NRC-010 - Staff Presentation Slides - Overview (Jan. 16, 2018)
ML18016B074
Person / Time
Site: Northwest Medical Isotopes
Issue date: 01/16/2018
From:
NRC/OGC
To:
NRC/OCM
SECY RAS
References
50-609-CP, Construction Permit Mndtry Hrg, RAS 54173
Download: ML18016B074 (18)


Text

NRC-010 Northwest Medical Isotopes Construction Permit Application Review

  • Mandatory Hearing (Overview Panel)
  • January 23, 2018

Panelists

- Deputy Director for Reactor Safety Programs and Mission Support, NRR

  • MaryJane Ross-Lee

- Deputy Director, NRR/DLP

- Deputy Director, NRR/DMLR

- Deputy Director, NMSS/FCSE 2

99Mo Overview

  • 99Mo decays to 99mTc

- Effective diagnosis

- Minimal exposure

  • 50,000 procedures daily
  • No domestically-produced supply 3

Establishing a Domestic Supply of 99Mo

  • NRC supports U.S. policy objectives to establish domestic 99Mo production
  • First construction permit for domestic 99Mo production issued to SHINE Medical Technologies in 2016
  • Northwest Medical Isotopes would produce 99Mo by processing irradiated low enriched uranium targets 4

Conducting the NWMI Review

  • Review of NWMI application supported by procedural efficiencies and previous licensing experience

- Two-part application submission

- Document templates

- Permit condition supporting quality assurance implementation

  • Staff and contractors spent ~12,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> reviewing NWMI application 5

Authorizing Construction

  • NWMI seeks authorization to construct 10 CFR Part 50 production facility
  • Staff review based on preliminary design and analysis of facility

- Design details may be left for operating license application

- Target fabrication activities to be considered under a 10 CFR Part 70 application 6

Conducting the Safety Review Safety Review ACRS Review Application Commission Submitted to NRC Mandatory Decision Hearing on Permit Environmental Review 7

Tailoring Review Methodology

  • Review accommodated unique aspects of the NWMI application
  • Staff adapted existing guidance for research reactors, production facilities, and fuel cycle facilities
  • Review focused on whether there was reasonable assurance that the final design would conform to design bases 8

Additional Information

  • In response to staff requests, NWMI provided additional information
  • In some cases, permit conditions were necessary to support findings
  • Regulatory commitments track items for resolution in Final Safety Analysis Report 9

Environmental Requirements

  • National Environmental Policy Act

- Informs Federal decision making

- Public disclosure

- NRC regulations implementing the National Environmental Policy Act 1

0

Environmental Review Process Environmental Report Draft Final Environmental Comment Environmental Environmental Site Audit Period

  • Impact Impact Statement Statement Scoping *
  • Opportunity for Public Request for Involvement Additional Information 1

1

Proposed Discovery Ridge Site

  • Agricultural land
  • Previously disturbed
  • No surface water features
  • No threatened or endangered species
  • No historical or cultural resources 1

2

Statutory and Regulatory Basis for Construction Permit Issuance

  • Commission authorized to issue permits by Atomic Energy Act, Section 103

3

Construction Permit Findings

  • Preliminary facility design described
  • Further technical or design information may be left for FSAR
  • Ongoing research and development identified
  • Facility can be constructed and operated without undue risk 1

4

Construction Permit Considerations

  • Construction will not endanger public health and safety
  • NWMI is technically and financially qualified
  • Environmental requirements have been satisfied 1

5

Introducing the Review Panels Panel Number Discussion Topics Evaluation Areas Safety Panel 1 Licensing Safety Evaluation Considerations Report Chapters 1, 4, and 12 Safety Panel 2 Accident Analysis Safety Evaluation Methodology Report Chapter 13 Environmental Panel

  • Final Environmental Final Environmental Impact Statement Impact Statement Process
  • Scope and Connected Actions
  • Analysis of Alternatives 1

6

Acronyms

  • NRR - Office of Nuclear Reactor Regulation
  • DLP - Division of Licensing Projects
  • NMSS - Office of Nuclear Material Safety and Safeguards
  • FCSE - Division of Fuel Cycle Safety, Safeguards, and Environmental Review 1 7

Acronyms

  • 99Mo - molybdenum-99
  • 99mTc - technetium-99m
  • NRC - U.S. Nuclear Regulatory Commission
  • NWMI - Northwest Medical Isotopes
  • CFR - Code of Federal Regulations
  • FSAR - final safety analysis report 1 8