ML18025B470

From kanterella
Jump to navigation Jump to search
NRR E-mail Capture - (External_Sender) Change in Implementation Period for Columbia LAR to Adopt TSTF-523
ML18025B470
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/24/2018
From: Linda Williams
Energy Northwest
To: John Klos
Plant Licensing Branch IV
References
Download: ML18025B470 (2)


Text

1 NRR-DMPSPEm Resource From:

Williams, Lisa L. <llwilliams@energy-northwest.com>

Sent:

Wednesday, January 24, 2018 11:35 AM To:

Klos, John

Subject:

[External_Sender] Change in implementation period for Columbia LAR to adopt TSTF-523 Follow Up Flag:

Follow up Flag Status:

Flagged

John, In Energy Northwests license amendment request to adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, approval was requested within one year of the date of submittal with the amendment being implemented within 60 days thereafter. Energy Northwest desires to modify the implementation period from 60 days to 90 days in light of the expected NRC approval of the amendment prior to the one year timeframe. This timeframe will ensure the amendment can be implemented as planned. Thanks, Lisa Lisa L. Williams Energy Northwest Licensing Supervisor 509.377.8148

Hearing Identifier:

NRR_DMPS Email Number:

132 Mail Envelope Properties (e6586eb9f94e4c0f901cf3598ee063e1)

Subject:

[External_Sender] Change in implementation period for Columbia LAR to adopt TSTF-523 Sent Date:

1/24/2018 11:35:06 AM Received Date:

1/24/2018 11:35:14 AM From:

Williams, Lisa L.

Created By:

llwilliams@energy-northwest.com Recipients:

"Klos, John" <John.Klos@nrc.gov>

Tracking Status: None Post Office:

SERVER250.domain1.energy-northwest.com Files Size Date & Time MESSAGE 596 1/24/2018 11:35:14 AM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

Follow up