ML18017A098
| ML18017A098 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna |
| Issue date: | 03/24/1980 |
| From: | Curtis N PENNSYLVANIA POWER & LIGHT CO. |
| To: | |
| References | |
| NUDOCS 8003310136 | |
| Download: ML18017A098 (2) | |
Text
TWO NORTH NINTH STREET, ALLENTOWN, PA.
18101 PHONE: (2'I5) 821.5151 NORMAN W. CURTIS Vice President. Engineering 8 Construction 821-5381 March 24, 1980 Mr. Boyce H. Grier Director, Region X
U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 SUSQUEHANNA STEAM ELECTRXC STATION INTERIM REPORT OF A DEFICIENCY IN PIPE SUPPORT DESIGN DRAWINGS RELEASED FOR FABRXCATION AND XNSTALLATION STATUS UPDATE ERs 100450/100508 FILE 840-4 PLA-462
Reference:
PLA-391, September 5,
1979
Dear Mr. Grier:
As'reported in the above referenced letter, Bechtel engineering has been conducting an ongoing review of pipe support design documents to cover all
- force, momerit calculations and their related pipe support details.
The Unit 1 verification program for the twenty-six (26) Reactor Pressure Vessel filland flush systems is basically complete with the exception of several isometrics that are on hold.
The Unit 1 program is scheduled for completion in April, 1980.
The Unit 2 verification program does not appear as extensive as Unit 1 and, consequently, is expected to be fully completed by June, 1980.
Progress in completing these activities has been slower than anticipated.
Delays in the completion of the overall verification program can be attributed to the increased scope of the evaluation program, unavailability of manpower, and our initial underestimation of the effort which has been and continues to be required.
Our latest projection for the completion and submittal of a final report is late July, 1980.
/
go/ 7 56 I/c PENNSYLVANIA POWER 8
LIGHT COMPANY 8IIOS SZOlgg
Mr. Boyce H. Grier March 24, 1980 We will keep the Commission advised of further developments as they occur.
Very truly yours, N.
W. Curtis Vice President-Engineering 6 Construction ARS:mcb cc:
Mr. Victor Stello (15)
Director-Office of.Inspection R Enforcement U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Mr. G. McDonald, Director Office of Management Information 6 Program Control U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Mr. Robert M. Gallo U. S. Nuclear Regulatory Commission P.
O. Box 52 Shickshinny, Pennsylvania 18655