to 9 and 9 ground) to detect any obvious short circuits that may be present (FP-E-5, Part II, Paragraph 7.1.25). When the cable over-tensioning condition was first reported by the field, Project Engineering determined that several options were available for the resolution of the problem, and evaluated each one of these options on an individual basis*. It was determined that the most viable option was to have the cable manufacturers justify and permit the use of an increased

maximum allowable tension value. To accomplish this, and at the advice of the cable manufacturer, a cable test plan was implemented at the jobsite. This would enable the cable manufacturers to provide justification for the increased maximum allowable tension values. Upon completion of the tension tests, the tested cables were sub-jected to a series of physical and electrical tests by the respective cable manufacturers. Based on the results of these tests, the manufacturers revised their data previously submitted and increased the maximum allowable pulling tensions for their cables. Accordingly, these increased allowable tensions were incorporated into Drawing E-59. (

REFERENCE:

Okonite.,Report dated Hay 10,

1979, Document Control Number 103968 and AIW Reports, Vendor Document Number 8856-E-130-A166(1)-1 dated 2/7/80 and -166(2)-1 dated 2/5/80).

Based on the revised values of maximum allowable pulling tensions, the Field has implemented Appendix B of the interim Response to this

HCAR, which outlined the procedures for the verification of cables installed prior to the June 14, 1979 work stoppage.

As a result of the verification program, the Field reported that there was no new Class 1E cables identified to be overtensioned. Fo'r Unit 1 and Common, Project Engineering has reviewed the use of small single conductor cable and two conductor "flat" cable for pulls yet to be made. Where deemed appropriate, consi'dering the complexity of the pull and raceway percent fill, such cables are being replaced with either a larger size conductor or a round multiconductor cable to facilitate'cable pulling. En addition, two conduct'or round cables have been added to the Purchase order. These cables are intended for limited use on difficult pulls. This procedure is also implemented for Unit 2. Project Engineering has begun a review of the more complex conduit networks for Unit 2 and, where appropriate, will modify the raceway design to facilitate cable pulling. Appropriate action has been taken by the Field to ensure that procedures established for, the cable pulling operations are followed for every cable pull. (See Bechtel Construction letter to PP&L Construction BCLPC-6374 dated July 12, 1979). The Field will continue to monitor every cable pull and document any cable damage and overtensioning. A sampling plan for meggering of multi-conductor control cable of flat-configurat'on and single conductor control cable !P8 and smaller has been aporoved by PP&L as per PCLBC-3181 dated 12/6/79 (Document Control Number 114820). The sampling plan, which covers both the installed control cables and future control cable'nstallation, has been implemented by the Field. As a result of this program, the Field reported in BCLPC-7743 dated 5/21/80 (Document Control Number 119795) to PP&L Construction that no failures were found on the sampling of Class 1E cables installed prior to the stop work date. En addition, a testing program has been implemented to test all Dll

(1/C f10 AWG) cable presently installed 9 Susquehanna SES. It consists of a DC megger at voltages up to 5 KV DC on all Q as well as non+ cable. The acceptance criteria will be 1000 megohm minimum resistance. All cable which fails thi.s criteria will be tagged for replacement or abandonment.

== Conclusions:== 1. Some safety-related cables were damaged during normal scheduled cable pulling activities. This damage was discovered and documented on NCRs during QC inspections. 2. The cause of the cable damage was one or more of the factors 1'sted under "Causes". The nature of the cable damage was varied, and was described in the referenced NCR's. Where overtension had originally been identified as a deficiency, new analyses by cable manufacturers showed that the original maximum sidewall pressures were conservative; therefore, .these original over-tension deficiencies, when rechecked, were all found to be acceptable under the revised maximum pulling tensions. 3. The mixing of large and small diameter cables in the same raceway and the use of 2/c cable in a flat configuration on both long and/or complex pulls will be avoided, wherever possible, in the Euture as a result of the corrective measures being implemented by both Project Engineering and Construc-tion. 4. Megger testing is in the construction procedures and will continue to be employed in the Euture. 5. As cable damage was discovered, it was documented through the QA Program. 6. The Fi'eld completed the implementation of Appendix B of the Interim

Response

to this MCAR, which outlined the procedures for the verification of cables installed prior to June 14, 1979 work stoppage. Based on the revised values of maximum allowable pulling tensions shown in Drawing E-59, the Field reported that there was no new Class lE cables identified to be overtensioned. 7. The project Field QC has been monitoring the Construction activities to ensure that procedures established Eor the installation of cables are followed. 8. Through the action taken and the testing programs implemented as outlined in the section entitled "Corrective Action", NPE believes the cable pulling problems have been satisfactorily resolved.

Attachment 2 Page 1 TABLE 1 Cables That Failed the Hegger Tes ts NCR Ho. (Date) 3749 (4/2O/79) 3871 (5/14/79) Scheme Cable Ho. PP18050111 CP 1D0019R Size 1/C-4/0 2-1/CII2 Cable Code ~(Hf.) R04(okonite) D21(AIW) NCR Dis osition Reject & rework HCR closed. Reject & rework Per FCR-1435. HCR closed. Remark 3896 (5/17/79) CP1D0019C 1/C810 D11(AIW) Reject & rework. 3897 3944 (5/25/79) 3964 (5/31/79) CP1D0020K APID0016H FP1V16018 BP1D0018N BP1D0017H CP1D0019U FPlQ40058 FP1Q40078 FP1V2522A FP1Q4005A FP1Q4007A BP1DOO17L 1/C810 1/C810 2-1/C82 2-1/C86 2-1/C810 2-1/C82 1-1/C810 1-1/C010 3/C810 4-1/C86 4-1/C82 2-1/CfI1O Dll(AIW) Dll(AIW) D21(AIW) D61(AIW) Dll(AIW) D21(AIW) Dll(AIW) Dll(AIW) D13(AIW) D61(AIW) D21(AIW) Dll(AIW) Remegger with cable ends disconnected cleaned. Cable passed megger test. NCR closed. Reject & repull. Reject & repull. HCR closed. Reject & rework. NCR closed. This cable was dispositioned to reject per NCR-4657

TABLE 1 Cables That Failed the He ger Tests Page 2 HCR No. (Date) 3949 (5/29/~9) 3992 (6/11/79) 4036 (6/15/79) 4085 (6/27/79) 4112 (6/29/79) 4114 (6/29/79) 4129 (7/3/79) 4130 (7/3/79) Scheme Cable No. BPOG4027A BPOG4028A EP1V2522A CP]D0020G EPIB0501K BPID0018K Bpln0017C BP1D0018G EP1$ 1311A EPlg1323A Size 3/C810 3/C810 3/C810 2-1/C810 1/C-4/0 2-1/C810 1/C810 2-1/C810 5-1/C810 5-1/C810 Cable Code ~(HE.) D13(AIW) D13(AIW) D13(AIW) Dll(AIW) R04(Okonite) Dll(AIW) Dll(AIW) D11(AI'W) Dll(AIW) Dll(AIW) HCR Dis osition Remeggered with cable ends disconnected cleaned. Cable passed megger test. NCR closed. Reject & rework. Per FCR-1435 Reject & rework. NCR closed. Reject & rework. HCR closed. Reject & rework. NCR closed. Reject & rework. HCR closed. Passed remegger test with cable ends dis-connected & cleaned. HCR closed. Re3ect & rework. HCR closed.. Remark

TABLE 1 Cables That Failed the Megger Tests Page 3 NCR No. (Date) 4612 (10/1/79) 4657 (10/8/79) 4682 (10/15/79) 4717 (10/19/79) 5027 (12/18/79) 5276 (2/6/80) Scheme Cable No. FP1V1601B BP1D0017L FPlV4511B RPlV4501B CK1D0019B EPlQ1305A EPlQ4029A EP1Q1304A EP1Q1308A EPlQ1312A EP1Q1311A EPlQ1307A Size 2.-1/CN2 2-1/CN10 3/CH 8 3/CN8 2-1/CN10 S-1/CN10 Cable Code (Mf.) D21 (AIH) Dll(AIH) D83(AIH) D83 (AIR) Dll(AIH) Dll(AIH) NCR Disposition Reject & rework. NCR closed. Reject & rework. NCR closed. Reject & rework. NCR closed. Reject & rework. NCR closed. Reject & rework. NCR closed. Reject & rework. NCR closed. Remark Disposition of this cable was per NCR-3964 5378 (2/26/80) 4128 (7/3/79) APlD0016H APlD0016V AP1D0015V DP1D0022K 2-1/CN10 2-1/CN10 Dll(AIH) Dll(AIH) Reject & rework NCR closed. cfianginj to 5$ code Reject & rework NCR open.

TABLE 1 Page 4 Cables That Failed the Hegger Tests NCR No. (Date) Scheme Cable No. Size Cable Code (HPG. ) NCB Dis osition Remark 5455 (3/12/80) 5599 (4/1/80) 5922 (5/29/80) BP 1 D001 BG DV200022K DP200021C 2-1/C810 2-1/C810 2-1/C810 Dll(AIW) Dll(AIW) Dll(AIW) Bemegger with cable ends disconnected f cleaned. Use as is, Reject 6 rework. Reject 6 rework. NCR closed. PHASE A shouted. NCR open. NCR open. 5959 (6/3/80) 5424 (3/4/00) PKlA4104A Ppln0006C Ppln0006U 7/C814 2~1/C075-HCH LO7 (AIW) B75(Okonite) Bemegger with cable ends disconnected and cleaned. Cable-acceptable. Berne@ger wz Lh ~ 1 QQQY pall)e NCR closed. )lO damage

reported, NCR open,

/I 4932 (12/1/79) AMl()0701 L'PR-16(T/C) TQ5 (Samuel Moore)

Rework, remegger 6

spare. Reroute new cable. NCR closed. Was on Table 1I. Ill(ll98020 1PR-16 $24(Samuel. Moore)

Attachment 3 Page 1 TABLE II Cable Damage Sustained During Pulling NCR No. (Date) Scheme Cable No. Size Cable Code (ttfg. ) Nature of Cable Damage NCR Dis osition Remark 3295 (12/28/78) FP180504L 3-1/C500HCM R50(Okonite) Overtension Reject 6 rework. NCR closed.. Note 1 3365 (1/24/79) FP180504N FP180504L 1-1/C-4/0 R04(Okonite) 3-1/C-500MCH R50(Okonite) None (Note 2) Use as is. NCR closed. FP180504N 1/C-4/0 R04(Okonite) 3470 (1/24/79) EP180503L EP180503N 1/C-4/0 R04(Okonite) 3-1/C-SOOMCH R50(Okonite) Cables over-tension 6 was too short. Reject 6 rework. NCR closed. 3515 (3/1/79) PP180501H 3-1/C-500MCH R50 (Okonite) New calculation using as-built data indicates no overtension. Review Calc. Cable acceptable. NCR closed. 3580 (3/16/79) FP)D000'6U 2-1/C-75QHCM, R75(Okonit:e) Oyegtensiqn Reject s rework, NCB, closed, (Tension allowable is 10QO. lbs, using the Basket Grip Method,) Notes: 1. Cable was reported t:o be overtensioned and replaced, Field disposition of the NCR, indicates, that; the actual tension was within the allowable cable tensile strength of 300Q lbs. Later, testing by Qkonite also shows that the act:ual tension was within the new allowable tension determined by Okonj.te,

TABLE II Page 2 Cable Damage Sustained During Pulling NCR No. (Date) Scheme Cable No. Size Cable Code (Hfg. ) Nature of Cable Dama e NCR Disposition Remark 3581 (3/16/79) FPlD0006C 2-1/C-750HCH R75(Okonite) Overtension. Reject 6 rework. NCR closed. 3667 PPlB0501H 3-1/C-500MCH (4/2/79) R50(Okonite) None Use as is. NCR closed. Note 2 3783 (5/1/79) 3807 (5/2/79) 3887 (5/17/79) AP2D0001A 3/CN2 AKOG2001C 12/CN14 FKOV5106D 7/CN14 FKOV5108D FKlV5501D D23(AIW) L12(AIW) LO7 (AIW) Two tears on the outer jacket. Reject 6 rework. NCR closed. Cable broke. Reject 6 rework. NCR closed. A cut through Reject 6 rework. the outer jacket. NCR closed. votes: 2. Actual tension was within the new allowable tension determined by Okonite.

TABLE II Page 3 Cable Damage Sustained During Pulling NCR No. (Date) Scheme Cable No. Size Cable Code (HPG.) Nature of Cable Dama e NCR Disposition Remark 3097 (5/18/79) EPlD0016S l-l/C52 APlD0015H AP1D0015L AP1D0016K l-l/CN10 1-1/CH10 2-1/CN 10 AP1D0015C 1-1/CN10 EP1D0015N 1-1/CN10 D21(AIH) Dll(AIH) Stress tears a holes on outer jacket. Conductor ex-posed. Stress tears 6 holes on outer jacket. One cond. exposed Stress tears and holes on outer jacket. Reject a rework. NCR closed. Note 3 3965 (6/1/79) 4001 (6/12/79) RKlQ0302D 7/C514 RK2Q7002D 2/C514 RK2Q7002D KKOQ7004C LO7(AIW) L02 (AIH) A cut in insula-tion. Some conductor damage. Overtension Reject 6 rework. NCR closed. Reject 6 rework. NCR closed. Notes: 3. Cable tension exceeded the allowable limit for using the basket grip method. As a result, six (6) cables have stress tears and holes through their outer jackets. This includes four (4) cables that were tom with conductors exposed. The seventh cable (APlD0016H) failed the megger test.

TABLE-II Page 4 Cable Damage Sustained During Pulling NCR No. (Date) Scheme Cable No. Size Cable Code (Hfg. ) Nature of Cable Damage NCR Dis ositiai Remark 4001 (6/12/79) BKOG2010D 7/CN14 L07 (AIH) Overtension. Reject 6 rework. NCR closed. BKOQ6004C BKOG2402E BKOG2402P BK2A0413C KKOQ7008C 2/CN14 3/CN14 4/CN10 5/CN14 2/CN14 L02(AIH) L03 (AIH) D14 (AIW) L05 (AIW) L02(AIH) Overtension. Conductors separated. 4003 (6/13/79) 4120 (7/3/79) CKOG0304R CKOS0409G CKOG0305K 12/CN 14 2/CN 14 7/CN14 LKOG2403N 2/CN14 RK2Q7002C 2/CN14 CKOS0417tt 2/CN14 CKOS0400G 2/CN14 CKOG0305tt 2/CN14 L02 (AIW) L02(AIW) L02 (AIW) L02(AIH) L12 (AIH) L02 (AIH) L07 (AIW) L02(AIW) Cut broken by Efcor type bushing. Damaged during hand pull I'I A cut 5 a nick on insulation, Damaged by a falling vent duct, Reject 6 rework, NCR closed. Reject 6 rework, QCR, closed, II 4497 (9/10/79) 4611 (9/26/79) AKOG0300Z 5/CN14 EPlgl314A l-l/CN10 L05(AIW) D11(AIW) A cut through the out:er jacket and into the insulation, Reject t'ework., NCR closed, A spare conductor Repair. spare conductor was damaged (orange) NCR closed,

TABLE II Page 5 Cable Damage Sustained During Pullin NCR Ho. (DATE) Scheme Cable No. Size Cable Code (Hfg.) Nature of Cable Damage NCR Remark 4794 (11/1/79) PFiv2600A 2-1/CN4/0 F04(Kerite) Deep Hicks Reject 6 rework, NCR closed, 4857 4861 (11/14/79) AP280501N AP280501L CP280503G 1-4/OAHG 1-500MCH 3-1/C-500HCH RQ4(Okonite) R50(Okonite) R50(Okonite) . Cuts in jacket, a (Note 4) BP280502L 3-1/C-50QHCH R50(Okonite) (Note 5) BP280502N l-l/C-4/10 R04 (Okonite) Use as is, II "Use as is, Cable passed the megger test, NCR closed. II 4902 (11/26/79) 4932 (12/1/79) EKlV2520n 2/CN14 JHl()0708H 1PR-16(T/C) LO2 (AIM) A cut on cable. Reject 6 rework, T()5(Samuel Hoore) Cable Broken

Rework, remegger a
spare, Reroute new
cable, NCR open, Notes:

4. Indentation on the outer jacket was reported to be caused by means used to secure cable coiled in a J-box. 5. Indentation on the outer jacket was reported to be a result when the cable was run oyer by a wheelbarrow. The cable was laying on the floor for pulling.

TABLE II Page 6 Cable Damage Sustained During Pullinq HCR Ho.- (Date) Scheme Cable Ho. Size Cable Code Hfg. Nature of Cable Dama e NCR Dis osition Remark 4939 (12/4/79) 5085 (1/4/80) 5097 (1/8/80) NCR closed. DKlQ3003C 12/CI14 L12 (AIW) (Note 6) Reject 6 rework. DKlQ3003C 12/CI14 .L12(AIW) Cable was crimped. Use as is. Passed megger test. (Documented and dispositioned on HCR-4611 dated 9/26/79) 5276 5355 (2/21/80) EPIQ4029A 5-1/CI 10 FPlQ4004A 4-1/CI6 Dll(AIW) D61(AIW) A cut to the conductor. Reject a rework. NCR closed. Cut in insulation. Reject 6 rework. 5415 EP1Y0005A 1-3/CI2 D23(AIW) Reject. 5450 (3/12/80) EHOI1101D EMOI1101E EMlSP00l4 EHlSP0015 EHlSP0016 EHlSP0017 PHOI1201D PHOI1201E 1PRI16 1PRI 16 7PRI16 3TR016 3PR516 3TR816 1PRI16 1PRN16 Q24(Samuel Hoore) No damage Use as is. reported.(Note 7) NCR closed. Q24 Q27 Q29 Q26 Q29 Q24 Q24 Nooos: / was discovered, The NCR reported that the damage appears to be caused by a heavy falling object. About 1 1/2" of the cable was flattened. 7. Tension calculations which includes the drain wires indicates that the actual t:ension (1000 lbs.) is within t:he maximum allowable tension.

TABLE II Page 7 Cable Damage Sustained During Pullin NCR No. (Date) Scheme Cable No. Size Cable Code (Mfg.) Nature of Cable Dama e NCR Dis osition Remark 5491 (3/19/80) FMOI7505K 3PR$ 16 FMOI7802F 3PRgl6 I Q26(Samuel Moore) Cable was crimped. Use as is. Passed continuity test. Cable with jacket inconsistency. 5723 (4/18/80) FK1Q0616C 7/CH14 L07 (AIW) Wire 522F has nicks in insul-ation. Repair with Raychem lfeat Shrink kit.}}